Near Southeast DC Past News Items: 11th Street Bridges
See JDLand's 11th Street Bridges Project Page
for Photos, History, and Details
In the Pipeline
25 M
Yards/Parcel I
Chiller Site Condos
Yards/Parcel A
1333 M St.
More Capper Apts.
Yards/DC Water site
New Marine Barracks
Nat'l Community Church
Factory 202/Yards
SC1100
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)
 
Go to Full Blog Archive


159 Blog Posts Since 2003
Go to Page: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 ... 16
Search JDLand Blog Posts by Date or Category

While I keep trying to get myself reacquainted with blogging (a process that clearly is not proceeding smoothly), I'm going to cheat and go with some Tidbits lists every so often, so that at least I can feel like I'm getting the spigot working better, even if it's still sputtering. Also, I have to get used to all these events, specials, and activities, which didn't used to be part of the Near Southeast blogging landscape.
* The BID reports in its latest newsletter that the Canal Park ice rink is scheduled to open on Monday, Dec. 16. And speaking of the park, if you haven't wandered by, you may not know that Christmas trees and wreaths are for sale there this year. See the market web site for details.
* On Saturday (Dec. 7), the 11th Street Bridge Park project is holding two "community design meetings" that will provide an update about the project and break out attendees into smaller groups to work on ideas. A nationwide design competition for the project is expected to be launched early in 2014. The bridge park itself is expected to cost $35 million, which at this point is mostly unfunded. One meeting is at 200 I Street SE from 2 pm to 6 pm (details and RSVP here) but there is also a morning meeting. (via DCist)
* ArtYards has the Chalk a Lot street art event on Saturday and Sunday (Dec. 7-8) at the NGA parking lot, 1st and M SE. And see also this Going Out Guide look at the ArtYards project.
* Osteria Morini is now open for lunch, and here's the menu. Plus there's Happy Hour specials now, too, from 4 to 7 pm Monday through Friday. And Post food critic Tom Sietsema took a First Bite there earlier this week.
* Bluejacket is going big with its first New Year's Eve celebration. For your $160 ticket, you'll get an open bar for all Bluejacket brews, plus a DJ and "passed bites." Then there will be a champagne toast as part of the ceremonial midnight keg drop. (No, seriously.) And Bluejacket/Arsenal is now open for lunch, too, and is serving Sunday brunch from 11 to 3, but you probably already know these things.
* VIDA Fitness, coming to the Twelve12 building at the Yards in 2014, is now offering membership pre-sales. Their site says that the Penthouse Pool Club will open on July 1, 2014 and the VIDA Fitness itself on Aug. 25, 2014.
* If you want to look a little farther into the future: WMATA has scoped out the subway alignments it would like to pursue as part of its 2040 "core configuration" plan. How would you feel about a new Blue and Yellow line under 2nd Street from Union Station, turning west with a station at New Jersey and I before heading to Virginia? (It would also run under M Street NW from Georgetown to New York Avenue.) I can't wait to set out from my retirement home with my brain-embedded camera to take photos of this project.
 

I was otherwise occupied on Sept. 7, the day of the big celebration on the now-completed 11th Street Local Bridge, but I finally wandered down to that neck of the woods a few days ago with my camera to capture the current state of affairs. And one might say that the landscape at 11th and O has changed a bit thanks to this project:
before
after
But there's more than just the newly wide open spaces at 11th and O. The girders for the new flyover that will carry traffic from the Southeast Freeway to the outbound I-695 bridge are all now in place; couple that with the demolition earlier this year of the old outbound flyover, and you have a very different vista at 11th and L than what's been there up to now:
before
after
(The low height of the flyovers above 11th does make that little stretch a bit claustrophobic, though, especially on foot.)
You also now have two-way traffic on 11th between O and M, so that vehicles coming across the local bridge from Anacostia can drive straight north on 11th.
And the dirt-fill-in work for Southeast Blvd. has progressed enough that the west side of 11th at the freeway no longer feels like an overpass, just the regular road.
Plus there's also work at 8th Street and Virginia Avenue to create a new on-ramp and also fashion the new exit to Southeast Blvd./11th Street.
If you don't feel like clicking on each of these photos, just head to my 11th Street Bridges and Southeast Blvd. pages to see them alongside a few other new shots. You may also want to dig into my photo archive to check out the before-and-afters at 11th and the freeway, 11th and L, 11th and M, 11th and N, and 11th and O. Though the photos don't quite seem to do the changes justice, especially if you're someone who has walked those blocks of 11th many times over the past few years.
Comments (0)
More posts: 11th Street Bridges, photos, Southeast Blvd., Traffic Issues
 

