The Draft Environmental Impact Statement that describes two alternatives for reconfiguring South Capitol Street from just south of Firth Sterling Avenue north to I-395 has now been released, and is available online: there's the compact executive summary for folks who just want the basics, or the full shebang, with 80-plus chapters, appendices, and reports. Note that this draft EIS does not include a final choice for the design of the new Douglass Bridge that would be built to the southwest of the current bridge, though that decision will be made with the final EIS. (I'm a fan of the arched bascule design, because I'm old school.) There's no way I'm going to try to provide a comprehensive overview of what this project is envisioning, so here's some bullet points:
* For Near Southeast, both build alternatives would reconfigure the intersection with the SE/SW Freeway, replacing the existing ramp that begins at I Street with an at-grade intersection underneath the freeway that would have two left-turn lanes to a new ramp. With the removal of the existing ramp to I-395, the intersection and South Capitol and I would also be reconfigured. Also included in this project would be streetscape improvements to New Jersey Avenue, with two travel lanes and two parking lanes and much wider tree-lined sidewalks.
* The main differences between the alternatives for this northern stretch of South Capitol Street are the intersections with Potomac Avenue and with M Street. At Potomac Avenue, there would be either a reconfigured signalized intersection or a large traffic oval connecting South Capitol, Potomac, Q Street, and the new Douglass Bridge. At M Street, a decision will be made between keeping the current underpass for north/south traffic or replacing it with an at-grade intersection. And, in the second build alternative, the K and L street intersections would be opened to cross traffic. There are also many changes planned for South Capitol Street and the Suitland Parkway south of the Douglass Bridge, which are spelled out in the Alternatives section if you're interested. (I'm waiting for a reply from DDOT about whether portions of each build alternative can be chosen a la carte to create a final alternative. UPDATE: As was the case with the 11th Street Bridges EIS, the final plans can indeed take some portions of one alternative and some from the other. So it's possible, as an example, that the traffic oval from alternative #2 could be chosen, but the unchanged M Street intersection from alternative #1 could be chosen, too.
* Depending on which alternatives and which bridge design is chosen, the Draft EIS puts the estimated costs for this project at anywhere between $508 million and $781 million. Flyers given out at the Anacostia Waterfront Community Fair last month indicated that construction on the new Douglass Bridge could begin in 2010, with completion in 2015. The Draft EIS doesn't seem to lay out any timeline for completion of the entire South Capitol Street project.
There are two public meetings planned to discuss the Draft EIS: on March 4 at Birney Elementary School, 2501 Martin Luther King Jr., Ave., SE, and on March 5 at Amidon Elementary School, 401 I St., SW. Both will run from 6:30 to 8:30 pm. The public comment period ends on March 31, and methods for submitting your comments are spelled out on the report site. You can also see print versions of the Draft EIS at a number of local libraries in the area.
Comments (1)
   
 
 More About South Capitol St.

JDLand.com Home

Comments

IMGoph says: (2/19/08 7:20 AM)
the removal of the long ramp on the east side of south capitol north of i street isn't such a big deal overall, given the rest of the scope of this project, but i think it's pretty neat thing. it's kind of like an interim move towards ridding the city of some of the concrete sprawl of the freeways.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

202_cyclist on Tidbits: Excellent news about the tower crane!
202_cyclist on Tidbits: JD-- While dogs are clearly the superior pets, I don't think anyone has ever ste...
JD on Tidbits: In on-topic news, BOLO for a new tower crane for the neighborhood, at 250 M/DDOT...
JD on Tidbits: Ahem. [image]
JES on Tidbits: As a dog owner, nothing pisses me off more than other dog owners who don't pick ...
202_cyclist on Tidbits: malatesta— I know you said this jokingly but I helped clean up the Anacostia las...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
70 B/O I ST SE   ROBBERY  04/16/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/15/19
1500 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 04/13/19
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/12/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/05/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/05/19
1500 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 04/03/19
200 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/02/19
200 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/02/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/30/19
1200 B/O VAN ST SE   BURGLARY
Burglary Two
 03/25/19
800 B/O 3RD ST SE   ASSAULT WITH A DANGEROUS WEAPON  03/25/19
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/23/19

