After not having a new high-rise residential project under construction in the neighborhood since spring 2009, it's sort of amazing to realize there are now three such buildings up out of the ground, with more than 900 new rental units in the pipeline for delivery within the next year to eighteen months. (And there could be another 650 units added to tally if both the Yards/Parcel N and 800 New Jersey/Whole Foods projects get going as expected in the coming months.)
The farthest along is the Twelve12 building at 4th and M, SE, at the Yards, which has its two residential towers topped out and its Harris Teeter space glassed in. Plus, it is also now seeing the glass being hung on the Vida Fitness/retail area at 4th and Tingey:
It will have 218 units, and the first move-ins are expected to happen by mid-year. This project is also where Sweetgreen and TaKorean will be located.
Meanwhile, the Toll Brothers building dubbed River Parc is racing right along, with five-plus of its 13 stories completed, helping to make the southwest corner of 1st and K look a teensy bit different than it did seven years ago:
This building will have 277 units, and is expected to begin leasing toward the end of 2014.
And up near the freeway, at New Jersey and I, the Park Chelsea is moving along, though the vertical progress of this 433-unit building is a bit slower than its smaller brethren. But as of now neighborhood eyes are probably more fixed on the completed paving of the new block of I Street between 2nd and New Jersey, though when the street will actually open to the public is not being trumpeted. (Spring 2014? Late 2014? We shall see!)
I think that, of the three, the Park Chelsea will have the biggest impact on the neighborhood skyline, both from on the ground (as you can now start to see in the various vantage points in the project's expanded before-and-after archive) as well as when looking into Near Southeast from the freeway. (And then it won't be too long until the Chelsea's sibling 800 New Jersey sneaks in just to its north and tweaks the views even further.). The downside is that a lot of views of the Capitol dome from Canal Park and Capitol Hill Tower are going to be lost to progress....
For more information/renderings for each project, and for more photos showing how these construction sites looked before work got underway, check out the Twelve12, River Parc, and Park Chelsea project pages. And join in with me in looking forward to the days starting to get longer, so that I can stop having to deal with the rotten winter sun angle and shadows.
Comments (0)
   
 
 More Recent News

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJBabyDaddy on Roundup of Some: Looks like the final piece of the final arch of the New Frederick Douglass Memor...
GarfieldPark on Roundup of Some: Wagtime has now turned into Dogtopia? New owners or what?
CJBabyDaddy on Roundup of Some: To my fellow New FDMB arch geeks: As of COB Friday, August 7, nine of the twelv...
CJBabyDaddy on Roundup of Some: La Famosa (1st floor of the Bower) targeting a late August or early September op...
GarfieldPark on Roundup of Some: Target date of Wed Aug 12th for I ST CVS. Can't come soon enough!
JES on Roundup of Some: It looks like punch bowl isn't completely dead, as they're reopening some locati...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
600 B/O L ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/10/20
800 B/O POTOMAC AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/09/20
1000 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/04/20
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/02/20
1100 B/O 2ND PLACE SE   BURGLARY
Burglary Two
 07/31/20
100 B/O I ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/30/20
100 B/O O ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/28/20
400 B/O M ST SE   THEFT
Shoplifting
 07/24/20
100 B/O M ST SE   BURGLARY
Burglary Two
 07/20/20
UNIT B/O N ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/20/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (theft From Building)
 07/13/20

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
07/22/20 
LA FAMOSA / null
E2009613 / SUPPLEMENTAL
1300 4TH ST SE 130   
07/24/20 
TOM AN / KIMOY LALLEMENT
A2005055 / CONSTRUCTION
New sail shade awning at exterior private space of La Famosa restaurant (Permit #TL2000028)
1150 5TH ST SE   
07/16/20 
DISTRICT OF COLUMBIA / null
P2007453 / SUPPLEMENTAL
   
07/22/20 
DISTRICT OF COLUMBIA / null
E2009571 / SUPPLEMENTAL
   
08/04/20 
DISTRICT OF COLUMBIA / KEVIN HURLEY
SB2000405 / CONSTRUCTION
We propose to perform 2 soil borings to maximum depths up to 50 feet below grade, or refusal. The borings will be advanced with a geotechnical drill rig, which utilizes 3.25" hollow stem augers. Upon completion, the borings will be backfilled with bentonite slurry, in general accordance with DOEE requirements.
10 I ST SE   
07/27/20 
CAPITOL HILL RACQUET CLUB / ANDREW ARNOLD; NA
SB2000413 / CONSTRUCTION
We propose drilling two (2), six-inch diameter geotechnical test borings (B-7 and B-8) using the hollow stem auger method to evaluate the subsurface conditions. The proposed test boring depths will be 85 feet below the existing ground surface. If a confining unit is encountered, outer casing will be installed which will extend 10 feet into the top of the confining unit or to the top of bedrock. Up...
150 I ST SE   
07/30/20 
SQUARE 737 LLC C/O WC SMITH / RUSSELL COX
B2007765 / CONSTRUCTION
Amendment to B1709058. Decrease number of dwelling units to 373 units. Construction of 2 spas. Electrical, Mechanical, Plumbing changes.
423 L ST SE   
07/24/20 
JOHN P LANG / MARGO RICKS
SOL2001665 / CONSTRUCTION
To install 4.56 kW size of solar panels with a system height of 1.1 feet on roof of building.
250 M ST SE   
07/21/20 
SQUARE 769 LLC / null
E2009527 / SUPPLEMENTAL
   
08/04/20 
SQUARE 769 LLC / BRIAN C STROTT; SQUARE 769 LLC
B1915078 / CONSTRUCTION
Revisions to permit B1813732. Changes to the roof area. Adding mechanical equipment to roof.
300 M ST SE   
07/27/20 
FEDERAL CENTER LP / null
E2009758 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
07/23/20 
GREYSTAR GP LLC / null
M2003144 / SUPPLEMENTAL
1105 NEW JERSEY AVE SE   
07/23/20 
GALLERY CAPITAL RIVERFRONT PROPERTY LLC / null
E2009620 / SUPPLEMENTAL
1200 NEW JERSEY AVE SE 20590   
08/05/20 
UNITED STATES OF AMERICA / null
E2010040 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
08/05/20 
US GOVERNMENT / null
E2010054 / SUPPLEMENTAL
   
08/07/20 
FC FACILITATOR LLC FOREST CITY REALTY TRUST / null
P2007950 / SUPPLEMENTAL
79 POTOMAC AVE SE 505   
07/15/20 
null / NA NA NA
EHOP20993669 / HOME OCCUPATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.