Since January, 2003
            
 (a random before-and-after moment)
January 22, 2006
October 16, 2016
1st at M, Looking North (see more)

The latest presentation slides from last week's 11th Street Bridges project's Community Communications Committee Meeting have been posted, and a few of them caught my eye (or bought my eye, for you fans of obscure Monty Python references). TheWashCycle recently posted a photo of the work underway on the overlooks that are now under construction just down-river of the new local bridge, using the old piers as their bases, and this is what they are expected to look like when completed (click to enlarge):
There is also a rendering (seen at right) of how the Anacostia Riverwalk Trail will run both under the bridges and down from O Street when finished; it also shows the small overlook that will be built out into the river just to the east of the entrance gate to the Navy Yard Promenade. WashCycle also got a recent photo of the path under construction, where you can see the outlines of what the rendering shows is coming.
The presentation slides also have some photos of the demolition underway on the old outbound freeway flyover, and aerial photos of the work that's completed and still underway on the east side of the river. There's also, on page 21, an image which looks like they've already almost completed the filling-in of the portion of the Southeast Freeway between 8th and 11th, since it shows dirt almost up to the underside of the existing bridge that takes 11th Street across the sunken freeway between I and L.
What all of this really means is that I need to get back to 11th Street with my camera pretty soon, since my last batch of photos is now a bit dated (waaah!).
Comments (11)
   
 
 More About 11th Street Bridges

JDLand.com Home

Comments

jacques says: (3/19/13 5:18 PM)
So does that mean the 11th Street Recreation Bridge has gone from "a long shot" to "completely off the table?"



JD says: (3/19/13 5:23 PM)
No, it was always planned that these overlooks would be built. If the recreation bridge somehow comes to pass, the overlooks would be demolished.



Maelstrom says: (3/19/13 8:20 PM)
new news - They've demolished the roadway lanes from half of 11th street by the flyovers - just the underlying steel is left.


monkeyrotica says: (3/20/13 8:35 AM)
What the? I was promised ziplines! Where the HELL are my ziplines?!?!?

link


dcgent says: (3/20/13 11:51 AM)
Completion date?


JD says: (3/20/13 12:02 PM)
By summer, I believe.


MarkB says: (3/20/13 1:57 PM)
Hope this isn't too off topic, but have we seen what the plan is for the current 8th SE St off ramp? It looks as if it's ramp is the next to go...


JD says: (3/20/13 3:44 PM)
@MarkB, if you look at this link:

link

It *appears* that they are planning for a new on-ramp at 8th, a smidge to the west of the current one. (New one marked as E-2) It seems like they had to move it a bit so that ramp D-4 can come from the freeway down to 11th Street at the new Southeast Blvd. intersection.


MarkB says: (3/20/13 5:12 PM)
Ahhh!!! Looking forward to Phase 2! Thanks!


ksalvador says: (3/25/13 8:54 AM)
On the presentations 5th slide you can see a good shot or ramps C-1 and C-2. In the pictures it doesn't look like there is traffic on them but I didn't know if missed an announcement. I know they were scheduled to be done in late fall. Do you know if they are open?

Thank you! Loooove your site. I just registered an account but I have been reading your posts for well over a year.


JD says: (3/25/13 9:26 AM)
I think the C1 and C2 ramps are opening soon--Dr. Gridlock mentioned them here: link It was the ramps to the 11th Street Local bridge from NB 295 and from the local bridge to SB 295 that opened last fall. I think C1 and C2 are the mirror images (to the local bridge from SB 295 and from the local bridge to NB 295).

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

202_cyclist on Catching Up With: @AllIsNotWells -- that is what I thought. Thank you for confirming.
202_cyclist on Catching Up With: @AllIsNotWells -- that is what I thought. Thank you for confirming.
AllIsNotWells on Catching Up With: @202 New member orientation for the 116th congress.
202_cyclist on Catching Up With: Folks— what big event is happening at the Courtyard Marriott this week?
CJBabyDaddy on Catching Up With: @spiritequality: Rhymes with “groovy tea waiter” and “newbie fee hater?”
JNB on Catching Up With: HQ2 to Crystal City. Just announced.
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/13/18
150 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/12/18
400 B/O M ST SE   THEFT FROM AUTO
Theft Of Motor Vehicle Parts Or Accessories
 11/11/18
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle) - Convenience Store
 11/11/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/09/18
700 B/O M ST SE   THEFT
Theft First Degree (all Other Larceny)
 11/09/18
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/08/18
400 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 11/07/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/07/18
800 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/31/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/30/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 10/29/18
50 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/18
100 B/O O ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/18
1400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  10/26/18
100 B/O M ST SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 10/23/18
900 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/23/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/22/18
900 B/O 5TH ST SE   HOMICIDE
Murder I
 10/20/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/20/18
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree (theft From Building)
 10/19/18
400 B/O M ST SE   THEFT
Shoplifting
 10/17/18
100 B/O N ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/17/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/23/18 
null / ANDY MCKELVEY
SP1800044 / CONSTRUCTION
Construct outdoor swimming pool on 10th floor roof of new building
1013 4TH ST SE   
11/05/18 
EVA WALTER / KYLE YOST
SOL1900066 / CONSTRUCTION
5.89kw rooftop solar pv system, less than 4' above roof
   
