Please note that JDLand is no longer being updated.
peek >>
Near Southeast DC Past News Items: zoning
In the Pipeline
25 M
Yards/Parcel I
Chiller Site Condos
Yards/Parcel A
1333 M St.
More Capper Apts.
Yards/DC Water site
New Marine Barracks
Nat'l Community Church
Factory 202/Yards
SC1100
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)
 
Go to Full Blog Archive


302 Blog Posts Since 2003
Go to Page: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 ... 31
Search JDLand Blog Posts by Date or Category

I wasn't able to see the meeting myself (I was at Madison Square Garden watching my beloved Roger Federer beat Pete Sampras), but on Monday night the Zoning Commission gave its approval on the Capitol Gateway Overlay Review for 1111 New Jersey Avenue, Donohoe's 220,000-square-foot office building to be built just north of the east entrance of the Navy Yard Metro station. At the first part of this hearing a few weeks ago, there was much back-and-forth about whether the garage entrance should be on New Jersey Avenue (the developer's preference) or in the alley (DDOT's preference, which was not looked on fondly by the zoning commissioners). My sources tell me that DDOT has "somewhat grudgingly" agreed to allow the entrance to be on New Jersey after all, but that they expect Donohoe to work with them to better manage the public space on New Jersey and probably reduce the amount of parking offered. The web site for the project says that it will be completed in 2010, which would probably mean a start date later this year; we shall see if that indeed comes to pass. Read more about the previous discussion on the garage entrance and on what exactly a CG Overlay Review is, if you're wanting more information.
Hopefully soon I can post an update on what happened at ANC 6D on Monday, the *other* meeting I missed while in New York.
 

* I mentioned this a few days back, but why not pass along another reminder that Monday at 7 pm is the ANC 6D monthly meeting, with presentations and votes on 401 M Street, the ballpark traffic management plan, and the South Capitol Street Draft EIS, plus a briefing by the Nats on the Opening Day "Fan Fest" activities. To get in on the fun, go to St. Augustine's Episcopal Church at 6th and M St., SW, starting at 7 pm.
* If the ANC isn't your bag, you can watch the Zoning Commission take up again the Capitol Gateway Overlay Review for Donohoe's planned office building at 1111 New Jersey. It's a continuation of the last hearing, which revolved mostly around whether the garage access would be from New Jersey or from the alley. The hearing starts at 6:00 pm, and 1111 is also on the public meeting agenda at 6:30 pm, which perhaps is a display of optimism that Donohoe and DDOT will have the garage issue straightened out and the review ruling can be made. Watch the webcast, if you're so inclined. (I'm going to be missing both of these meetings, so it might be a few days before I can get the scoop on them.)
* The new Enhanced Residential Parking Permit signs, which allow non-Zone 6 parking only on one side of the street in certain areas near the ballpark, continue to get installed. They came to my street north of the freeway within the past day or so.
* I thought I did good with last week's find of a November 2006 satellite photo of the neighborhood, but reader JK has upped the ante with the "Bird's-Eye View" option at Microsoft Live Search, showing not-real-high-up images from March 2007. But be careful when you're scrolling around--if you go to fast, the images flip back to shots from early 2003. (Which is festive in its own fun-house kind of way.)
 

Beginning the trek through the approvals process are the first new-construction buildings planned for The Yards--a 320,000-square-foot office building at 401 M Street and a 170ish-unit apartment building to its south at 400 Tingey Street. They would both have ground-floor retail, but it's what's planned for 401 M that will probably have everyone's attention, because a grocery store is proposed for that space, just inside the historic wall and sentry tower on the southeast corner of Fourth and M. (No, which grocery store it could be hasn't been announced yet.) Recent documents have said that 401 M could begin construction in late 2008, with delivery in 2010; the residential building's start depends on "market conditions." (Uh-oh.) A few more early renderings are on my 401 M/400 Tingey page. (See my Yards First Phase page for information on the retail and residential projects that are getting underway this year.)
There's a Zoning Commission Southeast Federal Center Overlay Review of the plans scheduled for April 17, and ANC 6D will be voting on whether to support the project at its March 10 meeting.
Also at Monday's ANC 6D meeting will be presentations and votes on plans for the Opening Day Fan Fest at the ballpark, the ballpark Transportation and Residential Curbside Management Plan (formerly known as the TOPP), and the South Capitol Street Draft Environmental Impact Statement. I attended Wednesday night's public meeting on the Draft EIS, and while the slides from the meeting haven't yet been posted on its web site, the DEIS's executive summary is a good substitute for the information that was available at the meeting--you can read my summary of the plans as well. There wasn't much public comment (maybe seven or eight speakers), and the concerns seemed to be more about making sure DDOT does a good job of handling the inconveniences and resident issues as a result of the planned changes, rather than any real opposition to the plans themselves. The public comment period ends March 31, and the Final EIS is expected to come out late this year.
Alas, I won't be able to attend this ANC meeting that's so chock full of Near Southeast goodness. But I'm guessing that spending that evening watching the Roger Federer-Pete Sampras exhibition at Madison Square Garden might be a bit more enjoyable.
 

