Please note that JDLand is no longer being updated.
peek >>
Near Southeast DC Past News Items: The Bixby
See JDLand's The Bixby Project Page
for Photos, History, and Details
In the Pipeline
25 M
Yards/Parcel I
Chiller Site Condos
Yards/Parcel A
1333 M St.
More Capper Apts.
Yards/DC Water site
New Marine Barracks
Nat'l Community Church
Factory 202/Yards
SC1100
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)
 
Go to Full Blog Archive


47 Blog Posts Since 2003
Go to Page: 1 | 2 | 3 | 4 | 5

On Monday night, the Zoning Commission briefly took up a group of items having to do with the Planned Unit Development (PUD) approved for Capper/Carrollsburg back in 2004. The first was the request that I've written about in the past to expand the allowed number of residential units in apartment buildings planned for two spots along L Street (between Second and Third behind the proposed 250 M Street office building and on the north side of the Old Capper Seniors site). See my previous entry for specifics.
There were also requests for three time extensions: to extend the first-stage PUD for an additional five years, to extend the deadline for filing second-stage approvals for the apartment building sites along Canal Park (including the trash-transfer station site) to 2013, and to extend the deadline for filing a building permit application for the planned community center at Fifth and K to January 2011, with an included extension of the start of construction to January 2012.
The commission voted 4-0-1 to have all of these items come up together on a future date to be determined (as one public hearing and one special public meeting for those of you well-versed in ZC phraseology).
 

At last night's Zoning Commission monthly public meeting, the DC Housing Authority made a presentation on the latest request for changes to the approved Planned Unit Development at Capper/Carrollsburg. I wrote a long explanatory entry about this request and the plans for multi-unit residential buildings at Capper back in July, and so I'm just going to plagiarize myself here:
"There are five new apartment buildings slated to be built, three of which along the east side of Canal Park where the temporary parking lots are, and another at New Jersey and K on the trash transfer site. And there is a new plan for a fifth apartment building, on L Street across from the Marine Bachelor Enlisted Quarters (B.E.Q), on the northern portion of the old Capper Seniors footprint.
"Under the original Capper plans, there was to be a strip of 61 townhouses built on this spot, but the DC Housing Authority has recognized that these homes would be dwarfed by the B.E.Q. to the north and the two planned office buildings directly behind them at 600 M Street. So DCHA has now filed a request with the Zoning Commission to allow an expansion in the total number of housing units allowed at Capper to 1,747, which would allow the construction of a four-story 189-unit apartment building (with a massing very similar to the B.E.Q.) on this stretch of L Street known as Square 882N. This Zoning Commission request is also looking to expand the number of units in the planned apartment building on the south side of L Street between Second and Third (let's call it Square 769N) to 171 units, as a result of its block-mate 250 M Street having recently gotten approvals to be built higher than originally requested."
As for last night's Zoning Commission presentation, there was a feeling apparently that it wasn't clear enough, so DCHA will be returning in early October with additional details.
 

While the focus lately has been on the start of the Capitol Quarter townhouses, there is more to the redevelopment of the old Capper/Carrollsburg public housing complex. There are the two completed seniors buildings (Capper Seniors #1 and 400 M Street), now providing 300 of the 700 old Capper public housing units that are being replaced. The first phase of Capitol Quarter includes 39 subsidized rental units, and the second phase (which is probably not going to start delivering until 2011) will have another 47 subsidized rentals; this is in addition to the sales of 121 market-rate and 91 workforce-rate townhouses throughout both phases. That leaves a little over 300 public housing units to come, which will be included in the 1,300 apartments expected to be constructed at Capper over the next five years or so.
There are five new apartment buildings slated to be built, three of which along the east side of Canal Park where the temporary parking lots are, and another at New Jersey and K on the trash transfer site. And there is a new plan for a fifth apartment building, on L Street across from the Marine Bachelor Enlisted Quarters (B.E.Q), on the northern portion of the old Capper Seniors footprint.
Under the original Capper plans, there was to be a strip of 61 townhouses built on this spot, but the DC Housing Authority has recognized that these homes would be dwarfed by the B.E.Q. to the north and the two planned office buildings directly behind them at 600 M Street. So DCHA has now filed a request with the Zoning Commission to allow an expansion in the total number of housing units allowed at Capper to 1,747, which would allow the construction of a four-story 189-unit apartment building (with a massing very similar to the B.E.Q.) on this stretch of L Street known as Square 882N. This Zoning Commission request is also looking to expand the number of units in the planned apartment building on the south side of L Street between Second and Third (let's call it Square 769N) to 171 units, as a result of its block-mate 250 M Street having recently gotten approvals to be built higher than originally requested.
I've updated the map and descriptions on my Capper Overview page to reflect these latest plans for the area, and it's worth taking a look at if you're not really familiar with exactly how wide-ranging the Capper Planned Unit Development is. (Reading the 2004 zoning order establishing the PUD and laying out the requirements isn't a bad idea, either.) I should also note that the apartment and office buildings will combine to have about 50,000 square feet of ground-floor retail. There should also be a new community center at Fifth and K, but it doesn't seem to be on the front burner just yet.
Of course, the question then becomes: when? Timelines are always dicey and should be taken with a couple pounds of salt, but it appears that these two L Street apartment buildings (882N and 769N) would be first up on the agenda, perhaps being delivered in 2011. The other two buildings on Second Street would come next, and the anticipated 400-unit building on the trash transfer site would probably be the last one to be built, finishing maybe sometime in 2013. The three office buildings and the second phase of Capitol Quarter townhouses would be sprinkled throughout that time frame as well, with 250 M Street probably being the first office building to get underway, possibly even later this year. (Have I thrown in enough "maybe"s and "possibly"s and "perhaps"s for you?)
At least these plans don't have to wait until school buses get moved!
 

