A proposal will be going before the WMATA board next week to allow the Nationals to lease the Southeastern Bus Garage at Half and M (just across from the about-to-reopen Navy Yard subway station west entrance one block north of the ballpark) and an adjoining surface parking lot just across Van Street. This would happen once the Metrobuses are relocated, which apparently is supposed to be by Friday, March 28.
The lease for the Van Street lot would start the next day, and the garage itself would be available on April 20 (after Metro takes a few weeks to remove equipment). For the first 12 months, the Nats would pay $27,370 a month to lease the garage and $9,500 a month to lease the Van Street lot. If they were to decide to lease them until 2010, the rates would be slightly higher.
This money would be used to offset operating expenses associated with the garage's closure, and could bring WMATA nearly $900,000 in revenue if the leases were to run until April 2010.
The unknown, of course, is what will happen with the sale of the garage site, which of course was originally awarded to Akridge for $69.25 million but which is now tied up in a lawsuit brought against WMATA by Monument Realty. The parking lease with the Nats does allow for cancellation by either party with 30 days notice.
The WMATA Planning, Development and Real Estate committee will vote on the propsal first on March 27, and, if it's approved, the full board will vote on it later that same day.
For Nats fans who might be wondering, the garage and lot are both in the Red Zone, so would cost $35 per game to use.
If the garage is indeed closing next week, there will be much rejoicing by pedestrians who've been dodging the buses for years, including distracted neighborhood bloggers trying to grab photos while standing in the middle of the Half and M intersection.
Comments (1)
   
 
 More About Nationals Park

JDLand.com Home

Comments

PK says: (3/22/08 12:44 AM)
It's not just bloggers who dodge buses that will be rejoicing, JD. It'll also be drivers who dodge buses and Metro workers who dart across the street in traffic.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

dcgent on I'm Dreaming of: I posted the link partly because I'm a Detroiter. Folks in SE are championing De...
jdc on I'm Dreaming of: Love the grandma slices at Wise Guys. And being from MI too, I also love Buddy's...
VelocityChris on I'm Dreaming of: The description and picture of the Detroit-style pizza sounds/looks just like th...
JD on I'm Dreaming of: Longtime readers may remember the many trips with Mr JDLand to Michigan, where h...
dcgent on I'm Dreaming of: Detroit-style pizza coming to undisclosed navy yard location https://dc.eater.c...
Westnorth on I'm Dreaming of: XO sauce is fish-based, as with many Cantonese sauces: https://en.wikipedia.org/...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1402 1ST ST SE   
11/25/19 
UNITED STATES OF AMERICA / DAVID C POSTLEWAITE
SB1900412 / CONSTRUCTION
Parcel G2:WSP will complete four borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). The proposed boring locations would be in the four quadrants of Parcel G2 to check for spatial variability in contaminant concentrations. WSP will collect and analyze three soil samples from each boring from depths corresponding to potential subgrade elevations (i.e. 10-12 ft. bgs, 20-22 ...
1212 4TH ST SE   
11/25/19 
FC 1212 LLC / TAMIKA STATON; OTIS
ER2000409 / SHOP DRAWING
Replace governor car #2 - Part #: TBA20641H6 Replace hoist belts #1 and #4 - Part #: SB0003119
1300 4TH ST SE   
11/15/19 
ASANA PARTNERS / DEBRA MARSHALL; THE DONOHOE COMPANIES INC
B2001773 / CONSTRUCTION
ADD EXTERIOR DOOR, ADD INTERIOR DOOR , ANY RELAYED,ELECTRICAL,PLUMBING, RELOCATING UNBUILT APPROVED NON LOAD BEARING FIRE RATED PARTITIONS @ FIRST FLOOR APPROVED UNDER PERMIT #B1711970. ATTACHED
   
12/06/19 
ASANA PARTNERS / S.A. COMUNALE; S.A. COMUNALE
P2001954 / SUPPLEMENTAL
1346 4TH ST SE   
12/06/19 
KAITLYNN MATTEO / W. SAKIE - BHAR; W. SAKIE - BHAR; NA
SG2000117 / CONSTRUCTION
Install one set of non illuminated sign on to existing store front building
861 NEW JERSEY AVE SE   
11/15/19 
CSX TRANSPORTATION INC / ERICKA CLARK; DGS CONSTRUCTION
TC2000008 / CONSTRUCTION
(2) tower cranes
   
11/26/19 
GREYSTAR GP I I, LLC / KIM MITCHELL; KIM MITCHELL
FD1900040 / CONSTRUCTION
TWO BELOW GRADE PRKING LEVELS, CONCRETE FOUNDATION WALLS, SLAB ON GRADE, COLUMNS ELEVATED DECKS UP TO GRADE WITH UNDERGROUND UTILITIES (MECHANICAL, PLUMBING, ELECTRICAL)
   
12/05/19 
MIKE ALLEN / JANE MCCRAY
AH2000244 / CONSTRUCTION
WO# 1611441 - Mike Allen / P. Helgeson. Pepco to install network transformer
1111 NEW JERSEY AVE SE   
11/15/19 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TANYA HILL; THYSSENKRUPP
ER2000366 / SHOP DRAWING
REPLACE EXISTING 8MM WORN HOIST CABLES WITH LIKE IN KIND ON ELEVATOR #4. WORK TO ALLOW UNIT TO BE RETURNED TO SERVICE.
125 O ST SE   
11/25/19 
DISTRICT OF COLUMBIA / DAVID C POSTLEWAITE
SB1900411 / CONSTRUCTION
WSP will complete three borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). WSP assumes that borings will not be installed inside the fleet maintenance facility due to access restrictions imposed by DC Water. The proposed boring locations form an ā€˜Lā€™ shape around the eastern and southern sides of the fleet maintenance facility. WSP will collect and analyze three soil samp...
71 POTOMAC AVE SE   
12/06/19 
MPR REALTY / BOB BIROONAK; BOB BIROONAK; ART DISPLAY CO
SG2000099 / CONSTRUCTION
One building name MAREN Two set of address numbers all signs are non-illuminated
227 TINGEY ST SE   
12/02/19 
FC 227 LLC / KAYLA SHATTUCK; BROOKFIELD PROPERTIES MANAGEMENT LLC.
RW1900122 / CONSTRUCTION
Construction of new retaining wall located between Canal Street St and Third Street, SE.
300 TINGEY ST SE   
12/04/19 
FC BOILERMAKER LLC / ROBERT S. WATTS; ROBERT S. WATTS
E2002289 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.