At Monday's ANC 6D meeting, Bryon Johnston of the 11th Street Bridges Project gave a presentation on the rebuilding of the bridges, including an overview of the design and its main features as well as an update on the construction progress. He was nice enough to pass along the slides, which may not mean quite as much without his narration but are still helpful for people who haven't been following along through the process.
A few parts of the new design on the Near Southeast side of the project are worth (re-)pointing out, if you can make it through my torrent of descriptions:
* The "freeway" traffic and the "local" traffic will now be separated, with four lanes inbound and four lanes outbound on the freeway/upriver bridge and two lanes inbound/outbound on the "local"/downriver bridge (which Johnston was referring to as "Local 11th Street" because 11th will now feel like a street that crosses a river), as shown on slide 10.
* The local bridge will allow easier access between Near Southeast and Anacostia, for not only cars but pedestrians and bicycles, as well as streetcars when the routes are expanded. As part of this, 11th Street south of M is going to become two-way, and there will be bike lanes in both directions on 11th north of the bridge. (Slide 9)
* Another feature that appears to be coming together for pedestrians and bicyclists is creating two overlooks that jut out above the river on the south side of the local bridge--these would use two of the in-water piers from the current downriver bridge, and you can see them at left and on slide 11.
* One of the big changes for traffic flow for both Near Southeast and Capitol Hill is that there is going to be a new two-lane on-ramp to go westward on the Southeast Freeway toward Virginia at 11th Street, underneath where the current flyover ramps are. (See slide 7.) Folks who have easier access to 11th Street will no longer have to drive along Virginia Avenue and/or 3rd Street to go westbound on the freeway.
But part of this new 11th Street intersection is that traffic coming from Pennsylvania Avenue along the sunken road that currently feeds directly into the freeway will instead be brought up to street level at this new signalized 11th Street intersection and will then drive straight onto the new on-ramp. So there will be some consternation from drivers using this route. (This is also shown on slide 7.)
* To go across the river from Near Southeast on the freeway bridge, for access to DC-295 northbound and I-295 southbound, drivers will have a new ramp on the southeast corner of 11th and M (slide 4). The existing ramp at 8th and Virginia will still be available, too.
* There will still be an exit ramp from the inbound freeway bridge to I Street, just as there is now (slide 4).
* If you look at slide 4 very closely (and/or click on the bird's-eye view at right) and follow the paths off of each bridge, you can see how the freeway bridges coming across the river will have an exit for M Street similar to the current exit, but it deposits drivers at M just west of 12th instead of using 12th itself. It also no longer has the neat little N Street cut-through directly from the ramp that some Navy Yard workers cherish. To get to the Navy Yard, drivers will turn left on M, then left at 11th, and then go to whichever gate they need.
Other information in the slides includes: a graphic showing of the new ramps and accesses on the east side of the bridges at 295 and MLK (slide 12), of which the biggest addition is that you'll now be able to get to and from 295 and the bridges in all directions. There's also recent construction photos (including the first structural steel being laid on the freeway bridge), and information on stormwater management areas, and upcoming traffic impacts (slide 19).
It's expected that the freeway bridge will open about a year from now, with the new local bridge being finished in the winter of 2012/2013. (Dr. Gridlock wrote about recent milestones and upcoming work a few weeks ago.)
If you want to know more, there's my 11th Street Bridges project page, and you can also spend a couple months reading the Environmental Impact Statement to see all the studying they did of potential, um, impacts. There's also this Fact Sheet that they handed out.
Comments (5)
   
 
 More About 11th Street Bridges

JDLand.com Home

Comments

Rick says: (11/10/10 7:06 AM)
JD - link to fact sheet is broken.


JD says: (11/10/10 8:24 AM)
Thanks, fixed.


BillP says: (11/10/10 9:16 AM)
SO excited that the prior stupidity of (1) not being able to get on the SE/SW freeway from 295 South and (2) having to use Penn Ave to go from the SE/SW freeway to 295 North is being corrected.

I know JD has mentioned "odd" placement of freeway signs on 395 and the SE/SW freeway as they pertain to near SE. Has anybody heard if they are going to try to "name" or "number" the stretch of the SE/SW freeway after 395 north departs via tunnel and 295, especially now that these freeways will actually be properly connected in all directions?


Froggie says: (11/11/10 8:43 PM)
Bill: officially, the SE Freeway is I-695. Whether DDOT signs it or not after project completion is anybody's guess. Given current precedent, I expect them to sign it as "TO I-295/DC 295" or "TO I-395".


JD says: (11/11/10 8:46 PM)
695 is so Baltimore. :-)

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2015!
 Top News
  
BillP on Scarlet Oak Close: Thanks JD. Glad to hear re Kruba, apparently there was an error on google maps, ...
JES on Scarlet Oak Close: Kruba better not close; I love the sushi at that place.
JD on Scarlet Oak Close: I just checked with Forest City, and they say that Kruba is open for lunch right...
BillP on Buzz Bakery Closing,: This Buzz was a huge disappointment compared to their other locations. I just do...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O 1ST ST SE   THEFT
Theft 2 (Theft F/Building)
 07/25/15
700 B/O L ST SE   ROBBERY
Robbery Snatch Or Pursesnatch
 07/23/15
1000 B/O HALF ST SE   THEFT
2nd Degree
 07/13/15
400 B/O M ST SE   THEFT
Theft 2 (Theft F/Building)
 07/09/15
70 B/O I ST SE   THEFT F/AUTO
Theft From Auto 1
 07/08/15
100 B/O M ST SE   THEFT
2nd Degree
 07/07/15
300 B/O L ST SE   THEFT
2nd Degree
 07/07/15
70 B/O I ST SE   THEFT
Theft 2 (Theft F/Building)
 07/06/15
300 B/O TINGEY ST SE   THEFT
 07/05/15
1200 B/O HALF ST SE   THEFT
 07/03/15
900 B/O M ST SE   THEFT
 07/02/15
1100 B/O 1ST ST SE   THEFT
 06/30/15
500 B/O M ST SE   THEFT F/AUTO
 06/28/15
1000 B/O 1ST ST SE   THEFT
 06/28/15
1100 B/O NEW JERSEY AVE SE   THEFT
 06/28/15

