Page Through from Before to After
 At 8 am on Friday, Dec. 23, the first double-stacked train passed through the newly built southern tunnel under Virginia Avenue, SE, marking the official completion of that phase of the Virginia Avenue Tunnel project. (Alas, the photo at left shows a train coming through the old tunnel, before the rails were laid into the new one, but whaddyagonnado.) Now Phase II of the project is kicking into gear, which is the rehabilitation and expansion of the existing 100-plus-year-old northern tunnel. That work is expected to be completed, along with the streetscape restoration improvements to Virginia Avenue, in mid-2018. As part of the work on the northern tunnel, the intersection of 7th and Virginia is expected to close Any Minute Now for about two weeks. Of course, 3rd Street remains closed at Virginia for similar work of demolishing the temporary deck over the now-completed new tunnel and rebuilding it over the northern tunnel; it is expected to reopen in January.
JDLand.com Home
dude says: (12/29/16 11:09 AM)
I like how every few months I get to take a different route home after getting off at the 6th ST exit.
Shogungts says: (12/29/16 12:39 PM)
@dude - not sure where your eventual end destination is, but if you are going to the Navy Yard area, have you tried exiting 395 at exit 6 (the exit to continue on 395N as opposed to 695)? I live on 3rd North of the highway, but If I am going to the Navy Yard area, I take exit 6, turn right onto Washington Ave, left onto D St and then right onto NJ ave. If 395 is backed up, I will often take exit 6 and instead of turning on NJ ave, I stay on D until I hit 3rd.
Shogungts says: (12/29/16 1:07 PM)
Edit: I said that I turn on D St, but actually it is E St that I use as I believe it is faster, but D would work as well.
bmooremsu says: (12/30/16 1:27 PM)
Is it just me or has there been a sharp uptick in the number of trains (and horns) that I'm hearing following the completion of this tunnel?
dude says: (12/31/16 6:05 PM)
@ShogunGTS yes I could do that as well, but I'd end up with a few more stops (lights/stop signs). We are at 4th and L so it's easy enough to get off at the 6th ST exit, left on Virginia, left on 4th. It's no big deal, just never lived in another place where the best route home changes every few months. I haven't noticed more trains or horns, but we are probably far enough away. That reminds me though, does anyone know why the National Anthem is being played around 8 every morning? Seems to me it started about a month ago. Perhaps it's always been happening but now it's louder? Personally I like it, but I don't know where it's coming from.
snakegriffin says: (12/31/16 10:07 PM)
That's new? I feel like I've been hearing it ever since we moved back to the neighborhood (April).
202_cyclist says: (1/1/17 12:48 AM)
Happy New Year! @Dude-- the Navy plays the national anthem and also the revelry daily. It is a recording.
202_cyclist says: (1/1/17 7:25 AM)
Did anyone else hear the several loud explosions around 2:30 AM? I assume someone was lighting off fireworks.
JD says: (1/1/17 9:55 AM)
The Hill is Home is on the National Anthem stuff--seems like the Navy Yard must have gotten a new sound system or something. link
Also, a reader reports this morning that the windows at Five Guys are papered over--can anyone confirm? I have heard nothing about it closing, and I can't imagine that location is struggling, but it's been there 11 years, so I dunno, maybe it's done?
202_cyclist says: (1/1/17 11:26 AM)
JD--- correct, we saw that Five Guys was closed yesterday and the the windows were papered over. Hopefully it isn't permanently closed.
snakegriffin says: (1/1/17 12:44 PM)
Maybe they saw the writing on the wall with the Shake Shack opening soon? I thought they did good enough business to compete though. I would patronize both!
JD says: (1/1/17 1:58 PM)
A source says it is indeed just a "refresh" at Five Guys. Maybe milkshakes are coming, too...
Add a Comment:
Comments are closed for this post.
JDLand Comments RSS Feed
See All Current News Items |
Full Blog Archive
|
|
|
Full Neighborhood Development Map
There's a lot more than just the projects listed here. See the complete map of completed, underway, and proposed projects all across the neighborhood.
What's New This Year A quick look at what's arrived or been announced since the end of the 2018 baseball season.
Food Options, Now and Coming Soon
There's now plenty of food options in the neighborhood. Click to see what's here, and what's coming.
Anacostia Riverwalk
A bridge between Teague and Yards Parks is part of the planned 20-mile Anacostia Riverwalk multi-use trail along the east and west banks of the Anacostia River.
Virginia Ave. Tunnel Expansion
Construction underway in 2015 to expand the 106-year-old tunnel to allow for a second track and double-height cars. Expected completion 2018.
Rail and Bus Times Get real time data for the Navy Yard subway, Circulator, Bikeshare, and bus lines, plus additional transit information.
Rail and Bus Times Get real time data for the Navy Yard subway, Circulator, Bikeshare, and bus lines, plus additional transit information.
Canal Park
Three-block park on the site of the old Washington Canal. Construction begun in spring 2011, opened Nov. 16, 2012.
Nationals Park
21-acre site, 41,000-seat ballpark, construction begun May 2006, Opening Day March 30, 2008.
Washington Navy Yard
Headquarters of the Naval District Washington, established in 1799.
Yards Park
5.5-acre park on the banks of the Anacostia. First phase completed September 2010.
Van Ness Elementary School
DC Public School, closed in 2006, but reopening in stages beginning in 2015.
Agora/Whole Foods
336-unit apartment building at 800 New Jersey Ave., SE. Construction begun June 2014, move-ins underway early 2018. Whole Foods expected to open in late 2018.
New Douglass Bridge
Construction underway in early 2018 on the replacement for the current South Capitol Street Bridge. Completion expected in 2021.
