The blistering pace of new projects slowed a bit this year, allowing me some (needed) breathing space in terms of keeping up with construction progress. But I wandered around on Saturday, and here's a few things of note I saw:
* The JBG apartment project now known as 1221 Van is speeding along, and has changed the skyline along South Capitol considerably. Taking southward-facing photos in the winter months is always dicey, but I couldn't pass up a shot of the new structure and its neighbor directly to the south.
* Insignia on M's logo at the top of its New Jersey Avenue face does easily catch one's eye.
* The preparation work to transform the O Street Pumping Station into the glimmery new DC Water Headquarters is now underway.
* CSX announced this week that the new second-track Virginia Avenue Tunnel is "nearing completion," and it certainly looks that way at the western mouth of both new and old tunnels. And I got to see a train coming out, too! (But the project isn't over--next work will shift to reconstructing the 100-year-old original tunnel.)
* The excavation for the combination condo-and-rental buildings project known as "Parcel O" at the Yards has proceeded apace.
* Conversely, the hole for the 99 M office building has remained basically unchanged since late summer. (Compare the below photo to this one taken in August.) There was a new crane-related after-hours permit approved for the site last week, so maybe things are about to start moving again. UPDATE, 12/13: A representative for the 99 M project has gotten in touch with me to say that there has actually been considerable "complex" work going on at the site, it's just that it's mostly underground/out of sight.
Comments (10)
   
 
 More About Development News

JDLand.com Home

Comments

dude says: (12/12/16 9:29 PM)
I like the look of Insomnia...


jdc says: (12/13/16 8:38 AM)
The pace of 99 M has definitely surprised me, compared to the speed of the hotel and projects also on 1st. Is it because of the massive hole that needed to be dug and shored up?


JD says: (12/13/16 9:20 AM)
As I mentioned in the post, it's not a slow pace--it's been stopped altogether since August. Given that it is right next to the Metro station, and that there are huge steel thingamabobs holding up the western and southern walls, there must be some issues with the shoring that they have been having to come up with a solution for.


202_cyclist says: (12/13/16 11:17 AM)
Perhaps because 1221 Van is out on its own along So. Capitol Street, it appears to be pretty big when viewed from a distance.

Also, I noticed that Dock 79 has a dog park. Is this only for residents of that building? Since we don't have a dog, I haven't paid attention to any previous discussion of that.


JD says: (12/13/16 12:11 PM)
UPDATE, 12/13: A representative for the 99 M project has gotten in touch with me to say that there has actually been considerable "complex" work going on at the site, it's just that it's mostly underground/out of sight.


conngs0 says: (12/13/16 12:47 PM)
Perhaps the "complex" work taking place underground that 99 M is referring to SafeTrack?


202_cyclist says: (12/13/16 12:53 PM)
@JD: Maybe 99M is building the secret tunnels....


Section314 says: (12/13/16 1:22 PM)
Now that the trailers are gone and McDonald's is closing, do you have any sense of when construction will start on these projects or on "Monument Valley"?


JD says: (12/13/16 1:28 PM)
There are excavation and/or foundation permits in process for the empty part of the Fairgrounds, and Monument Valley, and the NAB HQ/10 Van joint project, and the McD's project, and the Capper apt bldg at 2nd and L, and the second phase of the Parc Riverside. Those are all the ones I expect to get started in coming months, though of course something can always derail plans. But those are the ones that really seem to be planning to roll once they get their permits.


CJBabyDaddy says: (12/20/16 1:36 AM)
4th & Tingey: Billboard for The Bower is up, promoting sales to begin Spring 2017.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

202_cyclist on Capitol Riverfront BID: JD-- congratulations on the award. This morning I noticed that glass is being i...
Joni on Capitol Riverfront BID: Congratulations on your well deserved award! I think I've told you before that y...
sameter on Capitol Riverfront BID: congrats on being a constant in the community and being a positive change. well...
CJBabyDaddy on Capitol Riverfront BID: A meet-up after tomorrow’s 15th anniversary gala sounds like a great idea. (Can...
Message Board (beta)

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
300 B/O K ST SE   BURGLARY
Burglary Two
 01/13/18
1000 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/11/18
500 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 01/09/18
900 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/07/18
100 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 01/04/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/04/18
400 B/O M ST SE   THEFT
Shoplifting
 01/02/18
UNIT B/O K ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/31/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/19/17

Recent Issued Building Permits Archive  
1331 2ND ST SE   
12/22/17 
DC WATER / DAVE LEVINE
AH1800369 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water, Corman Construction 301-343-5417. TO EXCLUDE LEGAL HOLIDAYS.
1331 4TH ST SE CU   
12/27/17 
FC 1331 LLC / GARY BRENT; N/A
SG1800119 / CONSTRUCTION
Install 1 illuminated blade sign and 7 non-illuminated window vinyl signs - CHLOE BY HAIDAR KAROUM
   
12/28/17 
FC 1331 LLC / BEN BEDDO
TL1700205 / CONSTRUCTION
New Tenant Layout for restaurant
1300 4TH ST SE   
01/05/18 
FORREST CITY WASHINGTON / GEORGE ARTHUR KING
SB1800091 / CONSTRUCTION
To abandon 18 6 inch diameter 80 foot deep dewatering wells and 4 2 inch diameter 50 feet deep observation wells per the DOEE regulations
1346 4TH ST SE   
01/12/18 
ALAN OWINGS / ROBERT HENRY
AH1800415 / CONSTRUCTION
After Hours Permit for 1 / 15 / 18 from 7AM to 7PM to perform concrete operations, framing, operations, and utility operations.
411 I ST SE   
12/27/17 
ABIGAIL A SMITH / ROBERT D. JOHNSTON
E1802679 / SUPPLEMENTAL
337 L ST SE   
12/22/17 
JENNIFER LANCASTER / null
E1802602 / SUPPLEMENTAL
   
01/11/18 
JENNIFER LANCASTER / BJORN FALK
SOL1800005 / CONSTRUCTION
Installation of a 3.6kW solar PV system. Roof Mounted, 10 panels
300 M ST SE STE# 400   
01/03/18 
FEDERAL CENTER LP / SAM HOLLEN
B1803531 / CONSTRUCTION
INTERIOR RENOVATION TO 4TH FLOOR OFFICE CONFERENCE ROOM. PARTITIONS, CEILING, MECHANICAL, ELECTRICAL AND LIFE SAFETY. NO PLUMBING OR STRUCTURAL. 680 SQUARE FEET. CACI SUITE 400
25 POTOMAC AVE SE DOCK 79   
01/11/18 
RIVERFRONT HOLDINGS I LLC / null
P1802701 / SUPPLEMENTAL
227 TINGEY ST SE   
12/29/17 
JW CAPITAL PARTNERS / MELISSA DIAZ
FD1700126 / CONSTRUCTION
Parcel L1- Foundation to Grade permit for the new construction on an 11 story full service hotel building with restaurant and retail.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.