 Sliding from Before to After

At Monday's ANC 6D meeting, Bryon Johnston of the 11th Street Bridges Project gave a presentation on the rebuilding of the bridges, including an overview of the design and its main features as well as an update on the construction progress. He was nice enough to pass along the slides, which may not mean quite as much without his narration but are still helpful for people who haven't been following along through the process.
A few parts of the new design on the Near Southeast side of the project are worth (re-)pointing out, if you can make it through my torrent of descriptions:
* The "freeway" traffic and the "local" traffic will now be separated, with four lanes inbound and four lanes outbound on the freeway/upriver bridge and two lanes inbound/outbound on the "local"/downriver bridge (which Johnston was referring to as "Local 11th Street" because 11th will now feel like a street that crosses a river), as shown on slide 10.
* The local bridge will allow easier access between Near Southeast and Anacostia, for not only cars but pedestrians and bicycles, as well as streetcars when the routes are expanded. As part of this, 11th Street south of M is going to become two-way, and there will be bike lanes in both directions on 11th north of the bridge. (Slide 9)
* Another feature that appears to be coming together for pedestrians and bicyclists is creating two overlooks that jut out above the river on the south side of the local bridge--these would use two of the in-water piers from the current downriver bridge, and you can see them at left and on slide 11.
* One of the big changes for traffic flow for both Near Southeast and Capitol Hill is that there is going to be a new two-lane on-ramp to go westward on the Southeast Freeway toward Virginia at 11th Street, underneath where the current flyover ramps are. (See slide 7.) Folks who have easier access to 11th Street will no longer have to drive along Virginia Avenue and/or 3rd Street to go westbound on the freeway.
But part of this new 11th Street intersection is that traffic coming from Pennsylvania Avenue along the sunken road that currently feeds directly into the freeway will instead be brought up to street level at this new signalized 11th Street intersection and will then drive straight onto the new on-ramp. So there will be some consternation from drivers using this route. (This is also shown on slide 7.)
* To go across the river from Near Southeast on the freeway bridge, for access to DC-295 northbound and I-295 southbound, drivers will have a new ramp on the southeast corner of 11th and M (slide 4). The existing ramp at 8th and Virginia will still be available, too.
* There will still be an exit ramp from the inbound freeway bridge to I Street, just as there is now (slide 4).
* If you look at slide 4 very closely (and/or click on the bird's-eye view at right) and follow the paths off of each bridge, you can see how the freeway bridges coming across the river will have an exit for M Street similar to the current exit, but it deposits drivers at M just west of 12th instead of using 12th itself. It also no longer has the neat little N Street cut-through directly from the ramp that some Navy Yard workers cherish. To get to the Navy Yard, drivers will turn left on M, then left at 11th, and then go to whichever gate they need.
Other information in the slides includes: a graphic showing of the new ramps and accesses on the east side of the bridges at 295 and MLK (slide 12), of which the biggest addition is that you'll now be able to get to and from 295 and the bridges in all directions. There's also recent construction photos (including the first structural steel being laid on the freeway bridge), and information on stormwater management areas, and upcoming traffic impacts (slide 19).
It's expected that the freeway bridge will open about a year from now, with the new local bridge being finished in the winter of 2012/2013. (Dr. Gridlock wrote about recent milestones and upcoming work a few weeks ago.)
If you want to know more, there's my 11th Street Bridges project page, and you can also spend a couple months reading the Environmental Impact Statement to see all the studying they did of potential, um, impacts. There's also this Fact Sheet that they handed out.
Comments (5)
   
 
 More About 11th Street Bridges

JDLand.com Home

Comments

Rick says: (11/10/10 7:06 AM)
JD - link to fact sheet is broken.


JD says: (11/10/10 8:24 AM)
Thanks, fixed.


BillP says: (11/10/10 9:16 AM)
SO excited that the prior stupidity of (1) not being able to get on the SE/SW freeway from 295 South and (2) having to use Penn Ave to go from the SE/SW freeway to 295 North is being corrected.

