Not quite six months after buying the land on the northeast corner of Half and N streets across from Nats Park currently known as Monument Valley, the MacFarlane/Jair Lynch joint venture has now submitted to the Zoning Commission its new plans for the site, a 10-story building with 461,700 square feet of residential (and possibly hotel) development, combined with at least 60,000 square feet of retail.
Back a couple of lifetimes ago, Monument Realty also planned a residential, retail, and hotel project on this site, so this filing is actually a modification to the previously approved plans. The new designs by architectural firm Hord Coplan Macht, seen in these renderings purloined from the zoning filing, would add at least 23,000 square feet of retail to what had been planned, mostly in the second-floor space along Half Street, as shown in the drawing below, as well as potentially an additional 8,000 square feet on the second floor facing N Street, depending on the all-important "market conditions."
The new project would have either 445 residential units and no hotel at all, or 365 residential units and a 80-room hotel on the north end of the site (down from a 200-room hotel in Monument's designs). The new design includes condos (apparently 130ish of them) in the south wing along N Street, with the rest being rental units.
As in the original designs, there would still be a small street called "Monument Place" running between this building and its neighbor to the north, 55 M Street, allowing the retail offerings to wrap around onto the building's north side--however, in these new plans it would be a pedestrian-only street, negating the need for a curb cut on Half Street.
In addition, the basically-an-alley Cushing Place would still be extended through to N Street, through an opening in the ground floor of the south side of Lynch's building. (If you look closely at the top rendering, you can see it.) There would still be three levels of underground parking with approximately 231 spaces. And there would be all manner of streetscape work to make the sidewalks--and the walk to the ballpark--a bit more inviting than they are now.
For you zoning groupies, there's also one special exception being requested, that the project be allowed to have two roof enclosures instead of one on the south wing of the building that fronts N Street. And note that this is all under the Capitol Gateway Overlay design review process.
These new plans will be presented to ANC 6D on Monday night (March 9), with a zoning hearing date apparently as yet unannounced. My Monument Valley project page has a few of the old Monument renderings, should you wish to compare.
UPDATE: The zoning hearing is apparently now scheduled for May 28.
Comments (13)
   
 
 More About Monument Valley/Half St.

JDLand.com Home

Comments

BLT says: (3/8/15 8:33 PM)
The good thing is once construction does begin, it will go vertical rather quickly! This is exciting to see.


JES says: (3/9/15 11:54 AM)
So I'm not too familiar with construction timelines. Assuming zoning has no issues with this plan, what would be the earliest we'd see construction starting? A year?


JD says: (3/9/15 11:58 AM)
They have said they are targeting 2016. A CG Overlay review is a quicker process than a PUD, especially since this is a modification. Then it's building permits. And finalizing construction financing.



BLT says: (3/9/15 12:39 PM)
Looks like a construction trailer and equipment have arrived at the Homewood Suites site today. They were wotking on the fencing earlier today.


JD says: (3/9/15 12:40 PM)
If you're having trouble keeping track of the Half Street 2.0 resurgence, I created this handy graphic:
link

It's part of my spruced-up-for-Opening-Day What's New Since Last Season page:
link



JD says: (3/9/15 12:41 PM)
@BLT, thanks for the update! I look forward to the race amongst readers to be the first to report ground being broken there. :)


BLT says: (3/9/15 3:53 PM)
And the Bonchon signs are going up! I should win a jdland t-shirt for this special reporting. :)


JD says: (3/9/15 5:40 PM)
Since MJM sent me a pic on Twitter showing fencing stuff happening at the Ballpark Square/99 M site, can somebody confirm that there was also stuff happening today at the 50 M/Homewood Suites site? (right across Half from the Big Stick)



BLT says: (3/9/15 5:56 PM)
@jd...I can walk over to 50 M and snap a picture. Can I send to an email?


JD says: (3/9/15 6:01 PM)
Sure! You can just send to jd at jdland etc. Thanks.

(Not that I didn't trust you--just that sometimes people confuse project locations, and since there was action elsewhere, just wanted to be doubly sure.)


BLT says: (3/9/15 6:07 PM)
No problem. Lots going on around here and I'm sure sites are confused often.


JD says: (3/9/15 6:10 PM)
I now have photographic evidence that BLT was correct. :)



Westnorth says: (3/10/15 11:43 AM)
60,000 feet -- finally, a retail space big enough for a "junior anchor." Most of the buildings around here have had spaces <20,000 feet, and there's only so much specialty retail to go around so far.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

