As part of the path toward the planned reopening next fall of Van Ness Elementary School at 5th and M streets, SE, DCPS has scheduled public meetings on Nov. 18 and Nov. 20 for residents in Near Southeast and Southwest to learn about the plans for the school, and to be able to provide feedback on those plans.
These sessions follow a meeting back in September between parents' groups and Dr. Nathaniel Beers, DCPS's head of specialized instruction, in which the parents were displeased with some of the information coming from the school system, specifically the plans to not have a principal in place during the planning process, and also DCPS's intent to open the school with only two PK-3 and two PK-4 classrooms, and no kindergarten.
A subsequent communication from Dr. Beers to the Van Ness Parents Group indicated, however, that an "Executive Director" will be put in place in early 2015, a person "whose primary responsibilities are to functioning as the leader of Van Ness, including engaging deeply with future parents and community members and actively recruiting students to ensure Van Ness opens fully enrolled."
In addition, the plea from parents for kindergarten offerings in the initial 2015-16 school year was not fully ignored, with DCPS agreeing to review community analysis data again before making a final decision. This has the parents' group working hard to find kindergarten-age children who could be sent to Van Ness in 2015.
These meetings should also have some information on the School Improvement Team process for the school going forward.
The meeting schedule:
* Tuesday, Nov. 18, from 6 to 8 pm, at Van Ness Elementary; and
* Thursday, Nov. 20, from 6 to 8 pm at the James Creek Resident Council Office, 100 N St. SW.
Comments (0)
   
 
 More About Van Ness Elementary

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

Jscott280 on Roundup of Some: @TJ31 - yea envy is finally doing closings. Good luck on that estimate, we were ...
TJ31 on Roundup of Some: Did envy open up ? Avidian is at October now.
CJBabyDaddy on Roundup of Some: Looks like the final piece of the final arch of the New Frederick Douglass Memor...
GarfieldPark on Roundup of Some: Wagtime has now turned into Dogtopia? New owners or what?
CJBabyDaddy on Roundup of Some: To my fellow New FDMB arch geeks: As of COB Friday, August 7, nine of the twelv...
CJBabyDaddy on Roundup of Some: La Famosa (1st floor of the Bower) targeting a late August or early September op...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
600 B/O L ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/10/20
800 B/O POTOMAC AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/09/20
1000 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/04/20
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/02/20
1100 B/O 2ND PLACE SE   BURGLARY
Burglary Two
 07/31/20
100 B/O I ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/30/20
100 B/O O ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/28/20
400 B/O M ST SE   THEFT
Shoplifting
 07/24/20
100 B/O M ST SE   BURGLARY
Burglary Two
 07/20/20
UNIT B/O N ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/20/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (theft From Building)
 07/13/20

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
07/22/20 
LA FAMOSA / null
E2009613 / SUPPLEMENTAL
1300 4TH ST SE 130   
07/24/20 
TOM AN / KIMOY LALLEMENT
A2005055 / CONSTRUCTION
New sail shade awning at exterior private space of La Famosa restaurant (Permit #TL2000028)
1150 5TH ST SE   
07/16/20 
DISTRICT OF COLUMBIA / null
P2007453 / SUPPLEMENTAL
   
07/22/20 
DISTRICT OF COLUMBIA / null
E2009571 / SUPPLEMENTAL
   
08/04/20 
DISTRICT OF COLUMBIA / KEVIN HURLEY
SB2000405 / CONSTRUCTION
We propose to perform 2 soil borings to maximum depths up to 50 feet below grade, or refusal. The borings will be advanced with a geotechnical drill rig, which utilizes 3.25" hollow stem augers. Upon completion, the borings will be backfilled with bentonite slurry, in general accordance with DOEE requirements.
10 I ST SE   
07/27/20 
CAPITOL HILL RACQUET CLUB / ANDREW ARNOLD; NA
SB2000413 / CONSTRUCTION
We propose drilling two (2), six-inch diameter geotechnical test borings (B-7 and B-8) using the hollow stem auger method to evaluate the subsurface conditions. The proposed test boring depths will be 85 feet below the existing ground surface. If a confining unit is encountered, outer casing will be installed which will extend 10 feet into the top of the confining unit or to the top of bedrock. Up...
150 I ST SE   
07/30/20 
SQUARE 737 LLC C/O WC SMITH / RUSSELL COX
B2007765 / CONSTRUCTION
Amendment to B1709058. Decrease number of dwelling units to 373 units. Construction of 2 spas. Electrical, Mechanical, Plumbing changes.
423 L ST SE   
07/24/20 
JOHN P LANG / MARGO RICKS
SOL2001665 / CONSTRUCTION
To install 4.56 kW size of solar panels with a system height of 1.1 feet on roof of building.
250 M ST SE   
07/21/20 
SQUARE 769 LLC / null
E2009527 / SUPPLEMENTAL
   
08/04/20 
SQUARE 769 LLC / BRIAN C STROTT; SQUARE 769 LLC
B1915078 / CONSTRUCTION
Revisions to permit B1813732. Changes to the roof area. Adding mechanical equipment to roof.
300 M ST SE   
07/27/20 
FEDERAL CENTER LP / null
E2009758 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
07/23/20 
GREYSTAR GP LLC / null
M2003144 / SUPPLEMENTAL
1105 NEW JERSEY AVE SE   
07/23/20 
GALLERY CAPITAL RIVERFRONT PROPERTY LLC / null
E2009620 / SUPPLEMENTAL
1200 NEW JERSEY AVE SE 20590   
08/05/20 
UNITED STATES OF AMERICA / null
E2010040 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
08/05/20 
US GOVERNMENT / null
E2010054 / SUPPLEMENTAL
   
08/07/20 
FC FACILITATOR LLC FOREST CITY REALTY TRUST / null
P2007950 / SUPPLEMENTAL
79 POTOMAC AVE SE 505   
07/15/20 
null / NA NA NA
EHOP20993669 / HOME OCCUPATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.