Since January, 2003
            
 Page Through from Before to After

With Opening Day 2008 inching closer, the cobbling together of parking at the new ballpark is apparently turning out to be a greater challenge than constructing an on-time on-budget stadium. So this week the city put in another zoning amendment request to allow more temporary surface parking lots, this time covering eight squares in Southwest, all between P, T, 2nd, and South Capitol streets. (See my Stadium Parking page for a map with the new lots highlighted.) You can read the Office of Planning's report on the new case (07-08A) for more detail.
On Monday night the Zoning Commission approved this request on an emergency basis, meaning that the zoning change takes effect immediately, lasting 120 days while a hearing is scheduled and a permanent amendment is voted on.
As with the original amendment approved earlier this year, the lots can last no more than five years, are required to be available for public parking during non-game times, and must have District Department of Transportation approval of their traffic routing plans to ensure that access to the lots is not directed along I, P, or Fourth streets, SW. There's also a new requirement being added with this latest request, that a minimum of five percent of the spaces in these lots be reserved for a car/ride-share program.
These new lots are still subject to the cap of 3,775 total spaces laid out in the first amendment, unless special exceptions are obtained after the cap is reached from the Board of Zoning Adjustment on a per-lot basis. As with the squares covered earlier this year, it's not expected that lots will suddenly sprout on every one of the locations covered in the request; the main goal appears to be additional flexibility in finding possible spots for the needed spaces.
A separate zoning action a few months ago approved three temporary surface lots totaling under 800 spaces at The Yards, across the street from the stadium. There are also apparently negotiations underway about using the lots at RFK and providing shuttle service to the new ballpark.
There are other locations within a few blocks of the ballpark that will no doubt become temporary parking lots as well--one example is the Lerners' recent permit applications to build a lot on land they own at 1000 South Capitol Street.
At Monday's ANC 6D meeting, when this new zoning amendment was discussed, commissioners mentioned rumors of additional lots perhaps coming to the recently closed KFC and Exxon locations on the west side of South Capitol. But these blocks are not in the Capitol Gateway Zoning Overlay, and so don't require the special approval needed for the squares in the previous amendment requests. And these additional locations still require the Nationals to contract with the landowners, which might not always be an easy negotiation.
The ANC commissioners did not bring up many concerns about this new request, other than asking for confirmation that the traffic controls in the initial amendment cover these new lots, which Judi Greenberg of the Office of the Deputy Mayor for Planning and Economic Development assured was the case.
Commissioner Ron McBee said that he hopes to organize a town hall meeting for Southwest residents about all the parking plans when they are more concrete, and vice chair Andy Litsky reminded Greenberg that the DC Sports and Entertainment Commission is supposed to be meeting with community leaders to address ballpark-related concerns, but that there hasn't been a meeting in six months.
The zoning commission's approval of the emergency action came with little discussion, perhaps reflecting that most of the potential issues with these temporary lots were hashed out in the first request.
Time should solve many of the initial parking issues around the ballpark; right now there are seven office and residential projects already under construction around Near Southeast that by 2008 and 2009 will have multiple levels of underground parking that could potentially be available for gametime, just as with the lots are in the buildings around the Verizon Center. Most of the squares in these recent zoning requests, along most every other block between South Capitol and Second, will also eventually be home to buildings with underground parking.
UPDATE: An e-mail sent out today to Nationals season ticket holders says that 2008 ticket package information will be sent out "in the next month or so", and that a "comprehensive transportation package will also be sent to all season ticket holders shortly after you have received your seat location information." Presumably the "transportation package" means parking plans for season ticket holders (and maybe a really good Metro map!).
Comments (0)
   
 
 More About Nationals Park

JDLand.com Home

Comments

Sorry, comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

jdc on Roundup of Some: Being able to walk to Silver Diner is nice. I miss my routine of taking the morn...
JES on Roundup of Some: omg i would kill for a silver diner...
conngs0 on Roundup of Some: sharksfansd, I agree the Peet's closure is a shame as it was a solid option. No...
sharksfansd on Roundup of Some: Such a bummer about Peet's, as it was my go to instead of the other large coffee...
GG on Roundup of Some: So what’s the story with the CVS at Half and I? It’s looked fully stocked and r...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
100 B/O I ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/30/20
100 B/O O ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/28/20
400 B/O M ST SE   THEFT
Shoplifting
 07/24/20
100 B/O M ST SE   BURGLARY
Burglary Two
 07/20/20
UNIT B/O N ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/20/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (theft From Building)
 07/13/20
900 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/09/20
1500 B/O 1ST ST SE   SEX ABUSE
Assault W/intent To Commit First Degree Sexual Abuse (force) (rape)
 07/08/20
400 B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/06/20
1200 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/05/20
100 B/O H ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/03/20
100 B/O O ST SE   ROBBERY  07/03/20

