At Monday night's Zoning Commission meeting, the commissioners voted 3-0 after a brief discussion to approve a request by the DC Housing Authority and the
Capper/Carrollsburg redevelopers to extend (again) the approved timeline for the long-planned
Community Center at Fifth and K. The commissioners saw letters of support from both ANC 6B and 6D (you can
see 6D's letter here), and seemed appeased by the notion that the $7-plus million required to build the center is figured into the $25 million that DCHA plans to eventually receive from a second bond offering (after the
$29 million one late last year that's paying for infrastructure improvements), once the market improves.
In return for 6D's support for the time extension, the Housing Authority agreed to
a number of conditions, mainly having to do with status reports and project updates, but also agreed (according to the letter) to "work with the ANC, D.C. Department of Parks and Recreation, and the Marine Corps to implement the agreement governing use of the Marine Corps' playing fields for the community." This is apparently a reaction to attempts to gain wider public access than is currently given to the fields at
7th and Virginia barracks as was originally agreed to when DCHA transferred that land to the Marines back in 1999.
The new time extension for the community center calls for building permit applications to be filed by July 1, 2012, with construction having to begin within 12 months of that date.