I know JD has mentioned "odd" placement of freeway signs on 395 and the SE/SW freeway as they pertain to near SE. Has anybody heard if they are going to try to "name" or "number" the stretch of the SE/SW freeway after 395 north departs via tunnel and 295, especially now that these freeways will actually be properly connected in all directions?


Froggie says: (11/11/10 8:43 PM)
Bill: officially, the SE Freeway is I-695. Whether DDOT signs it or not after project completion is anybody's guess. Given current precedent, I expect them to sign it as "TO I-295/DC 295" or "TO I-395".


JD says: (11/11/10 8:46 PM)
695 is so Baltimore. :-)

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

Chaifetz10 on Columnist Walks the: @202 I walked on the bridge today from Dock79 down to Harris Teeter and I didn't...
Ampersand on Two-Year Change in: Last Thursday I biked north on 5th/6th from Navy Yard to Capitol Hill. The south...
202_cyclist on Wednesday Tidbits: Regarding my post above, Cultivate the City is operating this garden. We all mi...

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
16 B/O M ST SE   ROBBERY  09/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/19/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/18/16
1200 B/O 1ST ST SE   ASSAULT WITH A DANGEROUS WEAPON  09/17/16
400 B/O M ST SE   THEFT
Shoplifting
 09/16/16
1100 B/O 5TH ST SE   THEFT
Theft First Degree (all Other Larceny)
 09/06/16
700 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 09/06/16
1200 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/04/16
UNIT B/O I ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/04/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/28/16

Recent Issued Building Permits Archive  
1233 1ST ST SE   
09/16/16 
NA BALLPARK HOTEL LLC / NORTHEAST ELECTRIC; NA BALLPARK HOTEL LLC; HOSSEIN ECONO SIGN INC.
SG1600390 / CONSTRUCTION
To Install four signs: -3 - Channel letters on Raceways -1- Blade Sign
1331 2ND ST SE   
09/19/16 
DC WATER / DC WATER; CORMAN CONSTRUCTION
AH1601056 / CONSTRUCTION
After hour work for structure excavation and support for building permit B1311474 DC Water, Corman Construction 202-863-0052
933 5TH ST SE   
09/12/16 
null / NA NA NA
EHOP16924112 / HOME OCCUPATION
1015 HALF ST SE   
09/14/16 
HALF STREET SE LLC HALF STREET SE LLC / DARIN PASQUALLE; HALF STREET SE LLC HALF STREET SE LLC; DARIN PASQUALLE
E24765056 / SUPPLEMENTAL
   
09/21/16 
HALF STREET SE LLC / 1015 HALF SE LLC; JOHN GIUSEPPE-RAMCO
B1610675 / CONSTRUCTION
Construction of elevator lobby and common corridors on the 7th floor as shown on the electronically submitted mechanical, electrical, fire protection, and arch. dwgs. Interior work only. No structural work involved. approx. 2275 sf.
1210 HALF ST SE   
09/07/16 
HINES GLOBAL REIT 55 M STREET LLC / MATT LOSIGNOR
P1609218 / SUPPLEMENTAL
75 I ST SE   
09/07/16 
99 I ST SE LP / 99 I ST SE LP; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600354 / CONSTRUCTION
We will perform 2 soil borings and 2 CPT cone soundings on the site. The 2 soil borings and 2 CPT soundings will be extended to depths on the order of 90 ft below the existing site grades. The borings and soundings will be perfroemd within the bounds of private property and will be drilled utilizing a 3.25-inch hollow stem, continuous flight augers and generate a 6-inch annulus. After the borings...
82 I ST SE   
09/09/16 
GDVC EYE STREET LLC / MITCH A. PERMUY
E1609957 / SUPPLEMENTAL
88 K ST SE   
09/07/16 
99 I ST SE LP 99 I ST SE LP / 99 I ST SE LP 99 I ST SE LP; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600355 / CONSTRUCTION
We will perform 2 CPT cone soundings on the project site within the bounds of private space. The CPT cones will be extende to a depth of 90 feet below the existing ground surface, utilizing a 4-inch diameter cone and generate a 4-inch annulus. After the soundings are completed they will be backfilled with bentonite slurry which has a consistency of two pounds bentonite powder to one gallon water.
80 M ST SE 400   
09/15/16 
WELLS REIT II 80 M STREET LLC / null
P1609454 / SUPPLEMENTAL
50 M ST SE   
09/15/16 
KCG 50 M LLC / KCG 50 M LLC ENGLEWOOD LLC; TRACIE CLAXTON; CLAXTON
SG1600460 / CONSTRUCTION
2 Wall mounted Signs - Reversed Channel Letter 2 small wall mounted plague
80 M ST SE   
09/09/16 
WELLS REIT II 80 M STREET LLC / PHILIP G DONNELLY
E1609959 / SUPPLEMENTAL
99 M ST SE   
09/16/16 
BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVELOPMENT / BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVEL
AH1601047 / CONSTRUCTION
Place concrete mat foundation slab. Before work hours - 3AM to 7AM on 9 / 19 / 2016 and 9 / 20 / 2016, if weather or jobsite delays prevail. Permit will only be needed / used for 1 of the 2 days. (Per ANC agreement "before hours work on ONE of the following days: either September 17, 19, or 20," & "to begin no earlier than 3:00 am" )
   