It's only taken three months for me to finally get over to Seventh and M with camera in hand, but at last I've completed my mission, and have added the "afters" to my Old Capper Seniors page (and no, I'm not going to rename it my Nationals Parking Lot W page). Eventually, a 500,000-sq-ft office building by Forest City is planned for the site, but no timeline for getting that underway has been announced. (UPDATE: Link fixed. Oops.)
 

* We knew he'd been asked, but it's now confirmed that President Bush will be throwing out the first pitch at Nationals Park on Opening Night (March 30). Officials from the team have told me that they've acquired more than 50 magnetometers to handle the security checks for the expected 41,000-person sellout crowd. But it's also one more reason to get there plenty early; the gates will open at 3:30 pm. Barry passes along the message from Stan: Take Metro! Stan also says, as we've heard from multiple sources lately, that the team is continuing to work on some same-day/cash lot parking, though it isn't in place yet. (They've said previously that they're trying to figure out how to offer these spots in a way that would prevent too much additional congestion, perhaps by requiring spaces to be purchased via the Internet beforehand.)
* As for the surface parking lots, work is speeding up (just in time!). Striping and lighting looks to be mostly done on one of the Blue Zone lots at Third and Tingey in The Yards (dull parking lot photo here), and work continues on the two lots along First Street north and east of the ballpark. Ditto for the lots on Capper/Carrollsburg land, all of which are in the Orange Zone. Asphalt is being laid at Lot W at Seventh and M on the old Capper Seniors site (another dull parking lot photo here). Stormwater management systems, gravel, and lighting are in at lots U and T on Third Street between I and L (more not-quite-so-dull photos here and here, both of which show the new signs now posted).
To manage these Capper lots, the DC Housing Authority has chosen UStreet Parking, a certified DC Local, Small, Disadvantaged Business (LSDBE) that handles the parking at RFK, the Convention Center, and many swank spots that geeky old neighborhood bloggers will never see the inside of, such as Love and Ultra. Look for some free parking days in April, along with monthly parking accounts and possibly some cash parking, especially now that the Performance Parking signs (and the enforcement expected to accompany them) have taken away the bountiful free parking on Capper streets that local residents and workers have gotten used to.
UPDATE: And yes, I've gotten an updated version of the Maine Avenue sign. And "Nationals Park" is now added to the Sixth Street and South Capitol Street exit signs, though not yet with the Curly W attached.
 

It was time this weekend to catch up on photos for a bunch of locations, including the most aged batch of them all, the views of the ballpark's northern footprint along N Street, which haven't been updated since September, so you can now have your fill of photographs of imposing parking garages. The curbs and historic streetlamps are now in, and N Street has been paved from South Capitol to Half, and it looks like the paving east to First isn't far behind. So even though the half-shadow half-sunlight conditions weren't the best to work with, I took full updates of the First, Half, Cushing, and Van intersections along N, all of which you can see here.
One thing that really struck me today for the first time is just how wide First Street is becoming, as you can see in this batch of northward-looking photos. I also saw that all the businesses on the west side of First south of M have now vacated--as you can see above, it's odd to see those old about-to-be-demolished buildings with sparkly new sidewalks and streetlamps in front of them.
I also trudged around the road construction along First Street north of M as best I could to update photos of 100 M, Onyx, and 70/100 I, and also got a good new batch of 55 M photos as well as the always showy views from the freeway at South Capitol. And I finally got the last set of old Capper Seniors photos to show that the building is indeed gone. And heaven help me I even took a photo of the new sign advertising the Square 696 project, and also a few shots barely showing that work started this week on the first Capper parking lot at Third and I (because there's nothing more exciting than documenting the construction of a parking lot). There's just too much change, and I couldn't stop until it had all been documented! Aaaiiiieeeeee!!!!
For those of you brave enough to try, here's all the photos from the past two days on one page. (Thank heavens I've done a lot of work over the past year or so to automate the update process as much as possible.) Don't forget to click on the icons to see all photos of a location over the years....
 

Having driven by this evening, I can report that the last wing of the old Capper Seniors building has come down in the past few days. Nothing left but a big pile of rubble. I'll go back and get photos when it's not, um, DARK.
 