The showiest demolition in the neighborhood in years is coming to an end, and while I haven't been able to document it in the obsessive-compulsive way I would have liked, I did manage to make it to 11th Street this weekend to see the gator tail-like final remnants of the old flyover to the outbound 11th Street Bridges before it completely comes down.
At the same time, I was able to check out the progress on the filling-in of the sunken eastern portion of the Southeast Freeway to build Southeast Blvd., and dang if they haven't already piled the dirt up so that 11th Street is now level with the "land" just to its west.
Needless to say, I had to create a photo gallery of the remants and the progress, where you'll also see that work is speeding along on the new flyover to the outbound I-695 bridge.
But I wasn't just interested in the tearing down and filling in, so I continued down to O Street, where not only is the 11th Street Local Bridge inching ever closer to getting all of its lanes and pedestrian path opened, but the new asphalt Anacostia Riverwalk Trail path to the river has been laid, which also takes you to the spiffy new landing just completed by the riverside. And from that landing you can see the spiffy new overlooks that reach out onto the old bridge piers from the new local bridge. (For the record, I could have easily sidestepped the construction barrels and ventured onto the overlooks, but I am a good little citizen.)
Lots of images of the new trail, the landing, the bridge, and the surroundings are in a second new photo gallery.
If these two galleries aren't enough, you might take some time to browse my before-and-afters all the way down 11th Street, from the freeway to L to M to N to O to the river, as nearly four years of construction have altered the vistas from a maze of flyovers and embankments to, well, a completely different maze of flyovers and embankments. (But the new flyovers are a little lower on the horizon, at least.)
I also checked out the other projects that are in various stages these days, from Twelve12 to the Lumber Shed to the leafed-out and fountain-ed Canal Park to the hole in the ground that will be the Park Chelsea.
There's new pictures on each of those pages, but I also couldn't help myself and pulled together a third photo gallery, with photos from those spots and a few others that were particularly photogenic on a particularly photogenic day. (It even includes my very first visit to the footprint of one of the neighborhood's most central locations. Where might that be?)
[A postscript: I truly think Sunday was the most perfect day for taking pictures in the 10-plus years I've been wandering the neighborhood, with the achingly clear deep blue sky perfectly matched with the late-May sun strength and positions. I ended up walking more than eight miles in three separate treks, and came home with a smidge more than 1,000 photos, about 300 of which are now in my photo archive.]
 

The latest presentation slides from last week's 11th Street Bridges project's Community Communications Committee Meeting have been posted, and a few of them caught my eye (or bought my eye, for you fans of obscure Monty Python references). TheWashCycle recently posted a photo of the work underway on the overlooks that are now under construction just down-river of the new local bridge, using the old piers as their bases, and this is what they are expected to look like when completed (click to enlarge):
There is also a rendering (seen at right) of how the Anacostia Riverwalk Trail will run both under the bridges and down from O Street when finished; it also shows the small overlook that will be built out into the river just to the east of the entrance gate to the Navy Yard Promenade. WashCycle also got a recent photo of the path under construction, where you can see the outlines of what the rendering shows is coming.
The presentation slides also have some photos of the demolition underway on the old outbound freeway flyover, and aerial photos of the work that's completed and still underway on the east side of the river. There's also, on page 21, an image which looks like they've already almost completed the filling-in of the portion of the Southeast Freeway between 8th and 11th, since it shows dirt almost up to the underside of the existing bridge that takes 11th Street across the sunken freeway between I and L.
What all of this really means is that I need to get back to 11th Street with my camera pretty soon, since my last batch of photos is now a bit dated (waaah!).
Comments (11)
More posts: 11th Street Bridges, Pedestrian/Cycling Issues, riverwalk
 

As I wrote a few days back, the portion of the Southeast Freeway between 8th Street SE and Pennsylvania Avenue will be fully closed after the evening rush hour on Thursday, Jan. 31, to both begin work on the new Southeast Blvd. and to demolish the existing outbound flyover ramp and replace it with a new three-lane one.
One thing I didn't mention in that post is that, with these closures Thursday, both the 8th Street SE on-ramp to the outbound I-695 freeway bridge and the 9th Street ramp toward Pennsylvania Avenue will be closed.
As the helpful graphic at right from DDOT shows, if you're wanting to get on I-695 outbound, you'll need to use the ramp on the southeast corner of 11th and M.
Since this closure now makes the Southeast Blvd. project truly seem underway, I've been spurred into an unexpected burst of action, and have created a Southeast Blvd. project page, separate from my recently refreshed 11th Street Bridges page. Right now it's mainly drawings, "before photos," and links to my previous posts on the project, but I will keep it updated throughout the expected 18-to-20-month span of construction:
I also threw together a new 11th Street Bridges Progress Photo Gallery with some new shots from this past weekend, when I traipsed around N and O streets and up on the local bridge for the first time in way too long.
And now I think my guilt over some long-neglected photos is assuaged, at least for a little while.
Comments (9)
More posts: 11th Street Bridges, photos, Southeast Blvd., Traffic Issues
 