Recent Issued Building Permits Archive  
1100 2ND PL SE   
04/10/19 
SQUARE 769N OWNER LLC / FRANK CAVANAGH; X
SG1900275 / CONSTRUCTION
Install one building sign
1331 4TH ST SE CU   
04/01/19 
FC 1331 LLC / null
P1905037 / SUPPLEMENTAL
1000 5TH ST SE   
04/09/19 
UNITED STATES OF AMERICA / TANYA HILL
B1906864 / CONSTRUCTION
***DGS REPLACEMENT OF EXISTING SINKS WITH NEW SINKS AND CABINETS AT THE DAYCARE SPACES. REVISION OF EXISTING WATER SUPPLY AND WASTE PIPES FOR NEW SINKS.
   
04/13/19 
UNITED STATES OF AMERICA / null
E1906382 / SUPPLEMENTAL
   
04/17/19 
UNITED STATES OF AMERICA / FRANKLIN T GAINES
P1905523 / SUPPLEMENTAL
150 I ST SE BASE   
04/09/19 
null
E1906206 / SUPPLEMENTAL
150 I ST SE   
04/01/19 
PEPCO UTILITY WORK / MIKE BOONE
AH1900707 / CONSTRUCTION
PEPCO-WR#3518247-ALLEN / POWER COMM-CREWS TO INSTALL TRANSFORMER / CABLE MON-SAT.
250 M ST SE   
04/15/19 
SQUARE 769 LLC / STEVEN CHEN
AH1900779 / CONSTRUCTION
Work Onsite Only - Emancipation Day
   
04/18/19 
BAKER DC LLC / CHRISTINE LONG
TC1900019 / CONSTRUCTION
Permit for Baker DC LLC to temp erect tower crane on private property
300 M ST SE   
04/01/19 
FEDERAL CENTER, LP / SAM HOLLEN
B1907517 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR OFFICE SPACE.  PARTITIONS, FURNITURE, MECHANICAL, ELECTRICAL AND LIFE SAFETY.  980 SQUARE FEET. ICI SERVICES
   
04/02/19 
FEDERAL CENTER, LP / SAM HOLLEN
B1907519 / CONSTRUCTION
INTERIOR RENOVATION TO 8TH FLOOR OFFICE SPACE.  PARTITIONS, FURNITURE, MEP AND LIFE SAFETY.  990 SQUARE FEET. ICI SERVICES
1200 NEW JERSEY AVE SE   
04/15/19 
EARL MITCHELL / null
E1906389 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
04/09/19 
SQUARE 742 LLC / MICHAEL ZEARING
AN1900118 / CONSTRUCTION
Remove (3) (E) 2.5GHz RFS (APXVTM14-C-120) Panel Antennas with Associated Cabling Remove (3) (E) 2.5GHz Alcatel Lucent (TD-RRH8x20-2500) RRH's with associated cabling Contractor to verify existing mount and if necessary replace with 3.5" OD x 8' SCH. 40 Pipe per Sprint standards Install (3) (N) 2.5GHz Nokia Airscale MAA 64T64R 128AE B41 120 AAHC MIMO Antennas Install (3) (N) MIMO Mounting Br...
125 O ST SE   
04/18/19 
DISTRICT OF COLUMBIA / BILL SAUNDERS; TBD
B1908317 / CONSTRUCTION
ADD 1 RESERVE TANK TO CLEAN AGENT FIRE SYSTEM.
71 POTOMAC AVE SE   
03/26/19 
FLORIDA ROCK PROPERTIES, INC / FLORIDA ROCK PROPERTIES
BP1902307 / POST CARD
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.