On Monday night, the Zoning Commission voted 4-0-1 to approve DCHA's request for a second two-year time extension on the PUD deadlines to build the Capper Community Center on the now-empty lot on 5th Street SE between K and L. With this vote, building permits would need to be filed by July 1, 2014, with construction needing to be underway by July 1, 2015, provided another extension isn't someday requested and granted.
The extension received votes of support from both ANC 6B and ANC 6D, and a letter from a steering committee of Capper public housing residents also expressed support. Commissioner Peter May, referencing the "contentious" discussions in the past regarding this project and his own unhappiness about seeing it delayed, said it was "reassuring to know that key members of the community are supportive," otherwise he would be "similiarly unhappy." But he did vote in favor of the extension, as did Chairman Anthony Hood and commissioners Marcie Cohen and Michael Turnbull. (The commission's fifth seat is currently empty, with vice chair Konrad Schlater's recent decampment for a new job in Chicago.)
Included the paperwork provided to the Zoning Commission is a letter from DC Housing Authority executive director Adrianne Todman detailing the various high-finance moves over the past few years that have helped the overall Capper redevelopment move forward but that haven't trickled down to fund the community center. The letter says that the Housing Authority anticipates a $55 million bond issuance within the next year that will pay off the previous $29 million Bond Anticipation Notes and provide enough proceeds to continue the infrastructure work around Capper "and to construct the community center, which we estimate will cost $7.6 million." These moves require legislation, so we'll be able to cast an eye toward the DC council this fall to see if things are progressing as anticipated.
Also in that letter is this tidbit: "Lastly, DCHA is working with and soliciting a potential anchor tenant that will operate the community center and also contribute funding for the construction of the community center." Very interesting....
If you want to know still more about the history of plans for a new community center on this site (the old one was demolished in 2007), I point you to this pile of posts.
Comments (10)
   
 
 More About Capper

JDLand.com Home

Comments

MJM says: (7/12/12 12:25 PM)
More excuses but they sure can kick the can down the road


Sophia Monster says: (7/12/12 5:12 PM)
Happy to have them kick the can... just curious what type of anchor tenant is an appropriate fit for this location. A crossfit gym? A McDonalds? A dry cleaner? I can't picture it.


Carey says: (7/12/12 5:14 PM)
Could they be thinking Marines?


Eric says: (7/12/12 9:15 PM)
Why are you happy to have them kick the can? What's the significance of this place?


conngs0 says: (7/13/12 11:21 AM)
I suppose one good reason for the delay is that by allowing the neighborhood to grow up a bit more before beginning work on the Community Center, the planners will have a better idea of how to orient the building to best suit the needs of the neighborhood with less redundancy.

For instance, if a gym is constructed in the Twelve12 building, then perhaps there will be less of a need for one in the Community Center (or at least not as big of a gym). In that case, perhaps the Community Center could be equipped with a basketball court and other athletic facilities.

I'm also a little confused about what type of "anchor tenant" that would be approached to run the Community Center. Part of my confusion stems from a lack of understanding regarding the operation of community centers in general, but it doesn't seem conducive to a purely commercial enterprise.


Sophia Monster says: (7/13/12 12:47 PM)
I guess I don't think it's that bad to have the lot remain empty while appropriate plans are scoped out along the lines of conngs0's comment above. The programming of the community center will determine its space needs. I also really think it makes sense for that programming to serve what will happen at Van Ness... which as of now is a bit of a mystery.


JD says: (7/13/12 1:20 PM)
One thing to remember on the Community Center (and why for years it caused a lot of very contentious discussions) is that originally it was envisioned as a big amenity for the public housing residents, ensuring that they didn't lose access to a community center they had before Hope VI and also giving them something newer with better offerings in return for dealing with the dislocation of the closing of the Cappers.

In other words, a gym at Twelve12 is probably not going to help the public housing residents much at Capitol Quarter. There are needs designed into the CC for the subsidized members of the community that other people now moving into the neighborhood can get on their own. (Computer access, for one.) And a place for kids to hang out, instead of, as the cliche goes, "on the street."

But it's also now a very different "community" communicating its wants and desires to the Zoning Commission than during the CC's previous appearances. Might be good to make sure that the people for whom the center was originally envisioned don't lose their voice.



Sophia Monster says: (7/13/12 1:32 PM)
Interesting context, JD. And presumably some of the children "on the street" might also be Van Ness students.


Sophia Monster says: (7/13/12 1:32 PM)
(some day)


JD says: (7/17/12 10:48 PM)
Sorry for the silence all of a sudden--no big news to report (it is summer, after all), but I'm also having a bit of a post-surgery setback. Nothing serious, but have been resting instead of fulfilling my fiduciary duty here. Might be a few more days of that.


Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

Hastings on Whole Foods: I noticed two bright orange signs on the WF front doors regarding a hearing on D...
Westnorth on Whole Foods: Yawwwwwn. Wake me when it's time for happy hour. (Oh wait, I missed that!)
JD on Whole Foods: That's why you guys pay me the big bucks, right? :)
Ampersand on Whole Foods: JD I'm duly impressed by your ability to predict the location of the eventual WF...
Edna on Whole Foods: $5.99 / lb. for quinoa? Ouch. And I'm not one of those Whole-Foods-is-soooo-ex...
malatesta on Whole Foods: I mean, it is a whole foods, so trying too hard is like the whole deal, right?
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/10/18
50 M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/08/18
1100 B/O 10TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/07/18
100 B/O M ST SE   ROBBERY  10/05/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 10/04/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 09/28/18
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/27/18
100 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/26/18
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
1100 B/O 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/24/18
150 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/22/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 09/22/18
1000 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle) - Street / Unknown
 09/16/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/16/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/12/18 
null / DONNA G GRAHAM
AH1900071 / CONSTRUCTION
WR #3585809 - M.ALLEN / A.PRICE - 1100 2ND PLACE SE - PEPCO CREWS WILL BE SPLICING CABLES AT NIGHT STARTING 10 / 15 / 18 UNTIL 11 / 2 / 18 FROM 10:00 PM TIL 7:00AM MONDAY THROUGH SUNDAYS
1015 4TH ST SE   
09/19/18 
GASTON CHAN / null
E1810828 / SUPPLEMENTAL
1346 4TH ST SE   
09/28/18 
ALAN OWINGS / ROBERT HENRY
AH1801345 / CONSTRUCTION
After Hours Permit for 10 / 08 / 2018 to perform construction work with the below activities: Interior Operations: 7AM - 7PM - ADVANCED NOTICE TO RESIDENTS, OPERATION CONTACT PERSON ON SITE TO ADDRESS ANY UNEXPECTED NOISE ISSUES BEFORE 9:00AM WITH CONTACT NAME AND TELEPHONE. Exterior Operations: 9AM-7PM - NO EXTERIOR ACTIVITY, TRAFFIC, NOISE GENERATION BEFORE 9am WITH ON SITE OBSERVANCE. ...
   
10/09/18 
FC 1346, LLC / null
E1900300 / SUPPLEMENTAL
2 I ST SE   
09/19/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1801319 / CONSTRUCTION
WR #3573836 - VAETH / BRUNO - WARD 6 - 20003 - PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" ST ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL CABLES - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY THRU FRIDAYS) FROM 9PM TO 7 AM - PEPCO CREWS WILL ALSO BE WORKING WEEKENDS (SATURDAY AND SUNDAYS) FROM 6AM TIL 6PM - WORK IS ONGOING
   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802612 / SHOP DRAWING
Install 1 New G2S Elevator - 4000LBS @ 350FPM
   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802611 / SHOP DRAWING
Install 3 new G2S Elevators - 3500LBS @ 350FPM
   
09/26/18 
MCDONALDS CORPORATION / null
E1811060 / SUPPLEMENTAL
   
10/09/18 
CRESECENT CAPTIAL VIEW / null
P1900223 / SUPPLEMENTAL
4 I ST SE   
10/09/18 
CRESCENT COMMUNITIES / null
P1900221 / SUPPLEMENTAL
328 K ST SE   
09/27/18 
MARK BARRETT / null
E1811075 / SUPPLEMENTAL
   
10/04/18 
MARK BARRETT / BJORN FALK
SOL1800999 / CONSTRUCTION
Installation of a 5.559kW solar PV system. Roof mounted, 17 panels with integrated microinverters.
401 L ST SE   
10/11/18 
MICHAEL R BRICKMAN / FLOYD H. FURR
P1900299 / SUPPLEMENTAL
   
10/11/18 
MICHAEL R BRICKMAN / DARIUS LYVERS 703-491-1234
M1900108 / SUPPLEMENTAL
300 M ST SE 1ST 20024   
09/21/18 
ELLEN OPDYKE / null
P1809360 / SUPPLEMENTAL
300 M ST SE 3   
09/21/18 
FEDERAL CENTER LP / null
P1809359 / SUPPLEMENTAL
300 M ST SE 8 20024   
09/24/18 
BARBARA D HAMLETT / null
P1809404 / SUPPLEMENTAL
300 M ST SE   
09/25/18 
FEDERAL CENTER LP / null
E1811000 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1811001 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1810999 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
09/20/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1810877 / SUPPLEMENTAL
   
09/21/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1809362 / SUPPLEMENTAL
79 POTOMAC AVE SE 1ST FL   
10/03/18 
RIVERFRONT HOLDINGS I LLC / null
P1900101 / SUPPLEMENTAL
71 POTOMAC AVE SE   
09/28/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1801325 / CONSTRUCTION
After hours to pour concrete with pump truck 9 / 28 / 2018 to 10 / 28 / 22018 from 11pm to 7am
   
10/04/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1900029 / CONSTRUCTION
Afterhours to pour concrete with pump truck saturday 10 / 06 / 2018 from 12am to 7am
79 POTOMAC AVE SE   
10/04/18 
RIVERFRONT HOLDINGS I LLC / null
M1900054 / SUPPLEMENTAL
201 TINGEY ST SE   
10/09/18 
JBG/SEFC 170 LLC / DONNA G GRAHAM
AH1900051 / CONSTRUCTION
WR #3566756 - M.ALLEN / BRUNO - 201 TINGEY ST SE - PEPCO CREWS WILL BE INSTALLING NETWORK TRANSFORMERS AND INSTALLING CABLES - PEPCO WILL HAVE TO SHUT DOWN 3RD ST BETWEEN WATER ST & TINGEY ST SE TO SET TRANSFORMERS ONLY - WORK WILL BEGIN 10 / 12 / 18 THROUGH 11 / 30 / 18 - MONDAY THRU FRIDAYS FROM 10PM TIL 8AM AND SATURDAYS AND SUNDAYS FROM 6AM TIL 6PM
227 TINGEY ST SE   
10/09/18 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1900056 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for follow-up test run of the precast concrete fa├žade panel installation. Work to take place 7pm on 10 / 10 to 7am on 10 / 11.
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL 703-631-2711
FB1900011 / SUPPLEMENTAL
NO. TO BE INSTALLED (2) GROSS RATING: 999999 BTU / HR NATURAL GAS STEAM PRESSURE 160 PSI OUTPUT: 960,000 BTU / HR
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL
UP1900012 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.