Saturday was a lovely day for taking a couple of walks with camera in hand, and with work underway at locations that couldn't be any closer to my out-of-neighborhood house, I had no excuse to not get some updated photos of 225 Virginia/200 I, Capitol Quarter Phase 2, Canal Park, and the Little Red Building. (It was also nice chatting with the folks who correctly guessed that the oddball standing in the middle of the street taking photos must have been me.)
The showy demolition work is now well underway at 225 Virginia/200 I, and if the few shots and renderings on the project page aren't enough for you, you can do a virtual walk around the block to see which walls and windows are blown out at this point and to compare the current images with their "befores."
No time is being wasted at Capitol Quarter, where framing has now wrapped around from I to 3rd to K Street on the first block of Phase 2. You can take a "walk" around that block, too, if you haven't lately, or wander through the project page, both of which have plenty of images of the old Capper public housing buildings that were on this block for a very long time. I also added to the database some photos of what will eventually be the intersection of 3rd Place and L, once the new street gets built through its second block south of K. If you're big on old Capper photos, there's a few "before" images of L Street buildings in that sent that haven't been displayed on the site before now.
If photographs of fences are your thing, take a "walk" around the Canal Park perimeter, to see many pictures of the "traffic control" now in place in advance of the start of construction on the park (presuming it ever actually comes). Those barriers are going to put a crimp in some of my standard shooting locations for the next year or so, including where I've stood for the past eight years to take photographs of the Little Red Building, which in its new incarnation is now more of a brick red than the beet red it used to be. ANC commissioner Garber posted on Friday that the roof is going in over the next few days, at which point work on the interior can begin, as it slowly progresses toward becoming "Lot 38 Espresso."
Remember that the Click to see all available photos of this location.icon on any page gets you to the full batch of photos I've taken at any location (which, since I'm getting into the eighth year of doing this, can be kind of voluminous in some spots).
(I know that It seems kind of odd to still be posting photos when so many readers now live in the neighborhood, which of course wasn't always the case. But it's my schtick, and so I continue onward! Plus. there are plenty of people interested in Near Southeast who don't wander around every day--or maybe some of the residents don't know what these spots used to look like before....)
Comments (6)
   
 
 More About 225 Virginia/Old Post Plant/200 I

JDLand.com Home

Comments

Gary Karr says: (3/20/11 11:59 AM)
Or readers who are thinking about moving into the neighborhood...:-)


G says: (3/21/11 4:36 PM)
Must have been fun taking out those windows / walls on old Washington Star plant!


southwillriseagain says: (3/22/11 1:15 PM)
I am thinking that Canal Park might have its Federal funding taken away.

It has been 4 years since Eleanor Norton and surrounding developers got federal funding for Canal Park. They had a design..."ready to go." They had to redesign it to bring it to their budget 3 years ago. I am disappointed there is still no site activity although groundbreaking was 6 months ago. I want to see Canal Park built but I fear that with Republicans looking for every dollar to cut out of the budget, Federal funding will be lost (if it has not been lost already)...Can't we get moving with this project? What in the world can be holding it up for so long?

Could you give a history of Canal Park on your website?
(Thank God for the Yards Park!!!!)


JD says: (3/22/11 1:25 PM)
First off, I'm pretty sure there's no federal funding for Canal Park, or if there is, it's a very small portion of the total. There's city funding, money from the USDOT payment-in-lieu-of-taxes (PILOT) fund, some bond monies for infrastructure work, and some private funds.

I don't think they would have put up the barricades to close streets if they weren't very close to starting construction.

Could I give a history of Canal Park? link link

Start reading. :) You can start at the end and work forward if you want, to help correct your timeline a bit.




Ben in SE says: (3/22/11 1:47 PM)
And I am pretty sure they were tearing up the M Street block yesterday, so construction has already started.


MJM says: (4/5/11 10:17 PM)
Did Canal Park lose their funding again? Doesn't appear to have been any progress over the last week or so. They tore up some of the black-top and the little bob-cats have since disappeared unless they are on the same schedule as the LRB II.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJ1 on Inching from Quarantining: Oh wow... I live at Ore82 and didn't know about any of this.
GarfieldPark on Inching from Quarantining: @JD: Apparently, ORE will be eliminating (or making them smaller) some of it's ...
JD on Inching from Quarantining: Some interesting design notes found in the approved building permit for the thre...
KEWEE on Inching from Quarantining: Jeni's Splendid Ice Creams is coming to the retail space located at The Bower co...
CJBabyDaddy on Inching from Quarantining: Serious workplace accident on the ground this morning at the Chemonics construct...
MJM on Inching from Quarantining: Welcome to the neighborhood Pivot Physical Therapy. Its located behind Sprint (w...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/06/20
1200 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/05/20
100 B/O H ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/03/20
100 B/O O ST SE   ROBBERY  07/03/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 06/28/20
1200 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 06/25/20
1200 B/O SOUTH CAPITOL ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 06/23/20
1200 B/O NEW JERSEY AVE SE   ASSAULT WITH A DANGEROUS WEAPON
Assault W/i To Kill
 06/20/20
1000 B/O 3RD PLACE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/18/20
800 B/O SOUTH CAPITOL ST SE   ASSAULT WITH A DANGEROUS WEAPON  06/14/20
400 B/O M ST SE   THEFT
Shoplifting
 06/12/20
1000 B/O M ST SE   ROBBERY
Unarmed Carjacking
 06/09/20
UNIT B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  06/07/20