My Ballpark and Beyond column in today's District Extra of the Post covers last week's release of the Draft Environmental Impact Statement for South Capitol Street, the impending closure of Metro's Southeastern Bus Garage at Half and M, tonight's zoning hearing on allowing additional temporary surface parking lots in Southwest, and a reminder about today's ballpark job fair.
(And I've been under the weather the past few days, hence the somewhat brief updates.)
 

At Monday's ANC 6D meeting (which I missed because I had three meetings on my calendar for that night and the ANC never released an agenda for me to know whether I should go or not), there was apparently a big discussion of Zoning Case 07-08A, scheduled to be heard on Feb. 21, which seeks to allow temporary surface parking lots for no more than five years on a series of blocks in Southwest, mainly in Buzzards Point (squares 603, 605, 658, 661, 662, 662E, 664, 664E, and Square 658, Lot 7 for those of you with tax parcel maps handy, or look on the last page of this). A temporary emergency version of this text amendment passed with no discussion back in October; the Feb. 21 hearing is to make the amendment good for five years.
When the original case (07-08) establishing the ability to build temporary lots on a number of blocks in Near Southeast was passed, parking lots did not automatically appear on every block covered in the amendment. However, ANC 6D and residents of Southwest are apparently viewing this new amendment as the city going back on a promise to not build any parking lots in Southwest. Here is the ANC 6D resolution.
I've been at meetings over the past few months where city and team officials have said that there would be no ballpark parking offered in Buzzards Point this season because of the lack of sidewalks, streetlamps, and other improvements; the Office of Planning report for Case 07-08A says: "The Nationals have advised OP that, to date, no agreements with owners of individual lots have been reached so it is not likely that any of the temporary parking will be located on these sites prior to opening day in 2008[.]" I'm checking with the Nationals to see if this has changed. But certainly Buzzards Point would be still be viewed as a prime location for additional surface parking, if it's needed.
It's anticipated that the need for temporary surface lots will lessen as new buildings go up near the ballpark; in the next two years or so, underground garages that could potentially offer additional stadium parking will open at Monument Half Street, 100 M, 1015 Half, Onyx, 70/100 I, Velocity, and 909 New Jersey.
Comments (0)
More posts: ANC News, parking, Nationals Park, zoning
 

Last night the Zoning Commission heard the Capitol Gateway Overlay Review case for 1111 New Jersey, Donohoe's now 220,000-square-foot office building on the northwest corner of New Jersey and M. The Office of Planning report laid out how the project properly adheres to the requirements of the CG Overlay, and there was actually very little discussion by the commissioners of the building's design or landscape (save for a few questions about the width of the sidewalk on M Street, which is wider than what the CG Overlay calls for, because of various hardware for the Navy Yard Metro station below).
What took up the bulk of the discussion was whether the building's parking garage should be accessed via New Jersey Avenue or via the block's alley that runs north-south between L and M (which is shared with 100 M, Onyx, and whatever gets built on the St. Matthew's site). The original design had the garage driveway on New Jersey, but DDOT is asking that it be moved to the alley because of both a desire to not have curb cuts on a major state street like New Jersey and because the alley is an existing curb cut where pedestrians expect vehicular flow. But the commissioners were uniformly unhappy with the alley solution, given the narrowness of the alley (14 feet), the heavy amount of traffic there will be, and the very awkward garage entrance/exit that Donohoe has had to come up with in order to make the alley entry work. Donohoe didn't appear to be especially happy with the alley solution, either, but DDOT was pretty firm in their desire to have it there.
The record was left open, and DDOT and Donohoe said they would continue to work on the garage issue. A ruling on the overlay review could come at the March 11 Zoning Commission meeting.
Chairman Anthony Hood also briefly touched on ANC 6D's opposition to the project because of a lack of a community benefits package--Hood said that this project is not a PUD, and any desires to have amenities packages be part of CG Overlay reviews should have been dealt with when the Overlay was created, so the ANC's opposition was viewed as not germaine.
 

