This week's Ballpark and Beyond column in the Post is my summary of ANC 6D's deliberations on the ballpark liquor license. It also references a meeting held last night between community leaders and city and team representatives (though my deadline was before the meeting, so the column couldn't actually include anything *from* the meeting).
The meeting included updates on the road improvements in the area and the Navy Yard Metro station upgrades, both of which are still on track to be basically done by opening day (the Metro station might "still need another coat of paint", it was said, but will be "serviceable").
The Nationals are still working out their parking plans, not only in terms of the lots near the ballpark but also the satellite parking at RFK, and all the additional planning that goes with it (traffic flow, signage, shuttle buses, drop off/pick up locations, etc.). It appears as of now that there might not be season-ticket-holder lots in Southwest at all, not even at Buzzards Point. There was also mention that stadium-goers will not be funneled through the South Capitol Street exit of the freeway--the team is going to try very hard to move fans through all the other close-by freeway exits, but not South Capitol Street.
Circulator buses will not be part of the transit plans for the first season. But they're planning plenty of bike racks around the ballpark perimeter, and are also still working on a bicycle "valet" parking service.
Also, there's tentative plans for two stadium job fairs, possibly on Feb. 2 and Feb. 26 (details still being worked out).
And, everybody knows that the first few games will be "a challenge."
The general tone of the meeting was more cooperative and collegial than some of these meetings have been in the past (maybe because Tommy Wells was there for the first part and everyone wanted to be on their best behavior). There's plans for more meetings and workshops between these "stakeholders" (I really hate that word) to try to hammer out the best plans for traffic, pedestrian flow, and "curbside management" (aka on-street parking) before it's all then unveiled to the community at public meetings. There was also agreement that the group should get together after the first homestand in April to talk about what works/what doesn't.
UPDATE: Speaking of public meetings, here is the official announcement about the Jan. 11 city council Committee on Economic Development oversight hearing on "Parking and Traffic Plan for the Nationals' Stadium." It contains information on how to testify at the hearing, if you're so inclined.
Comments (0)
 
 More Recent News

JDLand.com Home

Comments

IMGoph says: (12/20/07 10:35 AM)
oh thank goodness for bike parking! biking to RFK always meant finding a good signpost somewhere to latch things to in the hopes that the bike would still be there when i got out.

if there's going to have a bike valet, does that mean the bike parking will be secure (or at least have someone keeping half an eye on it)? that would just be amazing.

i was going to be glad to see bikers getting attention at all here, but this is surpassing expectations.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Recent Comments:  
ScoopDC on Brew Garden, Park: The 909 Half Street SE site is a contaminated mess. Residents as 70 and 100 Capi...
conngs0 on Brew Garden, Park: At least they didn't find a bomb like the one they dug up underneath Twelve12!
JD on Brew Garden, Park: In other news, there's a new approved permit at 909 Half to another "three unde...
JD on Capper 'Flexibility' Gets: I wasn't referencing the tone, which I agree has been (somewhat surprisingly) ci...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1300 B/O 4TH ST SE   THEFT
Theft 1 (Theft F/Building)
 03/02/15
70 B/O I ST SE   THEFT
2nd Degree
 03/01/15
100 B/O K ST SE   THEFT F/AUTO
 03/01/15
1000 B/O 5TH ST SE   THEFT F/AUTO
Theft From Auto 1
 02/28/15
400 B/O M ST SE   THEFT
2nd Degree
 02/28/15
100 B/O K ST SE   THEFT F/AUTO
Theft From Auto 1
 02/27/15
1000 B/O 4TH ST SE   THEFT F/AUTO
 02/27/15
100 B/O CANAL ST SE   THEFT
2nd Degree
 02/24/15
1300 B/O 4TH ST SE   THEFT
Theft 1 (Theft F/Building)
 02/19/15
1000 B/O 2ND ST SE   THEFT F/AUTO
 02/18/15
100 B/O K ST SE   THEFT F/AUTO
 02/06/15

Active Public Space Permits Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1011 1ST ST SE   
02/12/15 
COLIN CLARK / MICHAEL BIANCO; COLIN CLARK; MITCH PERMUY
E98099105 / SUPPLEMENTAL
1000 5TH ST SE   
02/24/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
B1412422 / CONSTRUCTION
NEW BUILDING PERMIT FOR NEW COMMUNITY CENTER INCLUDING STEEL STRUCTURE BRICK AND MASONRY BACKUP
1240 12TH ST SE   
02/19/15 
WASHINGTON GAS LIGHT CO / CARLTON W ROBINSON
E1503465 / SUPPLEMENTAL
909 HALF ST SE   
02/25/15 
23 I LLC C/O RELATED COMPANIES / DAVID MILLER
SB1500157 / CONSTRUCTION
INSTALLATION AND MONITORING OF 8 INCLINOMETER MONITORING SYSTEMS. THREE INCLINOMETER CASINGS TO BE INSTALLED ALONG THE K STREET BORDER OF THE PROJECT. THREE CASINGS TO BE INSTALLED ALONG THE I STREET BORDER OF THE PROJECT. TWO CASINGS TO BE INSTALLED ALONG THE HALF STREET BORDER OF THE PROJECT.
   