The next step in converting the sunken portion of the Southeast Freeway between 8th Street SE and Pennsylvania Avenue to the eventual at-grade "Southeast Boulevard" is coming, as DDOT has announced that on Jan. 31, "all eastbound lanes along this stretch will be closed to traffic for approximately 18-20 months while crews fill the roadway to restore it to the local street elevation."
This will be preceded by for a week or so beginning around noontime on Tuesday, Jan. 22, with the route being reduced to only one lane.
Not only are these closures to allow for the filling-in of much of the old roadway, but also to start construction of bridge piers for "a new bridge over the SE Freeway," which I believe will be the new three-lane flyover ramp from the freeway to the outbound 11th Street Bridge, replacing the current one (seen at top left in the photo).
If you're worked up about this closure because you're using the route to Pennsylvania Avenue to then use the left-turn-to-DC295, you should already be using the new exit ramp from the outbound 11th Street Bridge directly to northbound 295 anyway!
The work of bringing in lots and lots (and lots and lots) of dirt to build up the sunken route has already begun on the old westbound side of the road, as seen in this photo I took earlier this month, when I also updated the before and afters for the 11th Street & not-yet-Southeast-Blvd intersection.
If you haven't been following this project, which is part of the $90 million second phase of the 11th Street Bridges project, the filling-in is so there will be an at-grade signalized intersection at 11th Street, SE. Drivers will arrive at the new intersection from the SE Freeway (or Pennsylvania Avenue) and have the option of getting onto 11th Street, or continuing straight. There will also be a new stretch of 12th Street north of M to Southeast Blvd., so that drivers exiting the 11th Street freeway bridges can continue north across M to the new boulevard, instead of turning left onto M and then right onto 11th.
There is also supposed to be a new pedestrian/cycling trail alongside this new Southeast Blvd., creating another connection between Virginia Avenue Park and Barney Circle than using the currently-ripped-up-by-DC-Water M Street route.
This construction drawing shows all the new intersections, ramps, flyovers, and whatnot for both phases of the project on the west side of the river, if you need some help visualizing.
There are also supposed to be public meetings coming this year as part of studies now underway on how to remake the Barney Circle-not-yet-Southeast-Blvd interchange.
Comments (1)
More posts: 11th Street Bridges, Southeast Blvd., Traffic Issues
 

UPDATE, Dec. 19: A tweet from DDOT confirms that the new ramp is "slated to open this afternoon, possibly in time for evening rush hour." UPDATE TO THE UPDATE: According to NBC4's Adam Tuss, the ramp is now open.
Original post: Just out from DDOT, an announcement that the long-awaited ramp from the outbound 11th Street freeway bridges (now known as I-695) to DC-295 northbound is expected to open "on or about December 19." This means that vehicles traveling eastbound on the southeast freeway can now remain on the freeway for their entire trip to DC-295 northbound, instead continuing along the stub of the Southeast Freeway ending at Barney Circle, then traveling across the Sousa Bridge to then endure a nightmare left turn onto DC-295.
Not mentioned in the announcement is whether at the same time the old route to Pennsylvania Avenue will be closed--if it doesn't close the 19th (see Update II below), it will be closing soon, as part of the two-year reconfiguration of that road as "Southeast Boulevard."
{I'm psychic!}
UPDATE: I should also note that, according to the graphic at right, eastbound freeway traffic will start being routed (temporarily!) on the new flyover built during the past few years that will eventually carry inbound traffic; but using it for outbound traffic at this point allows the existing older outbound flyover to be demolished to make way for a new outbound flyover. Photos and additional explanations here and here.
UPDATE II: However, if you're used to getting onto the eastbound freeway and 11th Street Bridges via the ramp at 8th and Virginia, be advised that ramp will close when demolition begins of the old outbound flyover, which is expected to start in late January. And, to answer another lingering question from this post, that's when the eastbound freeway east of 8th will be closed, which also means that the little ramp from 9th and Virginia to the eastbound freeway stub will be closed as well. (This all from @DDOTDC on Twitter.) You'll be able to access the new ramp to DC-295 northbound by getting on eastbound I-695 via the new-ish ramp on the southeast corner of 11th and M; in fact, the entrance lane from that ramp I believe puts you directly in the DC-295 NB exit lane. Or, if you're on the western end of the neighborhood, you can get on the eastbound freeway at South Capitol Street (only in my fever dreams).
Comments (7)
More posts: 11th Street Bridges, Southeast Blvd.
 

