Since January, 2003
            
 Sliding from Before to After

In the past few posts I've shown you the neighborhood's newest skeletons/skeletons to be, I've shown you buildings that are topped out but still getting exterior work done, and holes in the ground, and I know you are long since bored of this stretch of posts, but I will still do one more, looking at two projects that between them are managing to fall into all categories at once.
Plus, they are probably the two most watched projects in the neighborhood at the moment.
These are two views of JBG Smith's West Half 420-unit residential development, which, if I can count floors correctly, is still not yet topped out, but which, as seen in the second photo, is already hanging glass on the lower floors, presumably to protect the spaces from the roving gangs of All-Star hooligans that will descend next month. I think both photos do a good job of showing the very unique structure of this building, as it appears from the north to be funneling down into the ballpark. It also looks like the corner of the building facing the ballpark is prepped to have some signage hung. Digital? Temporary? Permanent? We Shall See! This building is expected to have about 65,000 square feet of retail on its first two floors.
And, across the way, we have:
The east side of the street will be home to 1250 Half Street, a residential project that is both a nearly topped-out skeleton (on the north end of the site) and a still-not-yet-out-of-the-ground hole to peer into (on the south end of the site). It is actually all one building, it's just that the foundation was built on the north end back when Monument Realty had plans to develop the rest of the block as it was building the 55 M office building, before, well, you know, Things Happened. So this allowed Jair Lynch Development Partners to plow ahead with above-ground work there while prepping the rest of the former Monument Valley hole to go vertical. This building will have as many as 440 rental units and over 60,000 square feet of retail (including anchor tenant Punch Bowl Social) when it's finished, though I should note that it is going to be completed in two phases, with construction of the phase two "boutique residential building" facing N Street coming later.
And here's what both will look like to people exiting the ballpark when they are finished.
Which is a little different from:
With that, I am done running down all of the latest construction statuses (statusi?). If you are worn out, don't blame me, blame the SEVENTEEN separate construction projects underway (19 if you include the Virginia Avenue Tunnel and the new South Capitol Street bridge).
Comments (12)
   
 
 More Recent News

JDLand.com Home

Comments

CJBabyDaddy says: (6/22/18 7:15 AM)
How long before the Nats debut your “JDLand All-Star Hooligan“ merchandise line?


RMP says: (6/22/18 8:17 AM)
TIL that One Hill South is apparently very popular among a certain demographic. link


202_cyclist says: (6/22/18 9:18 AM)
@RMP— BARF! BARF! and BARF!


202_cyclist says: (6/22/18 9:26 AM)
Well, One Hill South looks a lot more comfortable than a baby prison.


malatesta says: (6/22/18 9:55 AM)
That's, uh, not a very good article. It's correct in that I know there's plenty of people in my building who are staffers on the hill or at the white house. But I think badly mischaracterizes the neighborhood to push the weird narrative of the article.


JD says: (6/22/18 10:39 AM)
And since I skipped writing about the new Douglass Bridge, here's a good piece about the design and construction of the new bridge from an engineering point of view: link


202_cyclist says: (6/22/18 11:00 AM)
JD-- thank you for posting the article. I'm impressed by the engineering required to build the bridge. Also, that is a good aerial photo of the neighborhood in the article.


jdc says: (6/22/18 2:27 PM)
Sigh. If only, as shown in that photo, that segment of Half Street would be closed and turned into a short pedestrian mall. Whoever is living in all of these apartments seem to a) love pooches and b) love expensive cars.


NavyYardRes says: (6/24/18 9:22 AM)
From the Bridge article - "Traffic ovals will be created at each end and sections of South Capitol Street will be re-created as a scenic boulevard." - Do we really think a scenic blvd. design is best for the fastest and densest neighborhoods in DC. This is going to be a major bottleneck. They should tunnel from highway to bridge, straight shot.


JD says: (6/24/18 9:24 AM)
A tunnel was actually discussed back when I first started doing it. Prohibitively expensive.

And if they go through with getting rid of the M Street underpass, South Capitol will be a lot slower. :)


caphillguy says: (6/27/18 10:27 AM)
I'm confused about what the above says about 1250 Half Street. It's one building but it's being built in two phases with the second starting later? How does that work? Am I misinterpreting that?


