Since January, 2003
            
 Sliding from Before to After

Despite my subconscious desire to return to those days when I didn't bother going to public meetings, I ventured out on Wednesday night to DDOT's first quarterly public meeting on the Ward 6 Performance Parking Pilot Program. Much of the discussion centered on issues outside of Near Southeast (such as how Southwest's parking-enforcement hours still run from 7 am to midnight seven days a week, even though Capitol Hill rolled theirs back to 9:30 pm six days a week and no restrictions at all on Sundays), so I don't really have a lot to report in terms of any changes that might be happening to the streets south of the freeway and east of South Capitol.
There are a few numbers to pass along--so far in 2008 (from the start of the program on March 26 through the end of October) the Ward 6 pilot zone grossed a bit over $235,000 in parking fees, with it splitting pretty evenly between the 80 game days ($118k, averaging $1,650 per day) and the other non-game days ($115k, averaging $1,300 per day). However, it cost the city more than $860,000 to install the meters and signage, so the program isn't exactly operating in the black yet.
The current red visitors passes are scheduled to expire on Dec. 31--however, DDOT's Damon Harvey acknowledged that the realities of trying to send them out in late December (in the midst of the holiday mail deluge) and the issue of on-street parking enforcement for the inauguration means that it's likely DPW will be told to not consider the old passes expired until Feb. 1 or some other date.
There was really only one attendee who was vociferously against the pilot's restrictions; others who got up to spoke had concerns about portions of it, but given how these meetings can sometimes go, it seemed that most people were accepting of the program. DDOT's Harvey made sure to emphasize a number of times that this program is not just about ballpark parking--it's to get ahead of all of the expected development and commerce coming to Capitol Hill, Near Southeast, and Southwest, and protect resident and business parking before it gets out of hand.
There were no specific changes announced for 2009--however, it sounded like if there were changes they'd be put in place closer to Opening Day. Although most of the people who spoke at the meeting mentioned that they didn't really see any influx of ballpark-related on-street parking on the Hill or areas further away in Southwest, it would be wise to keep in mind two things for 2009: the possibility that the free Nats Express won't be running (no decision yet), and, on the flip side, the opening of two new office buildings within two blocks of the ballpark that will have three levels of underground parking that could become available (100 M and 55 M, and perhaps also the underground parking now being built in the hole just north of the ballpark, though there's been no announcements of whether any of these will be offering gameday parking). The potential lack of free parking could drive more fans to try to find on-street parking, but perhaps the growth of close-in garage spaces will mitigate that.
Tune in again in February when I'm sure the traffic and parking discussions will heat up for the new season! (Yippee.)
UPDATE: Don't miss my addendum, where I clear up that just because the meters haven't been paid for yet doesn't mean that the neighborhood won't already be seeing some of the revenue.
Comments (0)
   
 
 More About Nationals Park
 All posts: parking, Nationals Park

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

202_cyclist on Albi Opening This: There was soil boring activity this morning at the former taxi lot at New Jersey...
jdc on Retail Roundup: Concur with 202 - with Parc Riverside phase 2 and then DC Crossing finished, the...
Jscott280 on Albi Opening This: Fences up around parcel H. They are going to change the ingress points to N plac...
jdc on Albi Opening This: At 37 L, windows are going in and tower crane is gone. At Chiller site next door...
dcgent on Albi Opening This: UrbanTurf looks at what's coming housing wise for the area https://dc.urbanturf....
Shogungts on Albi Opening This: @Jason - not sure if that is the plan, but it would be nice. I went by there th...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1500 B/O SOUTH CAPITOL ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/24/20
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree - Felony (theft From Building)
 02/24/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/24/20
1200 B/O VAN ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/23/20
900 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 02/22/20
900 B/O 11TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/20
900 B/O M ST SE   BURGLARY
Burglary Two
 02/19/20
1200 B/O HALF ST SE   ROBBERY  02/18/20
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/20
400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  02/08/20
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/02/20
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/01/20
600 B/O VIRGINIA AVE SE   ASSAULT WITH A DANGEROUS WEAPON  01/29/20
1300 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/27/20

