From Saturday's Post: "Under a clear blue sky perfect for a baseball game, 500 construction workers responsible for one of the most expensive and most important projects in the District took a break yesterday for a quick pep talk. 'The closer we get to next year, the more people are looking at us to bring this project in on time and on budget,' Mayor Adrian M. Fenty told them on his first trip to the stadium site near the Navy Yard and South Capitol Street in Southeast." And while the article is based around Fenty's visit, the meat of it is really about the handoff of responsibility for ensuring the ballpark opens on time from outgoing DCSEC chair Allen Lew (heading off to try to repair the DC schools) to his replacement, Greg O'Dell.
Some quotes:
* "Lew said this week that the ballpark is on schedule, and remains within budget, with no indication that will change."
* " 'I'm going to be involved in this a lot more than I was," said [council member Jack] Evans, who keeps a small countdown clock on his desk, showing the number of days, hours and minutes until the anticipated first pitch at the stadium next April. 'I had kind of taken a step back because of the confidence I had that Allen would get this thing done. There was no need for me to be calling everybody up every week, saying: 'Where are we? Where are we?' But now I'm going to reinsert myself in terms of being in the loop constantly.' "
* "The stadium's steel framework and concrete seating decks are largely in place, as are miles and miles of ducts, electrical wires and pipes. Workers are drilling tens of thousands of holes in the decks to anchor seats. And a 200-foot tower crane has been erected to lift concrete and other materials for construction of a Nationals office building. Next month, workers plan to complete the steel framework for the ballpark's restaurant and main scoreboard and to start putting in the stadium seats. The project's schedule calls for installation of the scoreboard to begin in August. Then, in October, sod will be laid. The grass will take root before going dormant during the winter and then spring to life for Opening Day." [Dedicated readers of JDLand know all this already, of course!]
* "Still, problems remain, including a long-vexing issue that O'Dell will inherit when he takes control of the project. 'The biggest thing still out there,' Lew said, 'is coming up with an inventory of parking spaces to meet game day requirements.' " (The article says that 9,200 spaces will be needed; the March transporation presentation and various Office of Planning documents have been quoting 4,900 as the maximum needed for a sellout game. I guess when the draft Transporation Operations and Parking Plan comes out [Any Minute Now!], we'll see what the real number is.)
Read the entire article for additional details. And of course you can look at my stadium construction photo galleries or the official webcam if you want to see what it's looking like.
Comments (0)
   
 
 More About Nationals Park
 All posts: parking, Nationals Park

JDLand.com Home

Comments

Sorry, comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

Jscott280 on Checking in From: @SWneighbor - how does one post a picture on this thread. I have pics of Half St...
SWneighbor on Checking in From: Could someone please post a few photos of half street as it is now? I am stuck ...
jdc on Inching from Quarantining: My fingers are crossed for the neighborhood, which I have not seen since mid-Mar...
JD on Checking in From: I have not heard anything about Half Street going full pedestrian all the time. ...
VelocityChris on Checking in From: @sasq excellent, I hope it's true, surprised it hasn't been announced, even if i...
Sasq on Checking in From: @velocitychris I saw one of the foreman and asked. He confirmed that it would be...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1000 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/24/20
1200 B/O VAN ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/23/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/20/20
1100 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/19/20
1100 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/19/20
1200 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/17/20
100 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/15/20
1200 B/O 4TH ST SE   ASSAULT WITH A DANGEROUS WEAPON  05/12/20
300 B/O WATER ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/07/20
100 B/O H ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/03/20
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/03/20
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/28/20
400 B/O M ST SE   THEFT
Theft First Degree (theft From Building)
 04/24/20

Recent Issued Building Permits Archive  
1300 4TH ST SE RU-1   
05/14/20 
AP BOWER RETAIL LLC / null
P2006042 / SUPPLEMENTAL
1300 4TH ST SE   
05/08/20 
null / ;
P2005886 / SUPPLEMENTAL
   
05/15/20 
null / ;
P2006066 / SUPPLEMENTAL
929 5TH ST SE   
05/18/20 
CHRISTOPHER D FRENCH / CHRIS FRENCH; HERCULES FENCE OF MARYLAND, LLC HERCULES FENCE OF
F2000461 / CONSTRUCTION
1. Removal and replacement of front metal fence and gate in kind.  2. Removal and partial relocation of existing 6' tall wood fence in rear patio. The fence is currently approx. 30" inside the rear property line, and we intend to move the fence to our rear property line. The work includes removal of existing wood gate that opens from neighbor's property to our property along shared property line ...
300 M ST SE 4TH FL   
05/05/20 
FEDERAL CENTER LP / ;
P2005798 / SUPPLEMENTAL
250 M ST SE   
04/29/20 
SQUARE 769 LLC / TAMIKA STATON; OTIS
EN2001825 / SHOP DRAWING
Install 3 New Elevators - 3500Lbs @ 350FPM - Elevators 1 - 2 and 4
   
04/29/20 
SQUARE 769 LLC / TAMIKA STATON; OTIS
EN2001826 / SHOP DRAWING
Install 1 New Elevator - 4000Lb @ 350FPM - Elevator 3
   
04/29/20 
SQUARE 769 LLC / BRIAN C STROTT; NA
TL2000026 / CONSTRUCTION
9 story 173,125 GSF tenant improvement fit out.
   
04/29/20 
SQUARE 769 LLC / TAMIKA STATON; OTIS
EN2001827 / SHOP DRAWING
Install 2 New Elevators - 3500LB @ 200FPM - Elevators 5-6
300 M ST SE   
04/30/20 
FEDERAL CENTER LP / SAM HOLLEN; TBD
B2006591 / CONSTRUCTION
INTERIOR RENOVATION TO 5TH FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MEP AND LIFE SAFETY. NO STRUCTURAL. 4499 SQUARE FEET. NTT DATA.
   
05/01/20 
FEDERAL CENTER LP / null
E2007254 / SUPPLEMENTAL
   
05/14/20 
AMENTUM / null
E2007609 / SUPPLEMENTAL
111 N ST SE   
05/07/20 
BROOKFIELD PROPERTIES / MAHMOUD KHACHAN; NA
SB2000288 / CONSTRUCTION
Drill temporary eight soil borings to a depth of 80 each at the existing parking lot at 111 N Street SE, Washington DC. The diameter of the borings is 6 inches. The borings will be grouted upon completion in accordance with DCRA requirements as indicated in the work plan.
1111 NEW JERSEY AVE SE   
05/12/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E2007563 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
05/06/20 
UNITED STATES OF AMERICA / JUSTIN BELLOW; NA
B1913803 / CONSTRUCTION
PARCEL G PROJECT CONSISTS OF A NEW 12 STORY OFFICE BUILDING WITH STREET LEVEL RETAIL AND 2 LEVELS OF BELOW GRADE PARKING. 2 LEVEL PARKING APPROVED UNDER FOUNDATION TO GRADE FD1900047 & SHEETING AND SHORING SH1900050
   
05/19/20 
UNITED STATES OF AMERICA / null
M2002480 / SUPPLEMENTAL
   
05/19/20 
UNITED STATES OF AMERICA / null
P2006118 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.