On Monday night the Zoning Commission considered two Near Southeast cases on its consent calendar. I wasn't there (having chosen to go to the ANC meeting scheduled for the same time), and the ZC's web feed experienced technical difficulties, so I'm posting some bare bones info that folks at the meeting have been nice enough to pass along.
Monument Realty asked for 22 "minor modifications" to its previously approved design for the under-construction eastern side of Half Street. According to the Office of Planning report, the changes mostly centered on adjustments to the exterior architecture and the layout of the residential component. The most noteworthy change request is probably switching from a multicolored LED screen at the Metro entrance at Half and M (which WMATA turned down, apparently) to a backlit laminated glass panel. Also, nestled deep in the OP report is a request to modify the design for the hotel windows because the "hotel operator has pulled out" -- early on, the word had been that W Aloft would be running the midblock hotel on Half Street, but apparently this is no longer the case; I've heard nothing on any new operator. You can read the report to see the other requested changes. Though this was on the Zoning Commission's consent calendar, and the commission acknowledged that the changes are small, they still wanted to see some renderings showing the befores-and-afters of the proposed changes, and have scheduled a special public meeting for Jan. 28 at 6 pm to consider the request.
Now that the eastern side of Second Street (running along Canal Park) is considered "re-opened" (it's a long story), the developers of 250 M Street are requesting to base the office building's height on the width of Second Street, which is wider than M Street. This would allow 250 M to go up to 130 feet, which apparently is the same as the height of 1100 New Jersey on the west side of the park, although apparently the building's planned square footage would actually decrease slightly which would increase the total square footage to 233,405. Though this was on the consent calendar, the commission asked the Office of Planning to submit a report on this, and there will be a public hearing.
UPDATED to fix an error about 250 M's proposed new square footage.
Comments (0)
   
 
 More About staddis

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

smitty2k1 on Barre3 Studio Coming: Cornercopia is open every weekday for breakfast and lunch. They close fairly ear...
202_cyclist on Barre3 Studio Coming: I noticed another construction trailer this morning on the empty lot immediately...
jdc on Barre3 Studio Coming: I love Harry's, but competition is always good. That said, I wonder if this plac...
sameter on Barre3 Studio Coming: besides harrys being overpriced, it will do the neighborhood good to have compet...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
300 B/O K ST SE   BURGLARY
Burglary Two
 01/13/18
1000 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/11/18
500 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 01/09/18
900 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/07/18
100 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 01/04/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/04/18
400 B/O M ST SE   THEFT
Shoplifting
 01/02/18
UNIT B/O K ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/31/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/19/17

Recent Issued Building Permits Archive  
1100 2ND PL SE   
12/21/17 
CAPPER CARROLLSBURG VENTURE LLC / null
P1802299 / SUPPLEMENTAL
1331 2ND ST SE   
12/22/17 
DC WATER / DAVE LEVINE
AH1800369 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water, Corman Construction 301-343-5417. TO EXCLUDE LEGAL HOLIDAYS.
1331 4TH ST SE CU   
12/27/17 
FC 1331 LLC / GARY BRENT; N/A
SG1800119 / CONSTRUCTION
Install 1 illuminated blade sign and 7 non-illuminated window vinyl signs - CHLOE BY HAIDAR KAROUM
   
12/28/17 
FC 1331 LLC / BEN BEDDO
TL1700205 / CONSTRUCTION
New Tenant Layout for restaurant
1300 4TH ST SE   
01/05/18 
FORREST CITY WASHINGTON / GEORGE ARTHUR KING
SB1800091 / CONSTRUCTION
To abandon 18 6 inch diameter 80 foot deep dewatering wells and 4 2 inch diameter 50 feet deep observation wells per the DOEE regulations
1346 4TH ST SE   
01/12/18 
ALAN OWINGS / ROBERT HENRY
AH1800415 / CONSTRUCTION
After Hours Permit for 1 / 15 / 18 from 7AM to 7PM to perform concrete operations, framing, operations, and utility operations.
2 I ST SE   
12/20/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800359 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
411 I ST SE   
12/27/17 
ABIGAIL A SMITH / ROBERT D. JOHNSTON
E1802679 / SUPPLEMENTAL
337 L ST SE   
12/22/17 
JENNIFER LANCASTER / null
E1802602 / SUPPLEMENTAL
   
01/11/18 
JENNIFER LANCASTER / BJORN FALK
SOL1800005 / CONSTRUCTION
Installation of a 3.6kW solar PV system. Roof Mounted, 10 panels
300 M ST SE STE# 400   
01/03/18 
FEDERAL CENTER LP / SAM HOLLEN
B1803531 / CONSTRUCTION
INTERIOR RENOVATION TO 4TH FLOOR OFFICE CONFERENCE ROOM. PARTITIONS, CEILING, MECHANICAL, ELECTRICAL AND LIFE SAFETY. NO PLUMBING OR STRUCTURAL. 680 SQUARE FEET. CACI SUITE 400
25 POTOMAC AVE SE DOCK 79   
01/11/18 
RIVERFRONT HOLDINGS I LLC / null
P1802701 / SUPPLEMENTAL
227 TINGEY ST SE   
12/29/17 
JW CAPITAL PARTNERS / MELISSA DIAZ
FD1700126 / CONSTRUCTION
Parcel L1- Foundation to Grade permit for the new construction on an 11 story full service hotel building with restaurant and retail.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.