Recent Issued Building Permits Archive  
909 4TH ST SE   
02/12/20 
MEREDITH FASCETT / null
E2004655 / SUPPLEMENTAL
1300 4TH ST SE APT 214   
02/03/20 
null / NA NA NA
EHOP20983190 / HOME OCCUPATION
1021 5TH ST SE   
02/13/20 
KEVIN WILLIAMS / KEVIN WILLIAMS; KEVIN WILLIAMS
B2005053 / CONSTRUCTION
Apply for building permit to have final closing inspection for permit #B1602481 & B1602513 per inspector inspection report since these permits has expired.
150 I ST SE   
02/14/20 
SQUARE 737 LLC / JASON D DORRIS
AH2000818 / CONSTRUCTION
Construction of a new 13 story apartment building with three below grade parking levels, 1st floor retail, and amenity areas; 375 units and 181 parking spaces. To include mechanical, electrical, plumbing, elevators and structural work.
250 M ST SE   
02/14/20 
SQUARE 769 LLC / null
P2003901 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
01/30/20 
NEW JERSEY AT H LLC / MICHELLE GABBITAS
AH2000649 / CONSTRUCTION
Manhole rehabilitation on New Jersey, 2nd St and M St SE to repair 3 existing sewer manholes in DDOT ROW. Work will all be done through existing manholes (trenchless) and include lining, rebuilding and bypass of existing manholes.
1275 NEW JERSEY AVE SE 20003   
02/14/20 
BROOKFIELD PROPOERTIES / TIM GOOD
AH2000849 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Presidents Day, February 17, 2020. Operations would include below grade concrete and waterproofing activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am to 7pm period.
1275 NEW JERSEY AVE SE   
01/30/20 
UNITED STATES OF AMERICA / VINCENT J. BROWNING; VINCENT J. BROWNING
P2003449 / SUPPLEMENTAL
1-Oil / Sand interceptor
   
01/30/20 
US GOVERNMENT / null
E2004202 / SUPPLEMENTAL
   
02/07/20 
MILLER AND LONG / WILLIAM MOORE
AH2000699 / CONSTRUCTION
Afterhours to put up towercrane with mobile crane saturday 2 / 8 / 2020 and 2 / 9 / 2020 from 5am to 1159pm
1299 NEW JERSEY AVE SE   
02/18/20 
FOREST CITY SEFC LLC / STRAUCHON; SEE BELOW
BCIV1800153 / CONSTRUCTION
Phase 1A BCIV Permit Description - BCIV 1800153 - The subject BCIV permit is for the Phase IA development of Quander St SE, N Pl SE, and 1-1 / 2 St SE within the overall Forest City, Yards West (FCYW) development area which emphasizes: pedestrian-focused public realm, optimized utility corridor, fully integrated SWM design, and complete street and vision zero design. The FCYW Phase IA is comprised...
1322 PATTERSON AVE SE   
02/13/20 
JOINT BASE ANACOSTIA BOLLING - UNITED STATES NAVAL OBSERVATORY SI / TONYA HARRIS; TONYA HARRIS; TBD
BCIV2000046 / CONSTRUCTION
***FEDERAL PROPERTY*** PROJECT WILL CONSIST OF DREDGING THE EXISTING RETENTION POND AND INSPECTING AND CLEANING THE OUTLET CONTROL STRUCTURE (S1) LOCATED ON THE UNITED STATES NAVAL OBSERVATORY TO REMOVE SEDIMENT ACCUMULATION. CONTRACTOR SHALL AVOID THE CLEARING OF VEGETATION ON POND EMBANKMENTS AND SURROUNDING AREAS SO AS TO KEEP RESTORATION AND REPLANTING TO A MINIMUM.
71 POTOMAC AVE SE   
02/13/20 
MRP REALTY / JAMES VANEGAS
AH2000681 / CONSTRUCTION
Perform interior and exterior construction activities. New construction 14-story new residential multi-family building.
   
02/19/20 
RIVERFRONT HOLDINGS II, LLC / JUSTIN BISHOP; JUSTIN BISHOP
SP1900054 / CONSTRUCTION
Construct a 680 sqft concrete swimming pool inside an existing waterproofed structural box on the 14th floor. All MEP, decking and fencing work by other trades under separate permits.
227 TINGEY ST SE   
02/12/20 
GONE YARD HOTEL OWNER LLC / BOB BIROONAK; BOB BIROONAK
SG2000048 / CONSTRUCTION
one double face illuminated blade sign
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.