JD says: (6/27/18 10:31 AM)
If you look very closely at the rendering, you can see that the Half Street facade and the N Street facade fit together but don't fully connect (and you can see the dark brick wall on the N Street portion). There was originally talk of the N Street portion being condos, and maybe they are hedging that decision by referring to it now as a "boutique residential" building.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2018!
 Recent Posts

jdc on Four-Alarm Fire Rips: The photo at the top of this most makes it seem like the entire attic space, and...
dude on Four-Alarm Fire Rips: This sucks for all those people. Glad people seem to be ok, at least physically...
Bruce on Four-Alarm Fire Rips: Walt: I am very touched by the kind words. Many worked like a well oiled machine...
jdc on Four-Alarm Fire Rips: News story recounts things better than my memory can https://www.nbcwashington.c...
jdc on Four-Alarm Fire Rips: Some reporter at a news conference today (about that terrible stabbing of the wo...
walt on Four-Alarm Fire Rips: I'll chime in to give kudos to Anne and Bruce Darconte. I was nearby yesterday,...
Get JDLand Updates In Your Inbox!


Thousands and thousands of photos showing the neighborhood changing. More than 150 buildings no longer with us. All the news, since 2003. Photos from various archives showing the neighborhood in the more distant past. Maps from the early 1900s. Overhead Photo Comparisons: 1949, 1988, 2002-2008. All Blog Entries, 2003 - Present Major Events, 1799 - Present A series of blog entries looking at the neighborhood's history.
Near Southeast's Rearview Mirror


City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1000 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle) - Street / Unknown
 09/16/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/16/18
1000 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/15/18
1000 B/O 3RD ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/15/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 09/13/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/13/18
1000 B/O HALF ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/11/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/08/18
400 B/O M ST SE   THEFT
Shoplifting
 09/02/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/29/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/29/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/29/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/26/18

Recent Issued Building Permits Archive  
1108 3RD ST SE   
09/04/18 
JULIANA DUFFY / HERVE BILLIET
SOL1800816 / CONSTRUCTION
This is a new rooftop solar installation for 1108 3rd Street SE, Washington, DC, 20003.
   
09/06/18 
JULIANA DUFFY / null
E1810366 / SUPPLEMENTAL
1015 4TH ST SE   
09/17/18 
GASTON CHAN / KYLE YOST
SOL1800945 / CONSTRUCTION
5.89kw rooftop solar pv system, less than 4' above roof
   
09/19/18 
GASTON CHAN / null
E1810828 / SUPPLEMENTAL
1300 4TH ST SE   
09/07/18 
null / MITCH PERMUY 7274240492
E1810371 / SUPPLEMENTAL
1346 4TH ST SE   
09/07/18 
null / MITCH PERMUY 7274240492
E1810372 / SUPPLEMENTAL
1310 10TH ST SE   
09/10/18 
NAVFAC / BLAINE LINKOUS
EX1800093 / CONSTRUCTION
Federal property at the Washington Navy Yard. Project is for the installation of outside underground utilities including new potable water valves and stormdrain. All work is cut and cover utility install. Sediment controls will be provided.
2 EYE ST SE   
09/18/18 
null
M1803959 / SUPPLEMENTAL
   
09/18/18 
null
P1809280 / SUPPLEMENTAL
4 I ST SE   
08/29/18 
CRESCENT COMMUNITIES / MITCH A. PERMUY 727-210-0492
E1809865 / SUPPLEMENTAL
   
09/18/18 
JOHN MORIARTY / null
M1803958 / SUPPLEMENTAL
2 I ST SE   
08/27/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1801251 / CONSTRUCTION
WR #3573836-VAETH / BRUNO-WARD 6-20003-PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" ST ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL CABLE - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY THRU FRIDAYS) FROM 9PM TO 7 AM - WILL ALSO BE WORKING WEEKENDS (SAT & SUN) FROM 6AM TIL 6PM
   
08/29/18 
CRESCENT CAPITAL VIEW LLC / KIM MITCHELL
TL1800059 / CONSTRUCTION
EXPEDITION / VELOCITY PROGRAM - INTERIOR WORK ONLY FULL-SERVICE RESTAURANT WITH 78 SEATS AND 80 OCCUPANTS INDOORS. WITH BUILDOUT OF AN EXISTING COLD DARK SHELL STRUCTURE AT THE GROUND FLOOR OF THE 2 I STREET BUILDING PERMIT B1713380. THE BUILDOUT IS FOR A RETAIL KITCHEN.
   
