Thanks to the glories of the On Demand video offerings at the city's Office of Cable Television web site, I was able to catch Wednesday's hearing on the request to close the 8,197-square-foot alley that bisects Square 696, the block bounded by I, K, First, and Half streets that DRI Development bought in April for $64 million. As I posted a few weeks ago after DRI's presentation to ANC 6D, DRI is planning more than 825,000 square feet of office and retail on the block, in three buildings that would be built in three phases, the first being a 300,000-square-foot office building along I Street that could begin construction in the summer of 2008.
As part of its successful bid to get the ANC's support, DRI and its development partner Jamestown Properties have committed to a $100,000 payment to the Near Southeast/Southwest community fund, LEED certification, and an 8,000-square-foot public plaza at First and K streets to replace the "public space" being lost by the alley closing.
The early part of the hearing was pretty standard as these types of sessions go. The development's representatives described their agreement with the ANC, and also the planned 37,000-square-feet of retail what would serve not only the office tenants but also the residential projects that will soon surround the block on all sides. Also touted were the large south-facing public plaza (light-filled and sunny!) with a 20-foot-wide pedestrian "breezeway" through the block to open the area to pedestrians arriving from I Street, the innovative loading ramps within turnaround space inside the buildings to eliminate the need for commercial vehicles to back up or turn around out in the streets, the fitness center with changing and shower facilities to encourage bicycle use, and more.
Then, Council Member Tommy Wells began to ask questions about the amount of the developers' required contribution to the city's Housing Production Trust Fund, dedicated to the creation of affordable housing. Wells brought up a slight discrepancy between the number the developers were citing versus what the Office of Planning had determined the figure to be.
Developer figure? Approximately $890,000.
Office of Planning figure? More like $8 million.
The hearing then became a blur of real and estimated assessed values, total F.A.R. based on T.D.R.s (that's total floor-area ratios based on transfers of development rights, for those of you whose minds are blissfully unsullied with this stuff), buildable square footage, and on-the-fly calculations. Council Chairman Vincent Gray, after commenting that even the $890,000 figure cited by the developers would be the largest trust fund contribution ever, wondered how many projects in the District "would see the light of day" if the city starts talking about $8 million contributions. Wells and Gray agreed that the calculating discrepancies need to be resolved so that the trust fund law can be implemented consistently, and the hearing ended with pledges from the applicant to provide additional information.
And despite the wrangling over the trust fund contribution, Council Member Wells made sure to reiterate that he supports the project, especially because of the environmentally friendly aspects of the design.
In the meantime, the last tenant on the block (a taxi repair garage) will be vacating when its lease expires in February.
Check my Square 696 page for an early sitemap of the project, along with photos of the block.
Comments (0)
   
 
 More About Square 696 Residential

JDLand.com Home

Comments

Sorry, comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJBabyDaddy on Roundup of Some: Looks like the final piece of the final arch of the New Frederick Douglass Memor...
GarfieldPark on Roundup of Some: Wagtime has now turned into Dogtopia? New owners or what?
CJBabyDaddy on Roundup of Some: To my fellow New FDMB arch geeks: As of COB Friday, August 7, nine of the twelv...
CJBabyDaddy on Roundup of Some: La Famosa (1st floor of the Bower) targeting a late August or early September op...
GarfieldPark on Roundup of Some: Target date of Wed Aug 12th for I ST CVS. Can't come soon enough!
JES on Roundup of Some: It looks like punch bowl isn't completely dead, as they're reopening some locati...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
600 B/O L ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/10/20
800 B/O POTOMAC AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/09/20
1000 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/04/20
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/02/20
1100 B/O 2ND PLACE SE   BURGLARY
Burglary Two
 07/31/20
100 B/O I ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/30/20
100 B/O O ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/28/20
400 B/O M ST SE   THEFT
Shoplifting
 07/24/20
100 B/O M ST SE   BURGLARY
Burglary Two
 07/20/20
UNIT B/O N ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/20/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (theft From Building)
 07/13/20

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
07/22/20 
LA FAMOSA / null
E2009613 / SUPPLEMENTAL
1300 4TH ST SE 130   
07/24/20 
TOM AN / KIMOY LALLEMENT
A2005055 / CONSTRUCTION
New sail shade awning at exterior private space of La Famosa restaurant (Permit #TL2000028)
1150 5TH ST SE   
07/16/20 
DISTRICT OF COLUMBIA / null
P2007453 / SUPPLEMENTAL
   
07/22/20 
DISTRICT OF COLUMBIA / null
E2009571 / SUPPLEMENTAL
   
08/04/20 
DISTRICT OF COLUMBIA / KEVIN HURLEY
SB2000405 / CONSTRUCTION
We propose to perform 2 soil borings to maximum depths up to 50 feet below grade, or refusal. The borings will be advanced with a geotechnical drill rig, which utilizes 3.25" hollow stem augers. Upon completion, the borings will be backfilled with bentonite slurry, in general accordance with DOEE requirements.
10 I ST SE   
07/27/20 
CAPITOL HILL RACQUET CLUB / ANDREW ARNOLD; NA
SB2000413 / CONSTRUCTION
We propose drilling two (2), six-inch diameter geotechnical test borings (B-7 and B-8) using the hollow stem auger method to evaluate the subsurface conditions. The proposed test boring depths will be 85 feet below the existing ground surface. If a confining unit is encountered, outer casing will be installed which will extend 10 feet into the top of the confining unit or to the top of bedrock. Up...
150 I ST SE   
07/30/20 
SQUARE 737 LLC C/O WC SMITH / RUSSELL COX
B2007765 / CONSTRUCTION
Amendment to B1709058. Decrease number of dwelling units to 373 units. Construction of 2 spas. Electrical, Mechanical, Plumbing changes.
423 L ST SE   
07/24/20 
JOHN P LANG / MARGO RICKS
SOL2001665 / CONSTRUCTION
To install 4.56 kW size of solar panels with a system height of 1.1 feet on roof of building.
250 M ST SE   
07/21/20 
SQUARE 769 LLC / null
E2009527 / SUPPLEMENTAL
   
08/04/20 
SQUARE 769 LLC / BRIAN C STROTT; SQUARE 769 LLC
B1915078 / CONSTRUCTION
Revisions to permit B1813732. Changes to the roof area. Adding mechanical equipment to roof.
300 M ST SE   
07/27/20 
FEDERAL CENTER LP / null
E2009758 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
07/23/20 
GREYSTAR GP LLC / null
M2003144 / SUPPLEMENTAL
1105 NEW JERSEY AVE SE   
07/23/20 
GALLERY CAPITAL RIVERFRONT PROPERTY LLC / null
E2009620 / SUPPLEMENTAL
1200 NEW JERSEY AVE SE 20590   
08/05/20 
UNITED STATES OF AMERICA / null
E2010040 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
08/05/20 
US GOVERNMENT / null
E2010054 / SUPPLEMENTAL
   
08/07/20 
FC FACILITATOR LLC FOREST CITY REALTY TRUST / null
P2007950 / SUPPLEMENTAL
79 POTOMAC AVE SE 505   
07/15/20 
null / NA NA NA
EHOP20993669 / HOME OCCUPATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.