02/23/15 
23 I LLC C/O RELATED COMPANIES / 23 I LLC C/O RELATED COMPANIES; ANDREW DANCE
SB1500132 / CONSTRUCTION
A HOLLOW STEM AUGER WILL INSTALL UP TO 30 TEMPORARY DEWATERING WELLS BY ADVANCING A 12 OD / 8 1 / 4 ID BOREHOLE TO A DEPTH OF 65 FEET. AT DEPTH A 4 INCH PVC FLUSH JOINT THREADED WELL ASSEMBLY WILL BE SET AND SELECT FILTER PLACED. INTO EACH WELL WILL BE INSTALLED A 1 HP TURBINE SUBMERSIBLE PUMP. EFFLUENT WILL BE DIRECTED THROUGH A COMMON MANIFOLD TO A BAFFLED SETTLING TANK AND DISCHARGED TO THE LO...
   
03/03/15 
23 I LLC C/O RELATED COMPANIES / JOHN DIEHL ECC INC.
UT1500019 / CONSTRUCTION
REMOVAL OF THREE UNDERGROUND STORAGE TANKS ENCOUNTERED DURING EXCAVATION FOR REDEVELOPMENT ACTIVITIES. ONE 1 000-GALLON HEATING OIL TANK ONE 1 000-GALLON KEROSENE TANK AND ONE 500-GALLON OIL / WATER SEPARATOR.
1015 HALF ST SE   
02/12/15 
THOMAS AN / THOMAS AN; HYH ELECTRIC CO. INC.
SG1500156 / CONSTRUCTION
INSTALL ONE SINGLE FACE BUILDING SIGN AND ONE DOUBLE FACE BLADE SIGN
   
02/18/15 
HALF ST SE LLC / STEPHEN R. HOLMAN
P1503532 / SUPPLEMENTAL
   
03/02/15 
HALF ST SE LLC / MATT LOSIGNOR
P1503861 / SUPPLEMENTAL
50 M ST SE   
02/18/15 
ENGLEWOOD LLC / FVI2020
FD1500010 / CONSTRUCTION
FOUNDATION OF GRADE RELATED TO CONSTRUCTION OF A NEW HOTEL
55 M ST SE   
02/24/15 
HINES GLOBAL REIT 55 M STREET LLC / ANDREW P CARAYIANNIS
M1501184 / SUPPLEMENTAL
100 M ST SE   
02/13/15 
SQUARE 743 INC / RONNIE E WRIGHT
E1503331 / SUPPLEMENTAL
   
02/13/15 
SQUARE 743 INC / DAVID FLEMING
P1503495 / SUPPLEMENTAL
   
02/19/15 
SQUARE 743 INC / DAVID FLEMING
P1503597 / SUPPLEMENTAL
   
02/20/15 
SQUARE 743 INC / GREGORY E LIGON
E1503498 / SUPPLEMENTAL
   
02/23/15 
SQUARE 743 INC / ANTHONY G SAMBURG
E1503518 / SUPPLEMENTAL
901 M ST SE   
02/19/15 
US GOVERNMENT NAVY PWC / SUMMIT CONSTRUCTION AND ES
B1504570 / CONSTRUCTION
REQUEST AND E&S PERMIT FOR WORK ON FEDERAL INSTALLATION. INSTALLING FOOTINGS AND SLAB WITH PORTCH SUPPORTS. MINOR GRADING AND SEEDING. BUILDING FOOTPRINT IS UNDER 700SF. LAND DISTURBANCE INCLUDING GRADING AND SEEDING IS UNDER 2 500SF.
100 M ST SE   
02/19/15 
SQUARE 743 INC / JOHN H THOMSON
E1503464 / SUPPLEMENTAL
   
02/20/15 
SQUARE 743 INC / DAVID RAINE; SQUARE 743 INC; DAVID RAINE
P38575591 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
02/24/15 
NEW JERSEY AT H LLC / JOHN H THOMSON
E1503556 / SUPPLEMENTAL
   
02/13/15 
BAKER DC / CHRISTINE LONG
AH1500246 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 7:00PM THRU 7:00AM
909 NEW JERSEY AVE SE   
02/26/15 
909 NEW JERSEY AVENUE ACQUISITION LLC / DAVID L. HAHN
P1503815 / SUPPLEMENTAL
1000 NEW JERSEY AVE SE   
02/23/15 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / SHAWN ALEX HELLER
HO1500118 / HOME OCCUPATION
HOME OFFICE (LAW OFFICE).
25 POTOMAC AVE SE   
03/03/15 
RIVERFRONT HOLDINGS I LLC /
P1503907 / SUPPLEMENTAL
1500 SOUTH CAPITOL ST SE   
03/02/15 
WASHINGTON NATIONALS STADIUM LLC / MATT LOSIGNOR
P1503862 / SUPPLEMENTAL
   
03/03/15 
NATIONALS PARK / KEVIN HOOVER; NATIONALS PARK; KEVIN HOOVER
E21362502 / SUPPLEMENTAL
300 TINGEY ST SE   
02/13/15 
RICHARD CERVERA / NATHANIEL GILL
B1504014 / CONSTRUCTION
NEW SUMMER GARDEN
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




     © Copyright 2015 JD.