Since January, 2003

Ad by HillAds
 (a random before-and-after moment)
July 17, 2008
July 12, 2014
4th at Water St., Looking Southwest (see more)

I've tried over the past few months to clampdown on runaway Tidbits posts, but these are some pretty small tidbits, so I think I'll let them through:
* Douglass Bridge: The Feds have "freed up" $68 million from previously appropriate funds to allow DC to start buying up right-of-way land for the new South Capitol Street/Douglass Bridge. NBC4 quotes DDOT chief Terry Bellamy as saying "If I had my way and we had the money, we could possibly see a new bridge in about six to seven years." But, considering they're looking for $800 million for not just the bridge itself but all the associated improvements to South Capitol Street and its interchanges with I-395 and I-295, getting the rest of the money might be a little trickier.
* Half Street: According to the Post, Monument Realty and investment partner Victor MacFarlane "are now thinking about when to begin" developing the rest of their Half Street project. The southern portion of Monument's side of Half Street (the east side--you know, where the big hole in the ground is) was originally designed with both a hotel and a residential building. And there's still no word from Akridge on a start date for their side of Half Street (the Bullpen side).
* DPW Move: While the timeline for getting DPW into their new home on Okie St. NE and out of their New Jersey and K site has slipped (shocker!), things are still moving forward, and I'm hearing that they should be moved early in 2012. But this delay is not as yet impacting William C. Smith's plans for a new apartment building just to the north--various permits have recently been approved, and WCS expects to start some deep infrastructure work, along with some clearing and grading along New Jersey Avenue north of I, sometime in December. (But WCS needs DPW out before too long because a smidge of DPW land crosses what will eventually be the new I Street and onto the WCS property.)
* Wha?: Is it just me, or does this article seem like it was written in 2009? It's a bit odd to trot out version 83 of the "there's no food in Near Southeast" story when there are leases signed for at least 10 new eateries to open in the next 12 months: Lot 38 Espresso at the old Little Red Building site (Any Minute Now!), Potbelly and Kruba Thai in the Foundry Lofts by spring, the Park Tavern at Canal Park by summer, and six choices at the Boilermaker Shops by the end of 2012. Not to mention probably another couple places in the Lumber Shed, perhaps a big one at 100 M, and a Harris Teeter in 2013. But I still predict that, when the slew of What's Happening Around Nationals Park stories come pouring out in advance of Opening Day 2012, the focus will still be on the lack of movement along Half Street (see Tidbit #1).
* New Bridge: Don't forget the dedication ceremony for the Yards/Teague bridge on Tuesday at 1:30 pm on the Yards Park side of the bridge. In addition to the mayor and DC Water chief George Hawkins, the organizers are also expecting Eleanor Holmes Norton, Naval District Washington Commandant Rear Admiral Patrick Lorge, USDOT deputy secretary John Porcari--and the Racing Presidents!
Comments (5)
 
 More Recent News

JDLand.com Home

Comments

ZoolanderANDtheBoYz says: (11/21/11 4:49 PM)
Here is the what William C. Smith apartment building on New jersey Avenue will look like link
It looks like some of the apartment buildings over by Mount Vernon triangle neighborhood. A different look for our neighborhood.


JD says: (11/21/11 4:52 PM)
I don't think that's a recent rendering--it's the general idea of what they showed me a few months ago, but it's an early version. They're supposed to be passing along some new ones in the next few weeks.


JD says: (11/21/11 5:02 PM)
(But I don't know that for sure. Just doesn't seem to be much beyond a 35% rendering.)


MJM says: (12/6/11 1:14 PM)
Looks like the DPW site is back to full ops - that place has been packed with employee cars and orange trucks the last few weeks.