202_cyclist on Albi Opening This: There was soil boring activity this morning at the former taxi lot at New Jersey...
jdc on Retail Roundup: Concur with 202 - with Parc Riverside phase 2 and then DC Crossing finished, the...
Jscott280 on Albi Opening This: Fences up around parcel H. They are going to change the ingress points to N plac...
jdc on Albi Opening This: At 37 L, windows are going in and tower crane is gone. At Chiller site next door...
dcgent on Albi Opening This: UrbanTurf looks at what's coming housing wise for the area https://dc.urbanturf....
Shogungts on Albi Opening This: @Jason - not sure if that is the plan, but it would be nice. I went by there th...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1500 B/O SOUTH CAPITOL ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/24/20
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree - Felony (theft From Building)
 02/24/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/24/20
1200 B/O VAN ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/23/20
900 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 02/22/20
900 B/O 11TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/20
900 B/O M ST SE   BURGLARY
Burglary Two
 02/19/20
1200 B/O HALF ST SE   ROBBERY  02/18/20
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/20
400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  02/08/20
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/02/20
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/01/20
600 B/O VIRGINIA AVE SE   ASSAULT WITH A DANGEROUS WEAPON  01/29/20

Recent Issued Building Permits Archive  
909 4TH ST SE   
02/12/20 
MEREDITH FASCETT / null
E2004655 / SUPPLEMENTAL
1300 4TH ST SE APT 214   
02/03/20 
null / NA NA NA
EHOP20983190 / HOME OCCUPATION
1021 5TH ST SE   
02/13/20 
KEVIN WILLIAMS / KEVIN WILLIAMS; KEVIN WILLIAMS
B2005053 / CONSTRUCTION
Apply for building permit to have final closing inspection for permit #B1602481 & B1602513 per inspector inspection report since these permits has expired.
150 I ST SE   
02/14/20 
SQUARE 737 LLC / JASON D DORRIS
AH2000818 / CONSTRUCTION
Construction of a new 13 story apartment building with three below grade parking levels, 1st floor retail, and amenity areas; 375 units and 181 parking spaces. To include mechanical, electrical, plumbing, elevators and structural work.
250 M ST SE   
02/14/20 
SQUARE 769 LLC / null
P2003901 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE 20003   
02/14/20 
BROOKFIELD PROPOERTIES / TIM GOOD
AH2000849 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Presidents Day, February 17, 2020. Operations would include below grade concrete and waterproofing activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am to 7pm period.
1111 NEW JERSEY AVE SE   
02/25/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / WILL ROWELL; NA NA
B2000625 / CONSTRUCTION
Scope of Work; Plumbing additional bathroom and new fixtures-running lines under slab & within a 15' radius. Electrical installation of approx. 10 outlets / 5 switches / 200 amp services / sub panel & new lighting / wiring. HVAC relocating / dropping 2 new heat fans & installation of 2 ductless split systems. Sprinkler System Turn down of all sprinkler heads, re-balance and restart / re-charge
1275 NEW JERSEY AVE SE   
02/07/20 
MILLER AND LONG / WILLIAM MOORE
AH2000699 / CONSTRUCTION
Afterhours to put up towercrane with mobile crane saturday 2 / 8 / 2020 and 2 / 9 / 2020 from 5am to 1159pm
1299 NEW JERSEY AVE SE   
02/18/20 
FOREST CITY SEFC LLC / STRAUCHON; SEE BELOW
BCIV1800153 / CONSTRUCTION
Phase 1A BCIV Permit Description - BCIV 1800153 - The subject BCIV permit is for the Phase IA development of Quander St SE, N Pl SE, and 1-1 / 2 St SE within the overall Forest City, Yards West (FCYW) development area which emphasizes: pedestrian-focused public realm, optimized utility corridor, fully integrated SWM design, and complete street and vision zero design. The FCYW Phase IA is comprised...
1322 PATTERSON AVE SE   
02/13/20 
JOINT BASE ANACOSTIA BOLLING - UNITED STATES NAVAL OBSERVATORY SI / TONYA HARRIS; TONYA HARRIS; TBD
BCIV2000046 / CONSTRUCTION
***FEDERAL PROPERTY*** PROJECT WILL CONSIST OF DREDGING THE EXISTING RETENTION POND AND INSPECTING AND CLEANING THE OUTLET CONTROL STRUCTURE (S1) LOCATED ON THE UNITED STATES NAVAL OBSERVATORY TO REMOVE SEDIMENT ACCUMULATION. CONTRACTOR SHALL AVOID THE CLEARING OF VEGETATION ON POND EMBANKMENTS AND SURROUNDING AREAS SO AS TO KEEP RESTORATION AND REPLANTING TO A MINIMUM.
71 POTOMAC AVE SE   
02/13/20 
MRP REALTY / JAMES VANEGAS
AH2000681 / CONSTRUCTION
Perform interior and exterior construction activities. New construction 14-story new residential multi-family building.
   
02/19/20 
RIVERFRONT HOLDINGS II, LLC / JUSTIN BISHOP; JUSTIN BISHOP
SP1900054 / CONSTRUCTION
Construct a 680 sqft concrete swimming pool inside an existing waterproofed structural box on the 14th floor. All MEP, decking and fencing work by other trades under separate permits.
227 TINGEY ST SE   
02/12/20 
GONE YARD HOTEL OWNER LLC / BOB BIROONAK; BOB BIROONAK
SG2000048 / CONSTRUCTION
one double face illuminated blade sign
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.