09/11/18 
MCDONALDS CORPORATION / null
E1810511 / SUPPLEMENTAL
   
09/19/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1801319 / CONSTRUCTION
WR #3573836 - VAETH / BRUNO - WARD 6 - 20003 - PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" ST ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL CABLES - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY THRU FRIDAYS) FROM 9PM TO 7 AM - PEPCO CREWS WILL ALSO BE WORKING WEEKENDS (SATURDAY AND SUNDAYS) FROM 6AM TIL 6PM - WORK IS ONGOING
150 I ST SE   
09/10/18 
WILLIAM CSMITH CO / GLENNWOOD ROGERS
M1803857 / SUPPLEMENTAL
418 L ST SE   
09/14/18 
null / NA NA NA
EHOP18998072 / HOME OCCUPATION
202 M ST SE   
09/05/18 
UNITED STATES OF AMERICA / DANIEL KISER; X
SG1800384 / CONSTRUCTION
Installation of 4 wall mounted signs. 2 @ 26.25 SF and 2 @ 35.5 sf
300 M ST SE   
08/27/18 
FEDERAL CENTER LP / SAM HOLLEN
B1809629 / CONSTRUCTION
INTERIOR RENOVATION TO 3RD FLOOR OFFICE SPACE FOR NEW MEDICAL OFFICE. PARTITIONS, FURNITURE, MEP AND LIFE SAFETY. LEAD WALLS FOR X-RAY ROOM. NO STRUCTURAL. 3006 SQUARE FEET. THE CENTERS FOR ADVANCED ORTHOPEDICS, LLC SUITE 325 **CHANGE IN USE, LEVEL 2 ALTERATION
   
09/05/18 
FEDERAL CENTER LP / null
P1808927 / SUPPLEMENTAL
   
09/05/18 
FEDERAL CENTER LP / null
P1808926 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE 1ST FL   
09/18/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1809276 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE 3RD FLOOR   
09/17/18 
SQUARE 742 LLC / null
P1809222 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
08/30/18 
SQUARE 742 LLC / null
E1810159 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
09/07/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / ASHLEY TORRES
TL1800132 / CONSTRUCTION
Tenant Layout to 1st floor for commercial bank use. 3036SF
   
09/10/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
M1803863 / SUPPLEMENTAL
   
09/12/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1810553 / SUPPLEMENTAL
125 O ST SE   
08/29/18 
DISTRICT OF COLUMBIA / DAVID T FONTANA
B1803497 / CONSTRUCTION
Revision to issued permit B1700636 for new six story DC WATER HQ office to include: Minor door, ramp and partition changes, corrections to foundation, slab and framing due to field conditions, MEP & FA coordination with other changes, minor changes to landscaping and water utility site work.
71 POTOMAC AVE SE   
08/27/18 
FORIDA ROCK PROPERTIES INC / null
AH1801250 / CONSTRUCTION
afterhours to pour concrete on jobsite from 8 / 27 / 2018 to 9 / 27 / 2018 from 9pm to 7am
   
08/31/18 
FORIDA ROCK PROPERTIES INC / MITCH PERMUY 7272100492
E1810173 / SUPPLEMENTAL
79 POTOMAC AVE SE   
09/13/18 
RIVERFRONT HOLDINGS I LLC / JOHN HOMICK 301-390-4800
E1810571 / SUPPLEMENTAL
221 TINGEY ST SE   
09/10/18 
KELLY THORNBURG / GLENNWOOD ROGERS
M1803850 / SUPPLEMENTAL
227 TINGEY ST SE   
09/07/18 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1801286 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for precast concrete façade panel installation. Work to take place from 7pm on 9 / 24 / 2018 to 7am on 9 / 25 / 2018.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.