Recent Issued Building Permits Archive  
1300 4TH ST SE RU-2   
06/18/20 
AP BOWER RETAIL LLC / MELISSA BRENT
SG2000335 / CONSTRUCTION
Install 1 illuminated wall sign & 1 illuminated blade sign - JENIs ICE CREAM
150 I ST SE   
06/15/20 
SQUARE 737 LLC / BOB BIROONAK; NA; NA
SG2000323 / CONSTRUCTION
two illuminated building sign
151 M ST SE   
06/18/20 
BROOKFIELD PROPERTIES / CHRIS CRESCI; NA
SB2000292 / CONSTRUCTION
WSP will be advancing approximately 50 soil borings to 30 feet, and an additional 8 borings to 4 feet via direct push. A water sample will be collected from 3 of the deep borings. All borings will be abandoned via bentonite grout mix. Investigation derived waste will be stored in DOT 55-gallon steel drums. Private and public utility locating will take place prior to the work beginning
250 M ST SE   
06/19/20 
WILLIAM C SMITH / null
E2008622 / SUPPLEMENTAL
   
06/24/20 
SQUARE 769 LLC / null
M2002834 / SUPPLEMENTAL
   
06/24/20 
SQUARE 769 LLC / null
P2006931 / SUPPLEMENTAL
300 M ST SE   
06/16/20 
FEDERAL CENTER LP / null
E2008501 / SUPPLEMENTAL
   
06/18/20 
FEDERAL CENTER LP / null
E2008587 / SUPPLEMENTAL
111 N ST SE   
06/16/20 
BROOKFIELD PROPERTIES / NA; CHRIS CRESCI
SB2000293 / CONSTRUCTION
WSP will advance 22 soil borings to 25 feet and 8 soil borings to 4 feet via direst push. A groundwater sample will be collected from 2 of the deep borings by installing a temporary well to be in the ground for just a couple hours. Borings will be backfilled with bentonite / grout mix. IDW will be stored in DOT 55-gallon drums. A private and public utility mark out will be completed prior to b...
861 NEW JERSEY AVE SE   
06/10/20 
CXS TRANSPORTATION INC / ;
P2006604 / SUPPLEMENTAL
   
06/19/20 
CXS TRANSPORTATION INC / ;
P2006843 / SUPPLEMENTAL
   
06/22/20 
GREYSTAR GP LLC / KIM MITCHELL
B1903035 / CONSTRUCTION
The proposed project is three structures which are connected by a shared below-grade garage, which is one story deep on the east half of the site and two stories deep on the west half of the site. Two structures will be residential, with a total of 756 units, and the third will be a 225-key hotel. The west residential structure (Building 3) is planned to be 13 stories with ground and roof level am...
   
06/25/20 
CXS TRANSPORTATION INC / ;
P2006972 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
06/10/20 
SQUARE 742 LLC, C/O SPAULDING & SLYE/STE 100, / PAUL WHITLEY
AN1900284 / CONSTRUCTION
PROJECT CONSISTS OF: REMOVING: (2) EXISTING EQUIPMENT CABINETS, (3) EXISTING ANTENNA'S, (1) EXISTING RRU'S AND ANCILLARY EQUIPMENT / CABLE AND INSTALLING: (6) PROPOSED ANTENNA'S, (3) PROPOSED RRU'S, AND(2) PROPOSED EQUIPMENT CABINETS ON AN EXISTING TELECOM FACILITY
1111 NEW JERSEY AVE SE   
06/12/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TRACIE CLAXTON; NA; NA
SG2000257 / CONSTRUCTION
One Wall Mounted Sign illuminated
   
06/24/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P2006938 / SUPPLEMENTAL
401 WATER ST SE   
06/18/20 
BROOKFIELD PROPERTIES / CHRIS CRESCI
SB2000294 / CONSTRUCTION
WSP will advance 23 soil borings to 30 feet and 8 additional borings to 4 feet using direct push. A groundwater sample will be collected from 2 of the deep borings by installing a temporary well. Soil boirngs will be abandoned with bentonite / grout mix. IDW will be stored for disposal in DOT 55-gallon drums. A private and public utility mark out will be completed priot to starting intrusive w...
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.