1221 Van
290-unit residential building with 26,000 sf retail. Underway late 2015, completed early 2018.
NAB HQ/Avidian
New headquarters for National Association of Broadcasters, along with a 163-unit condo building. Construction underway early 2017.
Yards/Parcel O Residential Projects
The Bower, a 138-unit condo building by PN Hoffman, and The Guild, a 190-unit rental building by Forest City on the southeast corner of 4th and Tingey. Underway fall 2016, delivery 2018.
New DC Water HQ
A wrap-around six-story addition to the existing O Street Pumping Station. Construction underway in 2016, with completion in 2018.
The Harlow/Square 769N Apts
Mixed-income rental building with 176 units, including 36 public housing units. Underway early 2017, delivery 2019.
West Half Residential
420-unit project with 65,000 sf retail. Construction underway spring 2017.
Novel South Capitol/2 I St.
530ish-unit apartment building in two phases, on old McDonald's site. Construction underway early 2017, completed summer 2019.
1250 Half/Envy
310 rental units at 1250, 123 condos at Envy, 60,000 square feet of retail. Underway spring 2017.
Parc Riverside Phase II
314ish-unit residential building at 1010 Half St., SE, by Toll Bros. Construction underway summer 2017.
99 M Street
A 224,000-square-foot office building by Skanska for the corner of 1st and M. Underway fall 2015, substantially complete summer 2018. Circa and an unnamed sibling restaurant announced tenants.
The Garrett
375-unit rental building at 2nd and I with 13,000 sq ft retail. Construction underway late fall 2017.
Yards/The Estate Apts. and Thompson Hotel
270-unit rental building and 227-room Thompson Hotel, with 20,000 sq ft retail total. Construction underway fall 2017.
Meridian on First
275-unit residential building, by Paradigm. Construction underway early 2018.
The Maren/71 Potomac
264-unit residential building with 12,500 sq ft retail, underway spring 2018. Phase 2 of RiverFront on the Anacostia development.
DC Crossing/Square 696
Block bought in 2016 by Tishman Speyer, with plans for 800 apartment units and 44,000 square feet of retail in two phases. Digging underway April 2018.
One Hill South Phase 2
300ish-unit unnamed sibling building at South Capitol and I. Work underway summer 2018.
New DDOT HQ/250 M
New headquarters for the District Department of Transportation. Underway early 2019.
37 L Street Condos
11-story, 74-unit condo building west of Half St. Underway early 2019.
CSX East Residential/Hotel
225ish-unit AC Marriott and two residential buildings planned. Digging underway late summer 2019.
1000 South Capitol Residential
224-unit apartment building by Lerner. Underway fall 2019.
Capper Seniors 2.0
Reconstruction of the 160-unit building for low-income seniors that was destroyed by fire in 2018.
Chemonics HQ
New 285,000-sq-ft office building with 14,000 sq ft of retail. Expected delivery 2021.
Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.
|
|
No records added or modified in the past two weeks. |
|
Recent Issued Building Permits
| Archive
|
|
1300 4TH ST SE 1001
|
|
02/22/21
AP BOWER RETAIL LLC / null
E2104231 /
SUPPLEMENTAL
|
1346 4TH ST SE APT 1M
|
|
02/06/21
null / NA NA NA
EHOP21945129 /
HOME OCCUPATION
|
1331 4TH ST SE R-2
|
|
02/08/21
FC 1331 LLC / FC 1331 LLC
BP2101814 /
POST CARD
|
10 I ST SE
|
|
02/16/21
CAPITOL HILL RACQUET CLUB / NA; VICTORIA STEINHOFF
SB2100112 /
CONSTRUCTION
Installation of up to six (6) 3-inch diameter direct-push Geoprobe borings to depths of up to 30 feet below grade as part of an environmental assessment.
|
555 L ST SE
|
|
01/29/21
UNITED STATES OF AMERICA / RENNE WELL; RICK HARLAN SCHNEIDER
B2102004 /
CONSTRUCTION
DGS PROJECT REHABILITATION+RESTORATION OF THE HISTORIC LINCOIN FIELDHOUSE
|
861 NEW JERSEY AVE SE 20003
|
|
02/23/21
809-853 NEW JERSEY AVE ACQUISITION LLC / SUSANA VAZQUEZ
AH2100728 /
CONSTRUCTION
Dismantling of tower crane.
|
809 NEW JERSEY AVE SE
|
|
02/11/21
GREYSTAR GP LLC 809-853 NEW JERSEY AVENUE ACQUISITION LLC / null
E2103926 /
SUPPLEMENTAL
|
853 NEW JERSEY AVE SE
|
|
02/11/21
GREYSTAR GP LLC / null
E2103924 /
SUPPLEMENTAL
|
861 NEW JERSEY AVE SE
|
|
02/05/21
GS CSX HOTEL OWNER LLC / null
E2103762 /
SUPPLEMENTAL
|
1275 NEW JERSEY AVE SE
|
|
02/02/21
FC 1275 NJ LLC / null
E2103662 /
SUPPLEMENTAL
|
|
|
02/11/21
FC 1275 NJ LLC / null
P2103445 /
SUPPLEMENTAL
|
848 SOUTH CAPITOL ST SE
|
|
02/16/21
CXS TRANSPORTATION INC / VICTORIA STEINHOFF; TBD
SB2100111 /
CONSTRUCTION
Installation of up to six (6) 3-inch diameter direct-push Geoprobe borings to depths of up to 30 feet below grade as part of an environmental assessment.
|
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;
|
|
|
No commercial transaction records added or modified in the past two weeks. |
|
|