Since January, 2003
            
 Sliding from Before to After

This week's Ballpark and Beyond column in the Post is my summary of ANC 6D's deliberations on the ballpark liquor license. It also references a meeting held last night between community leaders and city and team representatives (though my deadline was before the meeting, so the column couldn't actually include anything *from* the meeting).
The meeting included updates on the road improvements in the area and the Navy Yard Metro station upgrades, both of which are still on track to be basically done by opening day (the Metro station might "still need another coat of paint", it was said, but will be "serviceable").
The Nationals are still working out their parking plans, not only in terms of the lots near the ballpark but also the satellite parking at RFK, and all the additional planning that goes with it (traffic flow, signage, shuttle buses, drop off/pick up locations, etc.). It appears as of now that there might not be season-ticket-holder lots in Southwest at all, not even at Buzzards Point. There was also mention that stadium-goers will not be funneled through the South Capitol Street exit of the freeway--the team is going to try very hard to move fans through all the other close-by freeway exits, but not South Capitol Street.
Circulator buses will not be part of the transit plans for the first season. But they're planning plenty of bike racks around the ballpark perimeter, and are also still working on a bicycle "valet" parking service.
Also, there's tentative plans for two stadium job fairs, possibly on Feb. 2 and Feb. 26 (details still being worked out).
And, everybody knows that the first few games will be "a challenge."
The general tone of the meeting was more cooperative and collegial than some of these meetings have been in the past (maybe because Tommy Wells was there for the first part and everyone wanted to be on their best behavior). There's plans for more meetings and workshops between these "stakeholders" (I really hate that word) to try to hammer out the best plans for traffic, pedestrian flow, and "curbside management" (aka on-street parking) before it's all then unveiled to the community at public meetings. There was also agreement that the group should get together after the first homestand in April to talk about what works/what doesn't.
UPDATE: Speaking of public meetings, here is the official announcement about the Jan. 11 city council Committee on Economic Development oversight hearing on "Parking and Traffic Plan for the Nationals' Stadium." It contains information on how to testify at the hearing, if you're so inclined.
Comments (1)
   
 
 More Recent News

JDLand.com Home

Comments

IMGoph says: (12/20/07 10:35 AM)
oh thank goodness for bike parking! biking to RFK always meant finding a good signpost somewhere to latch things to in the hopes that the bike would still be there when i got out.

if there's going to have a bike valet, does that mean the bike parking will be secure (or at least have someone keeping half an eye on it)? that would just be amazing.

i was going to be glad to see bikers getting attention at all here, but this is surpassing expectations.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

202_cyclist on Albi Opening This: There was soil boring activity this morning at the former taxi lot at New Jersey...
jdc on Retail Roundup: Concur with 202 - with Parc Riverside phase 2 and then DC Crossing finished, the...
Jscott280 on Albi Opening This: Fences up around parcel H. They are going to change the ingress points to N plac...
jdc on Albi Opening This: At 37 L, windows are going in and tower crane is gone. At Chiller site next door...
dcgent on Albi Opening This: UrbanTurf looks at what's coming housing wise for the area https://dc.urbanturf....
Shogungts on Albi Opening This: @Jason - not sure if that is the plan, but it would be nice. I went by there th...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1500 B/O SOUTH CAPITOL ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/24/20
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree - Felony (theft From Building)
 02/24/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/24/20
1200 B/O VAN ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/23/20
900 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 02/22/20
900 B/O 11TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/20
900 B/O M ST SE   BURGLARY
Burglary Two
 02/19/20
1200 B/O HALF ST SE   ROBBERY  02/18/20
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/20
400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  02/08/20
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/02/20
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/01/20
600 B/O VIRGINIA AVE SE   ASSAULT WITH A DANGEROUS WEAPON  01/29/20
1300 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/27/20