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
07/22/20 
LA FAMOSA / null
E2009613 / SUPPLEMENTAL
1300 4TH ST SE 130   
07/24/20 
TOM AN / KIMOY LALLEMENT
A2005055 / CONSTRUCTION
New sail shade awning at exterior private space of La Famosa restaurant (Permit #TL2000028)
900 5TH ST SE   
07/13/20 
null
B1906215-EXT-1 / CONSTRUCTION
1ST EXTENSION TO B1906215, EXTENSIOIN WILL EXPIRE ON 03 / 01 / 2020. ORIGINAL SCOPE: Reconstruction of 4-story residential building, the Arthur Capper Senior Center, damaged by fire.
1150 5TH ST SE   
07/08/20 
DISTRICT OF COLUMBIA / CASEY STRINGER; NA
B2008863 / CONSTRUCTION
DGS PROJECT Minor interior classroom renovations at existing school
   
07/16/20 
DISTRICT OF COLUMBIA / null
P2007453 / SUPPLEMENTAL
   
07/22/20 
DISTRICT OF COLUMBIA / null
E2009571 / SUPPLEMENTAL
10 I ST SE   
07/27/20 
CAPITOL HILL RACQUET CLUB / ANDREW ARNOLD; NA
SB2000413 / CONSTRUCTION
We propose drilling two (2), six-inch diameter geotechnical test borings (B-7 and B-8) using the hollow stem auger method to evaluate the subsurface conditions. The proposed test boring depths will be 85 feet below the existing ground surface. If a confining unit is encountered, outer casing will be installed which will extend 10 feet into the top of the confining unit or to the top of bedrock. Up...
423 L ST SE   
07/24/20 
JOHN P LANG / MARGO RICKS
SOL2001665 / CONSTRUCTION
To install 4.56 kW size of solar panels with a system height of 1.1 feet on roof of building.
250 M ST SE   
07/10/20 
SQUARE 769 LLC / null
E2009225 / SUPPLEMENTAL
   
07/21/20 
SQUARE 769 LLC / null
E2009527 / SUPPLEMENTAL
300 M ST SE   
07/27/20 
FEDERAL CENTER LP / null
E2009758 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
07/23/20 
GREYSTAR GP LLC / null
M2003144 / SUPPLEMENTAL
1105 NEW JERSEY AVE SE   
07/23/20 
GALLERY CAPITAL RIVERFRONT PROPERTY LLC / null
E2009620 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
07/08/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
M2002985 / SUPPLEMENTAL
1200 NEW JERSEY AVE SE 20590   
07/14/20 
JBG/FEDERAL CENTER LLC / SAM HOLLEN
B2006851 / CONSTRUCTION
INTERIOR RENOVATION TO 1ST FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MECHANICAL, ELECTRICAL AND LIFE SAFETY. NO PLUMBING. NO STRUCTURAL. 1700 SQUARE FEET. GSA / DOT
1275 NEW JERSEY AVE SE   
07/13/20 
FC 1275 NJ, LLC / PARKER HARRELL
SB2000382 / CONSTRUCTION
We are abandoning 14 gravel packed dewatering wells and one piezometer. All pumps and associated hardware will be removed from the wells. Each well casing will then be removed of perforated. We will then tremie each borehole using a bentonite slurry (two pounds bentonite powder to one gallon water).
1033 O ST SE 20374   
07/13/20 
UNITED STATES OF AMERICA / STANELY CARPENTER; JILL S CUTLER
BCIV2000111 / CONSTRUCTION
Install a safety shower and eye-wash station with a concrete base at the hazardous waste storage area near Building 166 at the Washington Navy Yard.
79 POTOMAC AVE SE 505   
07/15/20 
null / NA NA NA
EHOP20993669 / HOME OCCUPATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.