Since January, 2003
            
 Page Through from Before to After

It was more than six years ago that word first seeped out that Forest City Washington was looking to bring a large movie theater to the Yards, on land owned by DC Water that the development company would acquire.
But those negotiations have still not completely been resolved, and, in a time-extension request filed last week with the Zoning Commission, Forest City described the current situation, which will displease long-frustrated neighborhood moviegoers:
"Because of the extensive delays tied to the important and expansive discussions regarding DC Water's relocation and operational needs, as well as DC Water's need to retain control of the F-1 Parcel to facilitation construction of its headquarters building, Forest City's rights with respect to the lease with the theater operator have expired. Despite efforts to reconstitute that deal, it is clear that Forest City will not be able to proceed with the original approved program for a two-level, 16-screen theater above a four-level parking garage."
The filing goes on to say that the company is "now pursuing additional refinements to the approved plans." While the building's size and scale will likely stay the same, it is possible that the theater will be "reduced in size" and/or "incorporating other appropriate and compatible uses for the site to ensure a viable project." There is also apparently a need to relocate the building's planned loading and service access onto N Place and away from DC Water's ongoing operations. The facade design will likely change as well.
The filing states that the "very complicated planning constraints on this unique site" have "nearly reached final resolution," but that Forest City now requests an additional two years to work on redesigning the plan.
(Of course, this means that the replacement of "When will Whole Foods open?" with "When will the movie theater open?" as the most-asked question at JDLand will continue on for a while.)
Comments (2)
   
 
 More About The Yards at DC Water

JDLand.com Home

Comments

CJBabyDaddy says: (1/9/19 5:12 PM)
As a traditionalist, I, for one, will never stop asking, “When will Whole Foods open?”


jdc says: (1/10/19 9:14 AM)
With all of the apartments coming online over the next two years, I think a further delay is probably fine - you really need a lot of residential to support a 16 screen theater and I have always wondered what the catchment area is for this site...Still, I am hopeful a movie theater is the ultimate tenant because as a nearby office worker it would make seeing afternoon films very easy on half-days.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

Westnorth on Inching from Quarantining: M St SE is getting rush-hour bus lanes from 1/2 St to 10th St. https://ddot.dc....
CJ1 on Inching from Quarantining: Oh wow... I live at Ore82 and didn't know about any of this.
GarfieldPark on Inching from Quarantining: @JD: Apparently, ORE will be eliminating (or making them smaller) some of it's ...
JD on Inching from Quarantining: Some interesting design notes found in the approved building permit for the thre...
KEWEE on Inching from Quarantining: Jeni's Splendid Ice Creams is coming to the retail space located at The Bower co...
CJBabyDaddy on Inching from Quarantining: Serious workplace accident on the ground this morning at the Chemonics construct...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/06/20
1200 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/05/20
100 B/O H ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/03/20
100 B/O O ST SE   ROBBERY  07/03/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 06/28/20
1200 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 06/25/20
1200 B/O SOUTH CAPITOL ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 06/23/20
1200 B/O NEW JERSEY AVE SE   ASSAULT WITH A DANGEROUS WEAPON
Assault W/i To Kill
 06/20/20
1000 B/O 3RD PLACE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/18/20
800 B/O SOUTH CAPITOL ST SE   ASSAULT WITH A DANGEROUS WEAPON  06/14/20
400 B/O M ST SE   THEFT
Shoplifting
 06/12/20
1000 B/O M ST SE   ROBBERY
Unarmed Carjacking
 06/09/20
UNIT B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  06/07/20

Recent Issued Building Permits Archive  
1300 4TH ST SE RU-2   
06/18/20 
AP BOWER RETAIL LLC / MELISSA BRENT
SG2000335 / CONSTRUCTION
Install 1 illuminated wall sign & 1 illuminated blade sign - JENIs ICE CREAM
150 I ST SE   
06/15/20 
SQUARE 737 LLC / BOB BIROONAK; NA; NA
SG2000323 / CONSTRUCTION
two illuminated building sign
151 M ST SE   
06/18/20 
BROOKFIELD PROPERTIES / CHRIS CRESCI; NA
SB2000292 / CONSTRUCTION
WSP will be advancing approximately 50 soil borings to 30 feet, and an additional 8 borings to 4 feet via direct push. A water sample will be collected from 3 of the deep borings. All borings will be abandoned via bentonite grout mix. Investigation derived waste will be stored in DOT 55-gallon steel drums. Private and public utility locating will take place prior to the work beginning
250 M ST SE   
06/19/20 
WILLIAM C SMITH / null
E2008622 / SUPPLEMENTAL
   
06/24/20 
SQUARE 769 LLC / null
M2002834 / SUPPLEMENTAL
   
06/24/20 
SQUARE 769 LLC / null
P2006931 / SUPPLEMENTAL
300 M ST SE   
06/16/20 
FEDERAL CENTER LP / null
E2008501 / SUPPLEMENTAL
   
06/18/20 
FEDERAL CENTER LP / null
E2008587 / SUPPLEMENTAL
111 N ST SE   
06/16/20 
BROOKFIELD PROPERTIES / NA; CHRIS CRESCI
SB2000293 / CONSTRUCTION
WSP will advance 22 soil borings to 25 feet and 8 soil borings to 4 feet via direst push. A groundwater sample will be collected from 2 of the deep borings by installing a temporary well to be in the ground for just a couple hours. Borings will be backfilled with bentonite / grout mix. IDW will be stored in DOT 55-gallon drums. A private and public utility mark out will be completed prior to b...
861 NEW JERSEY AVE SE   
06/10/20 
CXS TRANSPORTATION INC / ;
P2006604 / SUPPLEMENTAL
   
06/19/20 
CXS TRANSPORTATION INC / ;
P2006843 / SUPPLEMENTAL
   
06/22/20 
GREYSTAR GP LLC / KIM MITCHELL
B1903035 / CONSTRUCTION
The proposed project is three structures which are connected by a shared below-grade garage, which is one story deep on the east half of the site and two stories deep on the west half of the site. Two structures will be residential, with a total of 756 units, and the third will be a 225-key hotel. The west residential structure (Building 3) is planned to be 13 stories with ground and roof level am...
   
06/25/20 
CXS TRANSPORTATION INC / ;
P2006972 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
06/10/20 
SQUARE 742 LLC, C/O SPAULDING & SLYE/STE 100, / PAUL WHITLEY
AN1900284 / CONSTRUCTION
PROJECT CONSISTS OF: REMOVING: (2) EXISTING EQUIPMENT CABINETS, (3) EXISTING ANTENNA'S, (1) EXISTING RRU'S AND ANCILLARY EQUIPMENT / CABLE AND INSTALLING: (6) PROPOSED ANTENNA'S, (3) PROPOSED RRU'S, AND(2) PROPOSED EQUIPMENT CABINETS ON AN EXISTING TELECOM FACILITY
1111 NEW JERSEY AVE SE   
06/12/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TRACIE CLAXTON; NA; NA
SG2000257 / CONSTRUCTION
One Wall Mounted Sign illuminated
   
06/24/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P2006938 / SUPPLEMENTAL
401 WATER ST SE   
06/18/20 
BROOKFIELD PROPERTIES / CHRIS CRESCI
SB2000294 / CONSTRUCTION
WSP will advance 23 soil borings to 30 feet and 8 additional borings to 4 feet using direct push. A groundwater sample will be collected from 2 of the deep borings by installing a temporary well. Soil boirngs will be abandoned with bentonite / grout mix. IDW will be stored for disposal in DOT 55-gallon drums. A private and public utility mark out will be completed priot to starting intrusive w...
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.