This week's Ballpark and Beyond column in the Post is my summary of ANC 6D's deliberations on the ballpark liquor license. It also references a meeting held last night between community leaders and city and team representatives (though my deadline was before the meeting, so the column couldn't actually include anything *from* the meeting).
The meeting included updates on the road improvements in the area and the Navy Yard Metro station upgrades, both of which are still on track to be basically done by opening day (the Metro station might "still need another coat of paint", it was said, but will be "serviceable").
The Nationals are still working out their parking plans, not only in terms of the lots near the ballpark but also the satellite parking at RFK, and all the additional planning that goes with it (traffic flow, signage, shuttle buses, drop off/pick up locations, etc.). It appears as of now that there might not be season-ticket-holder lots in Southwest at all, not even at Buzzards Point. There was also mention that stadium-goers will not be funneled through the South Capitol Street exit of the freeway--the team is going to try very hard to move fans through all the other close-by freeway exits, but not South Capitol Street.
Circulator buses will not be part of the transit plans for the first season. But they're planning plenty of bike racks around the ballpark perimeter, and are also still working on a bicycle "valet" parking service.
Also, there's tentative plans for two stadium job fairs, possibly on Feb. 2 and Feb. 26 (details still being worked out).
And, everybody knows that the first few games will be "a challenge."
The general tone of the meeting was more cooperative and collegial than some of these meetings have been in the past (maybe because Tommy Wells was there for the first part and everyone wanted to be on their best behavior). There's plans for more meetings and workshops between these "stakeholders" (I really hate that word) to try to hammer out the best plans for traffic, pedestrian flow, and "curbside management" (aka on-street parking) before it's all then unveiled to the community at public meetings. There was also agreement that the group should get together after the first homestand in April to talk about what works/what doesn't.
UPDATE: Speaking of public meetings, here is the official announcement about the Jan. 11 city council Committee on Economic Development oversight hearing on "Parking and Traffic Plan for the Nationals' Stadium." It contains information on how to testify at the hearing, if you're so inclined.
Comments (0)
 
 More Recent News

JDLand.com Home

Comments

IMGoph says: (12/20/07 10:35 AM)
oh thank goodness for bike parking! biking to RFK always meant finding a good signpost somewhere to latch things to in the hopes that the bike would still be there when i got out.

if there's going to have a bike valet, does that mean the bike parking will be secure (or at least have someone keeping half an eye on it)? that would just be amazing.

i was going to be glad to see bikers getting attention at all here, but this is surpassing expectations.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Recent Comments:  
JD on A Capper Mixed-Income: They are indeed new.
202_cyclist on A Capper Mixed-Income: Perhaps not the most exciting news but there are new parking meters that have be...
JD on A Capper Mixed-Income: There's a meeting coming on Nov. 20 for public comment on whether the city shoul...
ZoolanderANDtheBoYz on A Capper Mixed-Income: It sounds like they won't start construction till 2020. Off the topic. When the...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
200 B/O M ST SE   THEFT /  10/12/14
200 B/O I ST SE   THEFT /  10/08/14
70 B/O I ST SE   THEFT F/AUTO /  10/08/14
800 B/O L ST SE   BURGLARY /  10/07/14
9TH ST SE AND POTOMAC AVE SE   THEFT F/AUTO /  10/03/14
100 B/O K ST SE   THEFT F/AUTO /  10/03/14
VIRGINIA AVE SE AND 8TH ST SE   THEFT F/AUTO /  09/28/14
6D   THEFT F/AUTO /  09/27/14
1100 B/O NEW JERSEY AVE SE   THEFT /  09/26/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1212 4TH ST SE   
10/10/14 
FORREST CITY
TL1500006 / CONSTRUCTION
CHANGE OWNER ADDRESS ON EXISTING BUILDING PERMIT TL1400136
1019 4TH ST SE   
10/14/14 
JOHN SHORT
F1500026 / CONSTRUCTION
WE WILL INSTALL AN ORNAMENTAL IRON FENCE IN THE FRONT YARD WITH A GATE. THE FENCE IS 3 FEET HIGH AND THE FENCE WILL BE BLACK IRON. FENCE IS ENTIRELY ON PUBLIC SPACE.
1212 4TH ST SE   
10/16/14 
FC 1212 LLC / PAUL R. JABLONSKI
E1500411 / SUPPLEMENTAL
   
