With the 305-unit Dock 79 apartment building very close to completion, the developers of the site on the Anacostia River that us oldsters still refer to as Florida Rock have now filed with the Zoning Commission their plans* for the project's next phase, a 130-foot-tall 253-unit residential building with 12,500 square feet of retail at 71 Potomac Avenue.
There will be at least two levels of underground parking, with a third level being pondered "given the parking demands of [Nationals Park] and the pending soccer stadium." And although the building is not covered by the city's Inclusionary Zoning laws, the filing says that eight percent of the units will be set aside for households with incomes up to 80 percent of the Area Median Income.
The construction of this building will also bring the completion of "Florida Rock Alley," running between 71 Potomac and Dock 79 and providing another route for pedestrians to move between Potomac Avenue and the waterfront along with the access to parking and loading for both buildings. The waterfront Esplanade will also be extended along 71 Potomac's frontage.
The 12,500 square feet of retail is an increase the previously approved 5,600 square feet. In the filing statement, developers Florida Rock Properties and MRP Realty mention that "based on the success in leasing retail space in Dock 79, the Applicant is confident that there is a retail market along Potomac Avenue," and that "the desire for retailers to locate in this area has only increased" since the previous plans were approved in 2013.
The site plans are very helpful to not only understand where this Phase 2 building at 71 Potomac will be, but how the eventual third and fourth phases are dependent on the construction of the new Douglass Bridge and its accompanying traffic oval, and the demolition of the existing bridge. (The filing mentions DDOT's current estimated schedule of a notice to proceed on the new bridge in 2017 and completion in 2020, but We Shall See.)
There are a slew of renderings in the zoning packet, which of course I'm snagging (we'll call it a one-for-one exchange for all of the photos of mine they used in the site overview portion of the package!).
These plans will require ANC presentations and a vote and zoning hearings and building permits and financing, so don't pack your bags just yet.
*For those to whom such things matter, this is a second-stage PUD filing.
Comments (12)
   
 
 More About Development News

JDLand.com Home

Comments

202_cyclist says: (7/16/16 10:43 AM)
Thanks for the post. At 130 ft tall, this should have some spectacular views.

I think it is the FL Rock Alley--I noticed nice decorative overhead lights had been strung across this space. It should be a nice area when Dock 79 opens.


202_cyclist says: (7/16/16 10:49 AM)
I also like the solar panels above the dock in the rendering. Hopefully Forest City can do that with the Yards Park marina as well.


walt says: (7/16/16 3:43 PM)
image 7 looks strikingly like Velocity.


jdc says: (7/16/16 4:46 PM)
Doesn't look as nice on outside to me, IMO. I like the color palette of Dock 7.


dude says: (7/17/16 8:44 AM)
Looks fine, nothing special. Let's hope they build the larger garage. Can never have too much parking.


202_cyclist says: (7/17/16 9:43 AM)
Dude:

" Let's hope they build the larger garage. Can never have too much parking."

No offense but wrong, wrong, wrong. Much has been written about the adverse impacts of parking but abundant parking undermines transit ridership and walking/biking, significantly adds to the cost of housing, and ensures that the building is designed around accommodating vehicles rather than other aesthetic priorities.

link


dude says: (7/17/16 10:52 PM)
Oh right, people love riding metro.


RMP says: (7/18/16 8:10 AM)
I notice that Parcel O is now on the Highlighted Projects map. Look forward to following that progress.


jdc says: (7/18/16 8:36 AM)
I can imagine a future - maybe 2019/2020 - where the empty lots that plague JD Land are only the parcels around canal park and parcel A. Not that those aren't significant vacant land.


202_cyclist says: (7/18/16 10:54 AM)
@Dude-- I can't excuse the inexcusable with metro's performance.


FYI-- when I was running this morning, I noticed a needle in the vacant lot next to the charter school. Watch out if you are walking your dog there.


jdc says: (7/20/16 3:47 PM)
Does anyone see the office space or hotel in later phases not ever occurring, and instead it being changed to condos or apartments? I guess of the two, I think a hotel may be a bit more likely because of its proximity to the soccer stadium and Ft. McNair. But I cannot see office space really being a) needed or b) needed there.


jdc says: (7/20/16 3:49 PM)
I also see they're pulling the permit for the pool at Dock 79.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

Hastings on Whole Foods: I noticed two bright orange signs on the WF front doors regarding a hearing on D...
Westnorth on Whole Foods: Yawwwwwn. Wake me when it's time for happy hour. (Oh wait, I missed that!)
JD on Whole Foods: That's why you guys pay me the big bucks, right? :)
Ampersand on Whole Foods: JD I'm duly impressed by your ability to predict the location of the eventual WF...
Edna on Whole Foods: $5.99 / lb. for quinoa? Ouch. And I'm not one of those Whole-Foods-is-soooo-ex...
malatesta on Whole Foods: I mean, it is a whole foods, so trying too hard is like the whole deal, right?
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/10/18
50 M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/08/18
1100 B/O 10TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/07/18
100 B/O M ST SE   ROBBERY  10/05/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 10/04/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 09/28/18
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/27/18
100 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/26/18
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
1100 B/O 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/24/18
150 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/22/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 09/22/18
1000 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle) - Street / Unknown
 09/16/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/16/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/12/18 
null / DONNA G GRAHAM
AH1900071 / CONSTRUCTION
WR #3585809 - M.ALLEN / A.PRICE - 1100 2ND PLACE SE - PEPCO CREWS WILL BE SPLICING CABLES AT NIGHT STARTING 10 / 15 / 18 UNTIL 11 / 2 / 18 FROM 10:00 PM TIL 7:00AM MONDAY THROUGH SUNDAYS
1015 4TH ST SE   
09/19/18 
GASTON CHAN / null
E1810828 / SUPPLEMENTAL
1346 4TH ST SE   
09/28/18 
ALAN OWINGS / ROBERT HENRY
AH1801345 / CONSTRUCTION
After Hours Permit for 10 / 08 / 2018 to perform construction work with the below activities: Interior Operations: 7AM - 7PM - ADVANCED NOTICE TO RESIDENTS, OPERATION CONTACT PERSON ON SITE TO ADDRESS ANY UNEXPECTED NOISE ISSUES BEFORE 9:00AM WITH CONTACT NAME AND TELEPHONE. Exterior Operations: 9AM-7PM - NO EXTERIOR ACTIVITY, TRAFFIC, NOISE GENERATION BEFORE 9am WITH ON SITE OBSERVANCE. ...
   