A release just out from DDOT is announcing that the new ramp from 11th Street SE to the westbound Southeast/Southwest Freeway wll be opening on Thursday, Nov. 29. This means that vehicles from the eastern ends of Capitol Hill and Near Southeast won't have to drive along Virginia Avenue to the 3rd Street SE on-ramp anymore; it will also give easier westbound freeway access to traffic coming inbound on the 11th Street Local Bridge.
Also on Nov. 29, the westbound portion of the sunken SE Freeway between Pennsylvania Avenue/Barney Circle and 8th Street SE will be fully closed, as work continues on creating the new "Southeast Blvd." Drivers heading south on DC-295 who have long exited onto Pennsylvania to go west on the SE/SW Freeway will be directed to use the inbound 11th Street Freeway Bridge.
I wrote a lot about these changes back in September, so I'll just point you to those three posts for additional information and photos, or you can wander through my 11th Street Bridges project page.
Comments (4)
More posts: 11th Street Bridges, Southeast Blvd.
 

The 11th Street Bridges folks were nice enough to pass along a more recent drawing (March 2012, Concept Only! Not for Construction!) that shows the 11th Street Bridges' project Phase 2 plans.
They were also nice enough to pass along a very large version of this more recent drawing, enabling me to post a very large image in on the new ramps and lanes along and over 11th Street on the west side of the Anacostia River, and how the new Southeast Boulevard with a new signalized intersection at 11th Street will be built along what used to be the eastern end of the Southeast Freeway. It also shows the extension of 12th Street north of M to the new boulevard, along with all of the turn lanes and other movements. (All of this assuming the designs don't change.)
It's also handy if you haven't committed all the Phase 1 ramps and flyovers and lanes and paths to memory--they are shown in yellow and orange, while the Phase 2 plans are in blue and pink, and decommissioned roads and ramps are in a subtle x'ed-out motif. So, for the heck of it, here's a not-quite-so-enlarged image showing the entire project, on both sides of the river. Also, if you missed it, my photo gallery of the project's current state, from earlier this month.
(I should note that this map doesn't include how upcoming changes to Barney Circle might look, because that's still under deliberation.)
Comments (3)
More posts: 11th Street Bridges, Southeast Blvd., Traffic Issues
 

There's a lot going on over yonder at 11th Street these days, as the initial 11th Street Bridges project continues toward its expected completion next year while the now-funded Phase 2 work is starting to get underway.
I was able to arrange a tour last week (thank you, bridge folks!), and have put together a photo gallery of the most interesting shots.
However, there's a lot going on and so I'm going to break out some of the information here as well. (But go look at the gallery too!)
New Ramps from/to 11th Street Local Bridge
By the end of the month (or maybe even by the end of the week), two new ramps on the 11th Street Local Bridge will open, providing access to southbound I-295 from the local bridge and to the local bridge from northbound DC-295. There are signalized intersections at both ramps, with turns allowed in each direction. And, once construction is finished to make 11th Street two-way from O Street northward, commuters driving north on 295 will be able to use the new ramp to the local bridge to then arrive directly at the Navy Yard's entrance gate at 11th and N.
Southeast Blvd., and Outbound Freeway Traffic
This week saw the first of the lane closures that within a few months will signal the end of the SE Freeway east of 8th Street. Once all lanes are closed, traffic taking the old two-lane flyover to outbound I-695 will be temporarily routed onto the completed-but-not-opened inbound flyover connecting I-695 and I-395. This will allow for the razing of the old outbound flyover, and construction of a new three-lane flyover in the gap between the old and new ones. The filling of the old sunken freeway will also begin, for the new at-grade Southeast Blvd.
Old Outbound Bridge Demolition
The old outbound 11th Street Bridge is now little more than a bunch of old girders, which are starting to be removed. Soon, all that will be left will be the river piers, though two of those will be used to create viewing platforms that will be accessed via walkways from the new 11th Street Local pedestrian path. (And can be reused if anyone ever decides to pony up the millions needed to create the 11th Street Recreation Bridge.) In the meantime, work continues on the downriver edge of the new local bridge, to get it to its full four-lane-plus-ped-path width.
But there's more than just these items and photos. There's photos of the under-construction ramp that in about three months will take traffic from outbound I-695 to northbound DC-295, plus the big piles of dirt waiting to be used to fill in the eastern part of the Southeast Freeway, and the work on the ramp from 11th Street to westbound I-395, and more. So go look at the entire gallery. (I've also incorporated some of the new photos into my 11th Street Bridges project page, to go with the before-and-afters.) I also wrote in more detail about the Phase 2 projects a few months back.
Comments (6)
More posts: 11th Street Bridges, photos, Southeast Blvd., Traffic Issues
 