JD says: (12/6/11 1:16 PM)
Leaf time!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Tell readers about your apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
JD on Southeast Blvd.: (Laziness note: I appear to have successfully made it through my latest surgery,...
E. Masquinongy on Southeast Blvd.: I wonder about the wisdom of DDOT administering this development. This is an imm...
Andrew in DC on Southeast Blvd.: It sounds like DDOT is pulling a fast one. But they wouldn't do that would they...
202_cyclist on Southeast Blvd.: Will options A1 - A3 allow for more housing to be built along the former right-o...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
M ST SE AND HALF ST SE   ROBBERY /  08/17/14
800 B/O VIRGINIA AVE SE   THEFT F/AUTO /  08/17/14
M ST SE AND 5TH ST SE   THEFT F/AUTO /  08/15/14
1400 B/O 1ST ST SE   THEFT F/AUTO /  08/14/14
1000 B/O 1ST ST SE   BURGLARY /  08/12/14
800 B/O L ST SE   THEFT F/AUTO /  08/11/14
HALF ST SE AND L ST SE   THEFT F/AUTO /  08/11/14
1000 B/O NEW JERSEY AVE SE   THEFT /  08/07/14
1100 B/O 10TH ST SE   THEFT /  08/07/14
70 B/O I ST SE   THEFT /  08/02/14
100 B/O K ST SE   THEFT F/AUTO /  08/01/14
200 B/O L ST SE   THEFT F/AUTO /  07/30/14
L ST SE AND 2ND ST SE   THEFT F/AUTO /  07/30/14
70 B/O I ST SE   MOTOR VEHICLE THEFT /  07/29/14
70 B/O I ST SE   THEFT /  07/29/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1026 3RD ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
09/04/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
410 M ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 07/11/14
to
09/08/14
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
08/11/14 
TOLL DC LP / ALBERT J. PEARCE
FB1400108 / SUPPLEMENTAL
1259 1ST ST SE   
08/11/14 
CAPITAL RIVERFRONT HOTEL LLC / CAPITAL RIVERFR HOTEL LLC
AH1400636 / CONSTRUCTION
AFTER HOURS FOR PERMIT NUMBER B1401471 FOR 8 / 12 THROUGH 9 / 11 FROM 5AM TO 7PM MONDAY THROUGH SATURDAY.
1201 4TH ST SE   
08/12/14 
JBG/FEDERAL CENTER LIC / JIM CALABRESE
AN1400129 / CONSTRUCTION
PLEASE EXTEND PERMIT AN1300174 THIS IS THE FIRST EXTENSION AND PERMIT WILL BE VALID UNTIL 1 / 31 / 2015.
1212 4TH ST SE   
08/25/14 
FC 1212 LLC / MARK E. RESNICK
E1408462 / SUPPLEMENTAL
1331 4TH ST SE   
08/14/14 
F. C. 1331 LLC / FVI 2020
B1402843 / CONSTRUCTION
CONSTRUCTION OF A BRAND NEW 11 STORY BUILDING. THE BUILDING IN TOTAL IS 350 000 SQ FT. ADDING 327 RESIDENTIAL RENTAL UNITS 20 000 SQ FT. IN COMMERCIAL SPACE AND 3 BELOW GRADE PARKING LEVELS.
   
08/15/14 
CLARK CONCRETE
AH1400650 / CONSTRUCTION
AFTER HOURS TO POUR CONCRETE ON JOBSITE FROM 7AM TO 7PM FROM SUNDAY TO SATURDAY 8 / 15 / 2014 TO 11 / 15 / 2014
1000 5TH ST SE   
08/13/14 
UNITED STATES OF AMERICA /
FD1400132 / CONSTRUCTION
NEW FOUNDATION TO GRADE PERMIT FOR NEW COMMUNITY CENTER INCLUDING UTILITIES. REVISION TO FD1400029 TO REVISE STRUCTURAL DETAILS OF COLUMS.
   
08/20/14 
UNITED STATES OF AMERICA / BRUCE G. PICKETT
E1408304 / SUPPLEMENTAL
1220 12TH ST SE   
08/27/14 
FAIRBANKS MORSE ENGINE / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1411219 / CONSTRUCTION
INTERIOR ONLY NON-STRUCTURAL ALTERATION TO EXISTING OFFICE SPACE. WORK INCLUDS MINOR PARTITION CHANGES AND THE ASSOCIATED HVAC AND ELECTRICAL ALTERATIONS.
1015 HALF ST SE   
08/12/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
TL1400162 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 1ST FLOOR PERFORMANCE STUDIO SPACE AND OFFICE SPACE. PARTITIONS FURNITURE MECHANICAL ELECTRICAL AND LIFE SAFETY. CBS
   
