Last night the Zoning Commission voted 5-0 to extend the allowed building height and expand the total square footage of the proposed office building at 250 M Street in what is technically a modification to the Capper/Carrollsburg second-stage PUD that this office building is part of. The building, which will be going for LEED silver certification and which will have ground-floor retail, will now be 130 feet high and have 233,405 square feet of space. The discussions at the hearing centered mainly on the penthouse structure, the "next generation" elevator technology that allows for less overhead space, and how exactly the agreement with ANC 6D should be viewed.
William C. Smith's Brad Fennell testified that the developer has agreed to additional amenities beyond those in the original PUD (which included $325,000 toward the funding of Canal Park). He described the new amenities as "recruiting construction workers from ANC 6D by purchasing quarterly ads in the Southwester, creating an overall goal of 20% first-source employment for qualified ANC 6D residents, and providing contracting and new hiring opportunitiess for local residents and subcontractors by giving tiebreaking preferences to subcontractors headquartered in ANC 6D and for qualified construction workers living in that area." On May 12 the ANC tied 3-3 on the project, but apparently some subsequent tweaking of the proffer into this final form resulted in a letter from the ANC indicating that four commissioners would support the project with these additional amenities. The Zoning Commissioners felt that, since this was not an official vote of the ANC, it couldn't be given the required "great weight," but could be looked at the same as any feedback from a neighborhood association. The fact that no ANC members appeared at the hearing to testify in opposition also was noted.
You can read the Office of Planning report for all the specifics you could ever want about the changes in the design; if you're really interested, you can also read the original second-stage PUD approval of 250 M from last July, that last night's ruling is modifying. (The original Capper PUD is worth a look as well if you aren't familiar with what's been approved for the area's redevelopment.) Also, since I haven't mentioned it lately, it should be noted that this office building is technically a joint venture between WC Smith and the DC Housing Authority, with the monies from it helping to "financially leverage" the rest of the redevelopment of the Cappers.
This was the first vote; final action on this modification will be scheduled for a month or so from now. Earlier this year a WC Smith representative had told me that construction could begin in the middle of this year, but there was no mention of start dates at the hearing.
Comments (0)
   
 
 More About M Street

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

GarfieldPark on Inching from Quarantining: Whole Foods boarded up and closed. Harry's has also been boarded up, not sure if...
JD on Inching from Quarantining: Raze applications have been filed for the buildings on the west side of the 1000...
VelocityChris on Inching from Quarantining: The substance of the article doesn't add clarity to whether Half St SE will or w...
Sasq on Checking in From: @Jaal @jscott280 Hey neighbor! Last I was told, the 2nd floor "should"...
NavyYardGuy on Inching from Quarantining: https://dc.eater.com/2020/5/29/21274400/bammys-caribbean-restaurant-opening-menu...
NavyYardGuy on Inching from Quarantining: I'll try too. Link to Bammy's menu.
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
200 B/O M ST SE   BURGLARY
Burglary Two
 05/30/20
900 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/27/20
900 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/26/20
1000 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/24/20
1200 B/O VAN ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/23/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/20/20
1100 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/19/20
1100 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/19/20
1200 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/17/20
100 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/15/20
1200 B/O 4TH ST SE   ASSAULT WITH A DANGEROUS WEAPON  05/12/20
300 B/O WATER ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/07/20
100 B/O H ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/03/20
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/03/20

Recent Issued Building Permits Archive  
1300 4TH ST SE RU-1   
05/14/20 
AP BOWER RETAIL LLC / null
P2006042 / SUPPLEMENTAL
1300 4TH ST SE   
05/08/20 
null / ;
P2005886 / SUPPLEMENTAL
   
05/15/20 
null / ;
P2006066 / SUPPLEMENTAL
929 5TH ST SE   
05/18/20 
CHRISTOPHER D FRENCH / CHRIS FRENCH; HERCULES FENCE OF MARYLAND, LLC HERCULES FENCE OF
F2000461 / CONSTRUCTION
1. Removal and replacement of front metal fence and gate in kind.  2. Removal and partial relocation of existing 6' tall wood fence in rear patio. The fence is currently approx. 30" inside the rear property line, and we intend to move the fence to our rear property line. The work includes removal of existing wood gate that opens from neighbor's property to our property along shared property line ...
300 M ST SE 4TH FL   
05/05/20 
FEDERAL CENTER LP / ;
P2005798 / SUPPLEMENTAL
300 M ST SE   
05/14/20 
AMENTUM / null
E2007609 / SUPPLEMENTAL
111 N ST SE   
05/07/20 
BROOKFIELD PROPERTIES / MAHMOUD KHACHAN; NA
SB2000288 / CONSTRUCTION
Drill temporary eight soil borings to a depth of 80 each at the existing parking lot at 111 N Street SE, Washington DC. The diameter of the borings is 6 inches. The borings will be grouted upon completion in accordance with DCRA requirements as indicated in the work plan.
1111 NEW JERSEY AVE SE   
05/12/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E2007563 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
05/06/20 
UNITED STATES OF AMERICA / JUSTIN BELLOW; NA
B1913803 / CONSTRUCTION
PARCEL G PROJECT CONSISTS OF A NEW 12 STORY OFFICE BUILDING WITH STREET LEVEL RETAIL AND 2 LEVELS OF BELOW GRADE PARKING. 2 LEVEL PARKING APPROVED UNDER FOUNDATION TO GRADE FD1900047 & SHEETING AND SHORING SH1900050
   
05/19/20 
UNITED STATES OF AMERICA / null
M2002480 / SUPPLEMENTAL
   
05/19/20 
UNITED STATES OF AMERICA / null
P2006118 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.