While the plan that Tommy Wells announced last week to address on-street parking around the ballpark and on Capitol Hill is just beginning its trek through the legislative process, the first of the new parking lots that the city and the Nationals will want stadium-goers to use will get underway soon. Building permits have been approved in the last few weeks for temporary surface lots in the Capper footprint at Second and K, Second and L, and Sixth and M, and work on the first two should be starting this month. (The third lot will get started in January, after the wreckage from the almost-completed demolition of the old Capper Seniors building is cleared away.)
At the same time, a Request for Proposals has been issued by DC Housing Enterprises for the management of these lots, offering a one-year contract with up to four one-year renewal options. The RFP, while chock full of selection criteria, required certifications and other specifications, also gives a few details about the planned operations of the lots themselves, which together will have about 670 spaces (or more, if valet parking is used). They will be offering monthly prepaid public parking on weekdays from 6 am to 7 pm, at a rate of not less than $150 per month; some daily parking may be allowed as well.
But users of the lots will have to vacate prior to any Nationals game, since the lots are "expected to be subject to an exclusive arrangement" with the team that gives all spaces over to ballgame parking from two hours before the game until three hours after. And a nice arrangement it is--the DC Housing Authority will apparently receive $10 per parking space per game, whether all spaces are used or not.
The zoning rule passed earlier this year that allowed the creation of temporary ballpark-area lots such as these says that they may also be used for a "seasonal or occasional market for produce, arts or crafts with non-permanent structures," though no plans for anything like that have been announced. The rule also states that the lots can only last until April 2013, since it is believed development around the ballpark will bring plenty of underground parking that will negate the need for these surface lots. The three Capper lots will eventually be replaced with a mix of apartment buildings, townhouses, and office buildings, though start dates for those projects have not been announced.
One block south of Capper, at the Yards, another batch of temporary surface lots are planned, which would have about 700 spaces. Beyond these and the garages with 1,225 spaces on the ballpark site itself, no other stadium parking locations have been publicly identified, though the Nationals have said they have found enough parking spaces for all season ticket holders--they just haven't said where they all are yet. And the city and the team continue to say that Metro will be the best way to get to the ballpark.
You can check out my stadium parking map to see where these new lots are--it also shows the other locations where zoning allows temporary lots, plus existing lots and underground garages where parking could be made available.
 

Before the snow-that-never-was arrived yesterday, I took a quick spin to get some updated photos. There was still a smidgen of sun when I visited the old Capper Seniors site, where only the southwest wing of the huge building remained standing when I was there (but even that could be gone by now). I also wandered along Tingey Street behind the DOT HQ for the first time in a long time to see what's going on with the work at The Yards--they're now preparing to build some temporary parking lots and are doing their infrastructure work before starting the rehabs next year of three existing buildings into residential and retail offerings. I also took some shots along M Street and at Onyx on First and 100 M to take advantage of the overcast skies in those spots, since the building shadows on winter days when the sun's out are almost impossible to work with. Finally, I got updated photos of 55 M Street, the northern portion of Monument's Half Street project, where the section along M Street is now three stories high and a fourth story is underway on the southern edge of the building.
Here's the entire batch of new photos on one page--don't forget to click the if you want to see all photos in the archive from a certain angle. And in case you missed these a few days back, I recently took new overhead photos of the North of M area (looking south and west and northwest), showing quite a change in the last 21 months.
 

Two bills of Near Southeast interest passed their first readings at today's city council meeting, on the consent agenda, no less. (Consent agenda = no discussion or bickering! Yay!) First was Bill 17-0448, which authorizes the closing of the public alley on Square 696 (bounded by Half, First, I, and K), and which had been interesting mainly for the affordable housing trust fund contribution discrepancy that came up during the bill's hearing a few weeks ago, when the developers noted that they expected their contribution to be in the neighborhood of $900,000 and the Office of Planning determined the required sum be closer to $8 million. Apparently the final bill calls for a $1.1 million contribution, which council chairman Vincent Gray said is the largest trust fund contribution ever as the result of an alley closing. The developers also have agreed to create a 20-foot-wide pedestrian right-of-way through the middle of the block to allow for easy access from I Street to the planned public plaza on K Street, though apparently DDOT requested that this right-of-way be upgradable for "motorized access" in the future if necessary. This alley closing will allow DRI Development to move forward with their plans for 800,000 square feet of office space in three buildings with 37,000 square feet of ground-floor retail. There've been noises that the first construction on the site could begin in the summer of 2008, but nothing official has been announced. (The last tenants on the block, in the cab garage at First and K, are expected to move out in February when their lease expires.)
Also passed today was Bill 17-0292, the Capper PILOT funding bill that I just wrote about in detail a couple days ago. This authorizes a bond issuance of up to $55 million that will yield close to $37 million to pay for infrastructure improvements at Capper/Carrollsburg. The bonds will then be repaid by landowners making payments in lieu of property taxes. I should mention that these PILOT funds won't only be repaid by residents of Capitol Quarter--there are two planned office developments totaling 750,000 square feet that are within the Capper PILOT area (600 M Street at the old Capper Seniors site and 250 M Street) that will generate PILOT payments.
Each bill will come before the council again in January for their final votes.
 