On Thursday (Jan. 31) at 6:30 pm the Zoning Commission is having its Capitol Gateway Overlay review hearing for 1111 New Jersey Avenue, Donohoe's office building at the corner of New Jersey and M. As I've written before, this project has been expanded to include 220,000 square feet of office space with 5,700 square feet of ground-floor retail in a 130-foot-tall glass-facade building, and is now subject to a CG review because of acquiring some land from WMATA that fronts M Street. This was presented to the ANC two weeks ago, which did not support the project because of the lack of a community benefits package.
The Office of Planning is recommending that this project be approved by the Zoning Commission; you can see the OP report here, which lays out point-by-point how the project stands up against the various CG requirements. There's also a request for a zoning special exception to waive a rear yard requirement; the Board of Zoning Adjustment approved a similar waiver request back in May, but they're having to apply for the exception again because the building has grown in size since the BZA ruling, so there's now more building inside the rear yard area.
 

Last night ANC 6D held a special public meeting to decide whether or not to support Tommy Wells' Performance Parking bill when it has its council hearing on Wednesday. I was unable to attend, but reports from my vast network of moles indicate that the ANC will be supporting the bill, albeit it while "expressing strong concern" over some still-outstanding issues. (We'll find out what those are during Andy Litsky's testimony at the hearing.) The ANC vote was 4-2.
At almost the same time, the Zoning Commission held a brief special public meeting to take up the series of minor modifications that Monument Realty requested to its design for the east side of Half Street (yes, the area that's already under construction). I talked about these in slightly more detail a few weeks ago when this first came to the Zoning Commission; the ZC declined to approve these as part of its consent agenda at that meeting because the commissioners wanted a little bit more clarification, which they got in the filings for this second hearing. The only question that came from the dais was why Metro nixed the wire mesh panels with LED lights that Monument had originally envisioned as the walls around the Navy Yard station entrance at Half and M--the reply was that, in addition to weatherproofing concerns, Metro wanted its security people to be able to see into the station by shining a light from a car on the street, instead of having to go into the station. The wire mesh is now being replaced with a glass "frit" (yes, I had to look it up, too) that will be backlit with the lighting scheme Monument wants. With that, the commission approved the request 5-0; all the minor modifications are explained in the Office of Planning report.
 