10/16/14 
FC 1212 LLC / ARK SIGN SERVICES INC.; NONE
SG1500034 / CONSTRUCTION
INSTALL ONE WALL MOUNTED ILLUMINATED SIGN.
1103 9TH ST SE   
10/10/14 
ICP PARTNERS POTOMAC 810 LLC / HARRY RIDGEWAY
P1500293 / SUPPLEMENTAL
1220 12TH ST SE   
10/10/14 
WASHINGTON GAS LIGHT CO /
P1500284 / SUPPLEMENTAL
41 L ST SE   
10/24/14 
BILL CUMMINGS POC FOR WMATA MRP REALTY/CAS RIEGLER / EOIN DURCAN POC FOR SCHNABEL ENGINEERING
SB1400457 / CONSTRUCTION
TEMPORARY GEOTECHNICAL SOIL BORINGS NUMBER OF BORINGS: 3 DEPTH OF BORINGS: 60 FT DRILLING METHOD: 3.25 INCH HOLLOW STEM AUGER HOLE DIAMETER: 5 INCHES WELL ABANDONMENT PROCEDURE: TREMIE GROUTING WITH BENTONITE GROUT
80 M ST SE   
10/10/14 
VEIC / GEORGE DELGADO
B1411521 / CONSTRUCTION
INTERIOR ALTERATION TO SUITE 310 AS REQUIRED FOR EXPANSION. WORK TO INCLUDE ELECTRICAL MECHANICAL AND PLUMBING
20 M ST SE   
10/17/14 
SOUTHEAST REALTY LLC / DAMON ELLIS; .
SG1400457 / CONSTRUCTION
INSTALLATION OF NEW NON ELECTRIC SIGN 10FT L 1FT 8IN H 3IN W
99 M ST SE   
10/07/14 
BALLPARK SQUARE 701 LLC / STEVEN ADAMCHAK ECS MID-ATLANTIC LLC
SB1400475 / CONSTRUCTION
TWO GEOTECHNICAL BORINGS TO A AN APPROXIMATE DEPTH OF 60 FT BELOW EXISTING SITE GRADES TO BE LOCATED WITHIN PRIVATE PROPERTY. TWO BORINGS WILL BE CONVERTED TO TEMPORARY MONITORING WELLS.
100 M ST SE   
10/10/14 
SQUARE 743 INC /
P1500281 / SUPPLEMENTAL
   
10/07/14 
SQUARE 743 INC / ANTHONY G SAMBURG
E1500145 / SUPPLEMENTAL
   
10/15/14 
NORTHWOOD INVESTERS LLC / STANLEY HUBBARD; NORTHWOOD INVESTERS LLC; STANLEY HUBBARD
E14516088 / SUPPLEMENTAL
   
10/17/14 
WASHINGTON D.C. / GARY MCVEY; WASHINGTON D.C.; GARY MCVEY
E50257566 / SUPPLEMENTAL
901 M ST SE   
10/16/14 
CARLTON RAY
AH1500035 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
10/14/14 
COMCAST CABLE / MICHAEL SONESEN
AH1500018 / CONSTRUCTION
PLACING INNERDUCT IN EXISTING VERIZON MANHOLES. OCTOBER 9 2014 ? NOVEMBER 9. 2014. 7PM ? 2AM WEEKNIGHTS ? SATURDAYS
   
10/16/14 
CARLTON RAY
AH1500034 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1000 NEW JERSEY AVE SE   
10/14/14 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / RICHARD G. FINFROCK
P1500331 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
10/10/14 
DONOHOE DEVELOPMENT COMPANY / HERB LAWHORN
SB1400488 / CONSTRUCTION
A HOLLOW STEM AUGER WILL INSTALL 10 TEMPORARY DEWATERING WELLS BY ADVANCING A 12 INCH OUTER DIAMETER / 8 1 / 4 INCH INNER DIAMETER BORE HOLE TO A DEPTH OF 70 FEET BGS. AT DEPTH A 4 INCH PVC FLUSH JOINT THREADED WELL ASSEMBLY WILL BE SET AND SELECT FILTER PLACED. INTO EACH WELL WILL BE INSTALLED 2 HP TURBINE SUBMERSIBLE PUMPS. EFFLUENT WILL BE DIRECTED THROUGH A COMMON MANIFOLD TO A BAFFLED SETTLIN...
   
10/16/14 
GALLERY CAPITOL RIVERFRONT / THOMAS P MCGUIRE
E1500402 / SUPPLEMENTAL
25 POTOMAC AVE SE   
10/08/14 
MRP REALTY / JASON BENTLEY
SH1400037 / CONSTRUCTION
SHEETING AND SHORING FOR NEW BUILDING
300 TINGEY ST SE   
10/06/14 
FC BOILERMAKER LLC FC BOILERMAKER LLC / FC BOILERMAKER FC BOILERMAKER LLC
B1500169 / CONSTRUCTION
INSTALLATION OF KITCHEN FIRE SUPPRESSION SYSTEM
   
10/15/14 
FC BOILERMAKER LLC / BIRKHEAD ELECTRIC INC.; ERIN ANCHOR SIGN INC
SG1500023 / CONSTRUCTION
2-COMMERCIAL SIGN INSTALLATION
301 WATER ST SE   
10/23/14 
FOREST CITY
B1408021 / CONSTRUCTION
REVISION TO B1305741 EXTERIOR SEATING LOAD FROM 188 TO 345 EXTERIOR SEATING CONSIDER AS SUMMER GARDEN ON PRIVATE PROPERTY PER GSA / DC GOV EASMENT.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
CUSHING PL   09/11/14
$ 9,000,000
HALF STREET RESIDENTIAL PJV LLC
 
HALF ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
N ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
CUSHING PL   09/11/14
$ 9,000,000
HALF STREET RESIDENTIAL PJV LLC
 
N ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
N ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
HALF ST   09/11/14
$ 12,500,000
MR BP RESIDENTIAL #1A LLC
 
N ST   09/11/14
$ 12,500,000
MR BP RESIDENTIAL #1A LLC
 
0025 POTOMAC AV   08/08/14
$ 78,486,500
RIVERFRONT HOLDINGS I LLC
 


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.