09/16/16 
BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVELOPMENT / BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVEL
AH1601048 / CONSTRUCTION
Place concrete at 99 M Street SE for mat foundation slab. Saturday 9 / 17 / 2016 concrete placement from 3AM to 7PM. (Per ANC agreement "before hours work on ONE of the following days: either September 17, 19, or 20," & "to begin no earlier than 3:00 am" )
100 M ST SE 4   
09/09/16 
SQUARE 743 INC / null
P1609322 / SUPPLEMENTAL
100 M ST SE   
09/20/16 
QUARE 743 INC / QUARE 743 INC; QUARE 743 INC; PHILIP HAUHN
E14003252 / SUPPLEMENTAL
202 M ST SE   
09/09/16 
UNITED STATES OF AMERICA / EBONY BROWN DC HUMANITIES AND ARTS COMMISSION
TN1600199 / CONSTRUCTION
SPECIAL EVENT 202 ARTS & MUSIC FESTIVAL 1 SL 250 24 X 32 STAGE
1100 NEW JERSEY AVE SE 845   
09/21/16 
SQUARE 742 LLC SPAULDING & SLYE C/O WC SMITH / SQUARE 742 LLC SPAULDING & SLYE C/O WC SMITH; WILLIAM SNODDY
B1612012 / CONSTRUCTION
Interior Renovation on the 8th Floor on behalf of Maxim Health 5,138 sqft
1100 NEW JERSEY AVE SE   
09/14/16 
SPAULDING AND SLYE SPAULDING AND SLYE / HALEY HUGGINS; SPAULDING AND SLYE SPAULDING AND SLYE; JOHNNY RILING
E39166644 / SUPPLEMENTAL
125 O ST SE   
09/19/16 
DISTRICT OF COLUMBIA / DC WATER HQ; DAVID FONTANA MSC
EX1600110 / CONSTRUCTION
Site grading and demo per erosion control plan only for future new DC Water HQ building under seperate permit.
1244 SOUTH CAPITOL ST SE   
09/19/16 
1244 SOUTH CAPITOL RESIDENTIAL LLC / RONALD C. CAYTON
E1610018 / SUPPLEMENTAL
385 WATER ST SE   
09/15/16 
FC 385 WATER LLC / EDUARDO L. LOPEZ
E1610139 / SUPPLEMENTAL
355 WATER ST SE   
09/14/16 
OLIVIA DARROW RAGNAR EVENTS LLC
TN1600198 / CONSTRUCTION
SPECIAL EVENT RAGNAR RELMAY WASHINGTON DC 2 20 X 20 TENTS 25 10 X 10 TENTS 1 30 X 40 TENT FENCING FOR BEER GARDEN
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.