Recent Issued Building Permits Archive  
909 4TH ST SE   
02/12/20 
MEREDITH FASCETT / null
E2004655 / SUPPLEMENTAL
1300 4TH ST SE APT 214   
02/03/20 
null / NA NA NA
EHOP20983190 / HOME OCCUPATION
1021 5TH ST SE   
02/13/20 
KEVIN WILLIAMS / KEVIN WILLIAMS; KEVIN WILLIAMS
B2005053 / CONSTRUCTION
Apply for building permit to have final closing inspection for permit #B1602481 & B1602513 per inspector inspection report since these permits has expired.
150 I ST SE   
02/14/20 
SQUARE 737 LLC / JASON D DORRIS
AH2000818 / CONSTRUCTION
Construction of a new 13 story apartment building with three below grade parking levels, 1st floor retail, and amenity areas; 375 units and 181 parking spaces. To include mechanical, electrical, plumbing, elevators and structural work.
250 M ST SE   
02/14/20 
SQUARE 769 LLC / null
P2003901 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
01/30/20 
NEW JERSEY AT H LLC / MICHELLE GABBITAS
AH2000649 / CONSTRUCTION
Manhole rehabilitation on New Jersey, 2nd St and M St SE to repair 3 existing sewer manholes in DDOT ROW. Work will all be done through existing manholes (trenchless) and include lining, rebuilding and bypass of existing manholes.
1275 NEW JERSEY AVE SE 20003   
02/14/20 
BROOKFIELD PROPOERTIES / TIM GOOD
AH2000849 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Presidents Day, February 17, 2020. Operations would include below grade concrete and waterproofing activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am to 7pm period.
1275 NEW JERSEY AVE SE   
01/30/20 
UNITED STATES OF AMERICA / VINCENT J. BROWNING; VINCENT J. BROWNING
P2003449 / SUPPLEMENTAL
1-Oil / Sand interceptor
   
01/30/20 
US GOVERNMENT / null
E2004202 / SUPPLEMENTAL
   
02/07/20 
MILLER AND LONG / WILLIAM MOORE
AH2000699 / CONSTRUCTION
Afterhours to put up towercrane with mobile crane saturday 2 / 8 / 2020 and 2 / 9 / 2020 from 5am to 1159pm
1299 NEW JERSEY AVE SE   
02/18/20 
FOREST CITY SEFC LLC / STRAUCHON; SEE BELOW
BCIV1800153 / CONSTRUCTION
Phase 1A BCIV Permit Description - BCIV 1800153 - The subject BCIV permit is for the Phase IA development of Quander St SE, N Pl SE, and 1-1 / 2 St SE within the overall Forest City, Yards West (FCYW) development area which emphasizes: pedestrian-focused public realm, optimized utility corridor, fully integrated SWM design, and complete street and vision zero design. The FCYW Phase IA is comprised...
1322 PATTERSON AVE SE   
02/13/20 
JOINT BASE ANACOSTIA BOLLING - UNITED STATES NAVAL OBSERVATORY SI / TONYA HARRIS; TONYA HARRIS; TBD
BCIV2000046 / CONSTRUCTION
***FEDERAL PROPERTY*** PROJECT WILL CONSIST OF DREDGING THE EXISTING RETENTION POND AND INSPECTING AND CLEANING THE OUTLET CONTROL STRUCTURE (S1) LOCATED ON THE UNITED STATES NAVAL OBSERVATORY TO REMOVE SEDIMENT ACCUMULATION. CONTRACTOR SHALL AVOID THE CLEARING OF VEGETATION ON POND EMBANKMENTS AND SURROUNDING AREAS SO AS TO KEEP RESTORATION AND REPLANTING TO A MINIMUM.
71 POTOMAC AVE SE   
02/13/20 
MRP REALTY / JAMES VANEGAS
AH2000681 / CONSTRUCTION
Perform interior and exterior construction activities. New construction 14-story new residential multi-family building.
   
02/19/20 
RIVERFRONT HOLDINGS II, LLC / JUSTIN BISHOP; JUSTIN BISHOP
SP1900054 / CONSTRUCTION
Construct a 680 sqft concrete swimming pool inside an existing waterproofed structural box on the 14th floor. All MEP, decking and fencing work by other trades under separate permits.
227 TINGEY ST SE   
02/12/20 
GONE YARD HOTEL OWNER LLC / BOB BIROONAK; BOB BIROONAK
SG2000048 / CONSTRUCTION
one double face illuminated blade sign
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.