Last night the Zoning Commission voted 5-0 to extend the allowed building height and expand the total square footage of the proposed office building at 250 M Street in what is technically a modification to the Capper/Carrollsburg second-stage PUD that this office building is part of. The building, which will be going for LEED silver certification and which will have ground-floor retail, will now be 130 feet high and have 233,405 square feet of space. The discussions at the hearing centered mainly on the penthouse structure, the "next generation" elevator technology that allows for less overhead space, and how exactly the agreement with ANC 6D should be viewed.
William C. Smith's Brad Fennell testified that the developer has agreed to additional amenities beyond those in the original PUD (which included $325,000 toward the funding of Canal Park). He described the new amenities as "recruiting construction workers from ANC 6D by purchasing quarterly ads in the Southwester, creating an overall goal of 20% first-source employment for qualified ANC 6D residents, and providing contracting and new hiring opportunitiess for local residents and subcontractors by giving tiebreaking preferences to subcontractors headquartered in ANC 6D and for qualified construction workers living in that area." On May 12 the ANC tied 3-3 on the project, but apparently some subsequent tweaking of the proffer into this final form resulted in a letter from the ANC indicating that four commissioners would support the project with these additional amenities. The Zoning Commissioners felt that, since this was not an official vote of the ANC, it couldn't be given the required "great weight," but could be looked at the same as any feedback from a neighborhood association. The fact that no ANC members appeared at the hearing to testify in opposition also was noted.
You can read the Office of Planning report for all the specifics you could ever want about the changes in the design; if you're really interested, you can also read the original second-stage PUD approval of 250 M from last July, that last night's ruling is modifying. (The original Capper PUD is worth a look as well if you aren't familiar with what's been approved for the area's redevelopment.) Also, since I haven't mentioned it lately, it should be noted that this office building is technically a joint venture between WC Smith and the DC Housing Authority, with the monies from it helping to "financially leverage" the rest of the redevelopment of the Cappers.
This was the first vote; final action on this modification will be scheduled for a month or so from now. Earlier this year a WC Smith representative had told me that construction could begin in the middle of this year, but there was no mention of start dates at the hearing.
Comments (0)
   
 
 More About M Street

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

FstSE on Roundup of Some: @king of Arabistan: this is the greystar site currently under construction acros...
king of arabistan on Roundup of Some: So those buildings are planned for the parcel north of DC Water HQ? I guess no m...
bdj on Roundup of Some: It's a connection to Ore 82, I think JD posted about this 6-12 months ago.
202_cyclist on Roundup of Some: FstSE— thank you for posting. It isn’t quite th observation deck at the Willis ...
FstSE on Roundup of Some: Umm.. have we seen this yet? [image]
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1000 B/O 3RD ST SE   ROBBERY  11/21/20
1200 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/19/20
UNIT B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 11/18/20
1000 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/12/20
1100 B/O 2ND PLACE SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 11/12/20
1000 B/O 8TH ST SE   THEFT
Theft First Degree (theft From Building)
 11/12/20
1000 B/O HALF ST SE   THEFT FROM AUTO
Theft (theft Of Motor Vehicle Parts Or Accessories)
 11/10/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/05/20
300 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/05/20
900 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/01/20
UNIT B/O I ST SE   THEFT
Theft First Degree (shoplifting)
 10/31/20
900 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 10/29/20
300 B/O TINGEY ST SE   ROBBERY
Carjacking
 10/29/20
1300 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/28/20
1000 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 10/27/20
300 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/23/20

Recent Issued Building Permits Archive  
1200 1ST ST SE   
11/04/20 
PEPCO / DONNA G GRAHAM
AH2100169 / CONSTRUCTION
WO #16029084 / 02 - 1200 1ST ST SE - PEPCO / WA CHESTER TO REMOVE AND INSTALL CABLES MONDAY THROUGH SATURDAYS FROM 9PM TO 6AM STARTING 11 / 5 / 20 TO 12 / 5 / 20
1018 3RD ST SE   
11/10/20 
DAVID A LEINER / null
E2101357 / SUPPLEMENTAL
1020 3RD ST SE   
10/30/20 
MAYIAK LLC / null
E2101037 / SUPPLEMENTAL
1300 4TH ST SE 1001   
11/03/20 
YAAN REAL ESTATE LP / null
P2100950 / SUPPLEMENTAL
1300 4TH ST SE RU-1   
11/19/20 
AP BOWER RETAIL LLC / null
E2101650 / SUPPLEMENTAL
1057 5TH ST SE   
11/05/20 
PAM HARDER / null
E2101183 / SUPPLEMENTAL
1150 5TH ST SE   
10/28/20 
DISTRICT OF COLUMBIA / null
E2100958 / SUPPLEMENTAL
82 I ST SE   
11/12/20 
STARRY / null
E2101432 / SUPPLEMENTAL
330 K ST SE   
11/09/20 
MINDY J SHAW / CASEY CHARKHABI; NA
B2008664 / CONSTRUCTION
Adding a bathroom on the first floor
   
11/10/20 
JINGSONG XIA / null
P2101107 / SUPPLEMENTAL
100 M ST SE   
10/26/20 
NW 100 M STREET LLC / null
E2100822 / SUPPLEMENTAL
   
11/12/20 
LHREV WASHINGTON M ST LLC / null
P2101170 / SUPPLEMENTAL
   
11/12/20 
SQUARE 743 INC / ;
P2101121 / SUPPLEMENTAL
139 N ST SE   
11/10/20 
BROOKFIELD DEVELOPMENT / JUSTIN BELLOW; BROOKFIELD DEVELOPMENT
B2004436 / CONSTRUCTION
NEW CONSTRUCTION 10-STORY PLUS PENTHOUSE APARTMENT BUILDING WITH 379 UNITS. PROPOSED GROSS FLOOR AREA: 225,000 SF. SH2000028 issued
1275 NEW JERSEY AVE SE   
10/27/20 
BROOKFIELD PROPERTIES / TIM GOOD
AH2100124 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Veterans Day, November 11th, 2020. Operations would include exterior fa¿ade activities such as: exterior framing, glass and glazing, and brick as well as interior mechanical, electrical and plumbing rough-in activities with access limited to N Street. This permit would not include extended work hours beyond the normal...
   
11/04/20 
USA / null
E2101168 / SUPPLEMENTAL
   
11/09/20 
BROOKFIELD PROPERTIES / TIM GOOD
BP2100588 / POST CARD
125 O ST SE   
10/27/20 
DISTRICT OF COLUMBIA / null
M2100294 / SUPPLEMENTAL
71 POTOMAC AVE SE APT 1208   
11/02/20 
null / NA NA NA
EHOP20957167 / HOME OCCUPATION
71 POTOMAC AVE SE   
11/04/20 
RIVERFRONT HOLDINGS II, LLC / null
M2100380 / SUPPLEMENTAL
   
11/04/20 
RIVERFRONT HOLDINGS II, LLC / null
P2100978 / SUPPLEMENTAL
   
11/09/20 
MRP REALTY / null
E2101319 / SUPPLEMENTAL
227 TINGEY ST SE   
11/18/20 
FC 227 LLC / null
E2101630 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.