10/09/18 
FC 1346, LLC / null
E1900300 / SUPPLEMENTAL
2 I ST SE   
09/19/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1801319 / CONSTRUCTION
WR #3573836 - VAETH / BRUNO - WARD 6 - 20003 - PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" ST ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL CABLES - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY THRU FRIDAYS) FROM 9PM TO 7 AM - PEPCO CREWS WILL ALSO BE WORKING WEEKENDS (SATURDAY AND SUNDAYS) FROM 6AM TIL 6PM - WORK IS ONGOING
   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802612 / SHOP DRAWING
Install 1 New G2S Elevator - 4000LBS @ 350FPM
   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802611 / SHOP DRAWING
Install 3 new G2S Elevators - 3500LBS @ 350FPM
   
09/26/18 
MCDONALDS CORPORATION / null
E1811060 / SUPPLEMENTAL
   
10/09/18 
CRESECENT CAPTIAL VIEW / null
P1900223 / SUPPLEMENTAL
4 I ST SE   
10/09/18 
CRESCENT COMMUNITIES / null
P1900221 / SUPPLEMENTAL
328 K ST SE   
09/27/18 
MARK BARRETT / null
E1811075 / SUPPLEMENTAL
   
10/04/18 
MARK BARRETT / BJORN FALK
SOL1800999 / CONSTRUCTION
Installation of a 5.559kW solar PV system. Roof mounted, 17 panels with integrated microinverters.
401 L ST SE   
10/11/18 
MICHAEL R BRICKMAN / FLOYD H. FURR
P1900299 / SUPPLEMENTAL
   
10/11/18 
MICHAEL R BRICKMAN / DARIUS LYVERS 703-491-1234
M1900108 / SUPPLEMENTAL
300 M ST SE 1ST 20024   
09/21/18 
ELLEN OPDYKE / null
P1809360 / SUPPLEMENTAL
300 M ST SE 3   
09/21/18 
FEDERAL CENTER LP / null
P1809359 / SUPPLEMENTAL
300 M ST SE 8 20024   
09/24/18 
BARBARA D HAMLETT / null
P1809404 / SUPPLEMENTAL
300 M ST SE   
09/25/18 
FEDERAL CENTER LP / null
E1811000 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1811001 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1810999 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
09/20/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1810877 / SUPPLEMENTAL
   
09/21/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1809362 / SUPPLEMENTAL
79 POTOMAC AVE SE 1ST FL   
10/03/18 
RIVERFRONT HOLDINGS I LLC / null
P1900101 / SUPPLEMENTAL
71 POTOMAC AVE SE   
09/28/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1801325 / CONSTRUCTION
After hours to pour concrete with pump truck 9 / 28 / 2018 to 10 / 28 / 22018 from 11pm to 7am
   
10/04/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1900029 / CONSTRUCTION
Afterhours to pour concrete with pump truck saturday 10 / 06 / 2018 from 12am to 7am
79 POTOMAC AVE SE   
10/04/18 
RIVERFRONT HOLDINGS I LLC / null
M1900054 / SUPPLEMENTAL
201 TINGEY ST SE   
10/09/18 
JBG/SEFC 170 LLC / DONNA G GRAHAM
AH1900051 / CONSTRUCTION
WR #3566756 - M.ALLEN / BRUNO - 201 TINGEY ST SE - PEPCO CREWS WILL BE INSTALLING NETWORK TRANSFORMERS AND INSTALLING CABLES - PEPCO WILL HAVE TO SHUT DOWN 3RD ST BETWEEN WATER ST & TINGEY ST SE TO SET TRANSFORMERS ONLY - WORK WILL BEGIN 10 / 12 / 18 THROUGH 11 / 30 / 18 - MONDAY THRU FRIDAYS FROM 10PM TIL 8AM AND SATURDAYS AND SUNDAYS FROM 6AM TIL 6PM
227 TINGEY ST SE   
10/09/18 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1900056 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for follow-up test run of the precast concrete fa├žade panel installation. Work to take place 7pm on 10 / 10 to 7am on 10 / 11.
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL 703-631-2711
FB1900011 / SUPPLEMENTAL
NO. TO BE INSTALLED (2) GROSS RATING: 999999 BTU / HR NATURAL GAS STEAM PRESSURE 160 PSI OUTPUT: 960,000 BTU / HR
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL
UP1900012 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.