08/15/14 
HALF ST SE LLC / ROBERT L HUNTER
M1402951 / SUPPLEMENTAL
   
08/16/14 
SAM HOLLEN / DONALD VEALS; SAM HOLLEN; DONALD VEALS
E83010192 / SUPPLEMENTAL
200 I ST SE   
08/08/14 
DANIEL RILEY / OMAR BIAGAS; DANIEL RILEY; JOHN BIAGAS
E47247428 / SUPPLEMENTAL
41 L ST SE   
08/20/14 
WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY (WMATA) / SAMIR ALQUTRI - GEOTECHNICAL SOLUTIONS INC.
SB1400402 / CONSTRUCTION
GSI PLANS TO DRILL 4 SOIL TEST BORINGS TO CONFIRM SOIL STRENGTH WITH A HOLLOW-STEM AUGER EQUIPPED WITH A SPLIT SPOON SAMPLER FOR THE SPT N-VALUE TESTS DOWN TO A MAXIMUM DEPTH OF 80 FEET BELOW EXISTING GRADES. ALL BORINGS WILL BE DRILLED TO THE MAXIMUM DEPTH OR AUGER REFUSAL WHICHEVER OCCURS FIRST. THE BORE HOLES DIMENSION WILL BE 3.25 INCHES AND SHALL BE GROUTED UPON COMPLETION.
20 M ST SE   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
P96600069 / SUPPLEMENTAL
   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
G22130990 / SUPPLEMENTAL
   
08/25/14 
SUBWAY / N/A; DAMON ELLIS
SG1400416 / CONSTRUCTION
INSTALLATION OF NON ELECTRIC SIGN 10FT 8IN LENGTH 2IN WIDE 25IN HEIGHT
   
08/27/14 
JOHN GLUSEPPE-RAMCO / CARL LAVENDT; JOHN GLUSEPPE-RAMCO; CARL LAVENDT
E10905761 / SUPPLEMENTAL
100 M ST SE   
08/16/14 
NORTHWOOD INVESTERS LLC / STANLEY HUBBARD; NORTHWOOD INVESTERS LLC; STANLEY HUBBARD
E14516088 / SUPPLEMENTAL
901 M ST SE   
08/14/14 
CARLTON RAY
AH1400642 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
08/14/14 
CARLTON RAY
AH1400641 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
861 NEW JERSEY AVE SE   
08/21/14 
CONSOLIDATED RAIL CORPORATION / ROBERT COLISH
P1407975 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
08/12/14 
NJA ASSOCIATES LLC / COLIN CLARK
B1308085 / CONSTRUCTION
CONSTRUCT A NEW 13 STORY APARTMENT BUILDING WITH THREE BELOW GRADE PARKING LEVELS FIRST FLOOR RETAIL A PRIVATE SWIMMING POOL PROJECTIONS OF BAY WINDOWS 324 UNITS TO INCLUDE MECHANICAL PLUMBING ELECTRICAL AND ELEVATOR WORK.
1200 SOUTH CAPITOL ST SE   
08/26/14 
MR BALLPARK 4 LLC. / MR BALLPARK 4 LLC.; RPS INC.
SB1400375 / CONSTRUCTION
ENVIRONMENTAL SOIL BORINGS FOR DUE DILIGENCE INVESTIGATION. ADVANCE A SERIES OF 10 ENVIRONMENTAL SOIL BORINGS AT THE SUBJECT SITE TO COLLECT SOIL AND GROUNDWATER SAMPLES FOR FIELD SCREENING AND LABORATORY ANALYSIS. THE SOIL BORINGS ARE BEING CONDUCTED AS PART OF A DUE DILIGENCE INVESTIGATION ASSOCIATED WITH A REAL ESTATE TRANSACTION. INVESTIGATION DERIVED WASTE -IDW- WILL BE LABORATORY TESTED AND ...
1230 SOUTH CAPITOL ST SE   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / RAYMOND SCIANNELLA
E1408379 / SUPPLEMENTAL
   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / CHRIS WING
B1410888 / CONSTRUCTION
INTERIOR ALTERATION TO EXISTING SELF STORAGE BUILDING TO REPLACE FIRE ALARM SYSTEM.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.