11/07/18 
EVA WALTER / null
E1901297 / SUPPLEMENTAL
1346 4TH ST SE   
10/18/18 
FC 1346, LLC / DFM DEVELOPMENT SERVICES, LLC
B1809670 / CONSTRUCTION
Parcel O-2 at the Yards. Revision to Permit B1610576 for installation of flood wall on 5th Street, SE, the reduction of roadway width, and widening of sidewalk to provide adequate pedestrian clear space between flood wall and edge of tree pit. TPR
   
11/01/18 
ALAN OWINGS / ROBERT HENRY
AH1900133 / CONSTRUCTION
After Hours Permit for 11 / 12 / 2018, to perform construction work with the below activities: Interior Operations: 7AM-7PM Exterior Operations: 9AM-7PM
1000 5TH ST SE   
10/31/18 
UNITED STATES OF AMERICA / JOY WILDER
B1901427 / CONSTRUCTION
Non Construction permit to change load for current Child Development Center with 26 children 3 to 6 years old +3 Staff to Child Development Center with 30 Children + 3 Staff.
2 I ST SE   
11/05/18 
CRESCENT CAPITAL VIEW / CASSANDRA MOSLEY
AH1900160 / CONSTRUCTION
Installation of wet utility services to the new building at 4 I Street SE including fire service, domestic service, and storm sewer.
10 I ST SE   
10/24/18 
CAPITOL HILL RACQUET CLUB / BOB BIROONAK; N/A
SG1900026 / CONSTRUCTION
Relocating existing freestanding sign
110 I ST SE   
11/06/18 
null
E1901238 / SUPPLEMENTAL
200 I ST SE 20009   
10/25/18 
DISTRICT OF COLUMBIA / null
M1900267 / SUPPLEMENTAL
200 I ST SE   
11/05/18 
GOVERNMENT OF THE DISTRICT OF COLUMBIA / null
E1901223 / SUPPLEMENTAL
   
10/25/18 
DISTRICT OF COLUMBIA / CLIFFORD DIXON
B1809410 / CONSTRUCTION
DGS OCTO BUILDING...NEW GENERATOR ON THE ROOF WITH ASSOCIATED MECHANICAL
   
11/07/18 
DISTRICT OF COLUMBIA / DANIEL MCGUIRE
P1901098 / SUPPLEMENTAL
300 M ST SE 8TH FL   
10/24/18 
FEDERAL CENTER LP / ALFRED JORDAN 2024375067
E1900838 / SUPPLEMENTAL
300 M ST SE 8TH FLOOR 20003   
10/22/18 
JBG SMITH - MORGAN JOHNSON-MASSEY / null
E1900736 / SUPPLEMENTAL
130 M ST SE   
11/09/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / RICHARD PLUMLEY
P1901176 / SUPPLEMENTAL
250 M ST SE   
11/07/18 
WCSMITH - BRIAN STROTT / GEORGE ARTHUR KING
SB1900025 / CONSTRUCTION
Drill and construct two 2 inch diameter observation wells 42 feet below existing grade utilizing mud rotary drilling methods. All drill spoils will be contained, tested and disposed of per DOEE regulation.
400 M ST SE   
10/18/18 
CAPPER SENIOR 11 LIMITED PARTNERSHIP / null
E1900650 / SUPPLEMENTAL
   
11/02/18 
CAPPER SENIOR 11 LIMITED PARTNERSHIP / null
E1901156 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
10/31/18 
CONSOLIDATED RAIL CORPORATION / BRANDON KNAPP
AH1900131 / CONSTRUCTION
Work in the public ROW with the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, concrete structure, paving, and site restoration construction activities.
   
11/07/18 
CONSOLIDATED RAIL CORPORATION / RPS INC
SB1900023 / CONSTRUCTION
Per Work Plan, Geotechnical Investigation, dated October 18, 2018 (see attached), the work involves drilling 12 soil borings using a HSA rig for the purpose of collecting soil samples for geotechnical subsurface exploration. Boring depths range from 80 to 150 ft. Borings will be properly backfilled after completion.
1111 NEW JERSEY AVE SE   
10/23/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / MICHAEL PISA; PISA
SG1800505 / CONSTRUCTION
Install 2 sets of wall mounted illuminated channel letters
   
10/25/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1900860 / SUPPLEMENTAL
   
11/05/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / MICHAEL B. BELL
E1901199 / SUPPLEMENTAL
227 TINGEY ST SE   
11/01/18 
JOHN MORIARTY & ASSOCIATES / DFM DEVELOPMENT SERVICES, LLC
AH1900141 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 11 / 5 through 12 / 5.
300 TINGEY ST SE   
11/05/18 
FC BOILERMAKER LLC / DREW PEISHEL; JOHN RANOUS
B1813340 / CONSTRUCTION
Minor interior tenant improvment including building one non-load bearing partitiion wall adding millwork fixtures including cash desk, fitting rooms. No Structural work. Some electrical updates. **LEVEL 2 ALTERATION
   
11/08/18 
FC BOILERMAKER LLC / STEPHEN ADAMS 2403042373
E1901337 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.