The last Near Southeast item on Monday's ANC 6D meeting was a request for the commission's support of the latest design of RiverFront on the Anacostia, better known as Florida Rock. This is the nearly six acres of land directly south of the ballpark, on the Anacostia River, where developers have spent 10 years trying to transition away from the concrete business currently operating there to a 1.1-million-square-foot mixed-use waterfront destination. They came close to an approved design in 2006, but in February 2007 the Zoning Commission unexpectedly sent the architects back to the drawing board, wanting a greater amount of residential space in the project, better views to and from the ballpark, and a better "expression of place."
After nearly a year, a revised design is ready to go to the Zoning Commission for approval. It now includes 323,000 square feet of residential space, 80,000 square feet of retail and 465,000 square feet of office space.
Some of the ideas floated early in the redesign process have been modified or removed, most notably "The Pitch", the plaza directly across from the ballpark's grand staircase and adjacent to the planned Diamond Teague Park. This space no longer has pitcher and catcher statues but is instead now a "festive" open plaza that will be more "integrated" with Teague and will help with the expected flow of ballpark visitors coming to and from the water taxi piers that someday may materialize out by the little red brick pumphouse.
Also, the residential and hotel buildings have had their heights grow to 130 feet, to allow for the extra square footage the zoning commission wanted. But the hotel's top two floors will now be "pure residential".
As for when some movement will actually be seen at the site, David Briggs of Holland & Knight set out a timeline based on zoning approvals, construction drawings, and the vaunted DC permitting process that estimates the start of construction on the first phase (the eastern office building) in probably fall of 2009.
He mentioned a number of times the amount of pressure that Florida Rock is under to shut down the concrete plant and to build temporary parking lots, but he explained that the site currently makes money for its company and shareholders, and there's little interest in closing it down sooner than necessary. (Briggs did say that a temporary landscaping of the eastern plaza, next to Diamond Teague, could be a possibility once the zoning approvals are received, but that the underground parking for RiverFront does extend beneath that plaza, and so excavation and construction work will need to be done there.)
It should be noted that this timeline is really about the first two phases (the eastern office building and the 160-unit residential building), because the western office building and the hotel can't be built until the construction of a new Douglass Bridge allows Florida Rock to use its land that is currently occupied by the old bridge. (The year 2016 was tossed around as a possible date for when these later phases could get started.)
Community benefits remain similar to past presentations, including an estimated 25 units of workforce housing, anticipated LEED certification for the buildings, First Source and LSDBE hiring, and a combined underground loading dock for the three western buildings, as well as the more basic amenity of replacing a huge concrete plant with shiny new buildings and access to the waterfront. The ANC has always been enthusiastic about this project, and this time around was no different, with the commissioners voting 5-2 to support the new design. The Zoning Commission hearing, for what is officially considered a modification to the project's second-stage PUD, is scheduled for March 20.
I'm really trying to just hit the newsiest items here--definitely take some time to look through my RiverFront page (have to stop calling it Florida Rock sometime) for much more detail on the current design. And read all the archived news items, too, if you want a better feel for the twists and turns this project has taken.
 

At Monday night's ANC 6D meeting, Monument Realty presented its request for the ANC's support in closing a 2,417-square-foot alley that runs between South Capitol and Van streets not far north of N Street. This alley is north of the now-closed BP Amoco and south of what is now a WMATA employee parking lot on land owned by Monument (there used to be a neon yellow bungalow there, until late 2006). Christy Shiker of Holland & Knight told the commissioners that the Amoco property--which faces the ballpark's western parking garage--is too small to develop on its own, but with the alley closed and the lots combined, Monument would build a 130-foot-high residential building with approximately 150 to 200 units plus 14,000 square feet of ground-floor (or perhaps two-story) retail. Monument is not committing at this time to pursuing LEED certification for this building.
Shiker then described the community benefits package that Monument was offering to the ANC in return for the loss of this public space, including a $50,000 contribution to the community fund, the retail, First Source employment preferences, and an affordable housing component that would match whatever is called for whenever the city's Inclusionary Zoning mandates are finally hammered out. Monument would also work toward agreements on ANC6D resident preferences, to be determined with the ANC at a later date.
This became a sticking point, with Commissioner David Sobelsohn concerned about giving the ANC's support for this project merely on promises to make agreements later. Shiker pointed out that Monument has made these agreements before for their other Ballpark District projects, and also that the ANC will have another crack at the project when down the road it undergoes its mandatory Capitol Gateway Overlay Review. But Sobelsohn still felt that the ANC was being handed a "take it or leave it" proposition.
An audience member asked if Monument would be planning to build a temporary parking lot if the alley closing is approved, but Shiker said that Monument's goal is to develop the land, that they "want a building, not a parking lot." (Though one must admit that that is some pretty plum stadium-parking territory.) There were also questions about the Public Space Storage building just to the north (echoing my WTDW entry from last week), but Monument's representatives said that they didn't think the storage company would be moving.
Commissioner Bob Siegel moved to support the alley closing with further negotiations on the proposed benefits package as the project proceeds, but the ANC voted 2-2-1 and so the resolution did not pass.
The alley closing bill is B17-0552, and Shiker told the ANC that she expected a public hearing in late February, with perhaps council action in March or April. No date for actual construction of the project was mentioned.
Coming tomorrow--a recap of the Florida Rock portion of the ANC meeting, though you don't have to wait until then to see the latest project renderings that were presented. But my long-winded summary of what was said during the meeting will have to wait a bit longer.
 