Recent Issued Building Permits Archive  
1200 1ST ST SE   
07/16/15 
FOREST CITY WASHINGTON / W. TEASS / P.NETTELBECK / TEASS/ WA; RAMSEY MEISER
BCIV1500036 / CONSTRUCTION
CONSTRUCTION OF A TEMPORARY PARKING LOT OPEN PARK SPACE. ALL WORK TO BE PERFOMED IN PRIVATE PROPERTY.
   
07/21/15 
DISTRICT OF COLUMBIA / MARK EY FUHRMAN
E1507720 / SUPPLEMENTAL
1233 1ST ST SE   
07/10/15 
MITCH PERMUY / CLINT HOLMES; MITCH PERMUY; MITCH PERMUY
E18733216 / SUPPLEMENTAL
   
07/14/15 
BALLPARK HOTEL LLC BALLPARK HOTEL LLC / MICHAEL GROSE; BALLPARK HOTEL BALLPARK HOTEL LLC; MITCH PERMUY
E45868221 / SUPPLEMENTAL
1277 1ST ST SE   
07/10/15 
MITCH PERMUY / CLINT HOLMES; MITCH PERMUY; MITCH PERMUY
E93589903 / SUPPLEMENTAL
   
07/14/15 
BALLPARK RESIDENTIAL LLC BALLPARK RESIDENTIAL LLC / MICHAEL GROSE; BALLPARK RESIDE BALLPARK RESIDENTIAL LLC; MITCH PERMUY
E26661076 / SUPPLEMENTAL
1331 2ND ST SE   
07/17/15 
CORMAN CONSTRUCTION / PAMELA STRICKLAND
SH1500057 / CONSTRUCTION
SUPPORT OF EXCAVATION FOR DC WATER OWNED SEWER STRUCTURE CSO 009 / 011A
1016 3RD ST SE   
07/15/15 
CARLOS DIAZ / JOSEPH SEMPER; CARLOS DIAZ; JOSEPH SEMPER
E78706918 / SUPPLEMENTAL
   
07/23/15 
ROBIN SANTILLAN / ROBIN SANTILLAN; ROBIN SANTILLAN; CARLOS MONTES
P55998454 / SUPPLEMENTAL
1331 4TH ST SE   
07/13/15 
FC 1331 LLC / OTIS ELEVATOR COMPANY
EN1501337 / SHOP DRAWING
TYPE OF ELEVATOR : ONE (1) TRACTION / STEEL / CENTRAL / VERTICAL TRANSPOTATION LICENSE NUMBER : ELC1300386 ISSUE DATE : 08 / 04 / 2014 EXPIRATION DATE 11-30-2015
   
07/13/15 
FC 1331 LLC / OTIS ELEVATOR COMPANY
EN1501334 / SHOP DRAWING
TYPE OF ELEVATOR : TWO (2) TRACTION / STEEL / CENTRAL / VERTICAL TRANSPOTATION LICENSE NUMBER : ELC1300386 ISSUE DATE : 08 / 04 / 2014 EXPIRATION DATE 11-30-2015
913 5TH ST SE   
07/13/15 
MARGARET LITTLEJOHN
B1509950 / CONSTRUCTION
TUCKPOINTING. SCAFFOLDING TO BE ERECTED.
1000 5TH ST SE   
07/16/15 
DISTRICT OF COLUMBIA / MAURY M. PARKER
M1502393 / SUPPLEMENTAL
   
07/23/15 
DISTRICT OF COLUMBIA / WALTER T JONES
E1507778 / SUPPLEMENTAL
1007 8TH ST SE   
07/23/15 
CALLE OCHO LLC / JERONE SCOTT
P1507675 / SUPPLEMENTAL
901 HALF ST SE   
07/21/15 
BAKER DCLLC / CHRISTINE LONG
AH1500614 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 3AM THRU 9PM
1015 HALF ST SE   
07/09/15 
HALF ST SE LLC / ANDREW ARNTSON; HALF ST SE LLC; ANDREW ARNTSON
P63100436 / SUPPLEMENTAL
1201 HALF ST SE   
07/27/15 
WEST HALF RESIDENTIAL II LLC / ECS MID-ATLANTIC LLC C/O DON SESER
SB1500398 / CONSTRUCTION
WE WILL PERFORM A TOTAL OF THREE SOIL BORINGS ON THE PROPOSED SITE. THE BORINGS WILL BE ADVANCED TO A DEPTH OF 60 TO 100 FEET BELOW EXISTING SITE GRADES AND WILL BE LOCATED WITHIN THE BOUNDS OF THE PRIVATE PROPERTY. THE BORINGS WILL BE DRILLED UTILIZING 3.25-INCH HOLLOW STEM CONTINUOUS FLIGHT AUGERS. THE BORINGS WILL BE PERFORMED UTILIZING AN ATV-MOUNTED DRILL RIG AND WILL GENERATE AN APPROXIMATE ...
1220 HALF ST SE   
07/09/15 
BUFFALO WILD WINGS / X-PEDITERS PLUS INC.
D1500674 / CONSTRUCTION
INTERIOR DEMOLITION ONLY. PER PLANS.
   
07/13/15 
BUFFALO WILD WINGS / ALLIIANCE
TL1500106 / CONSTRUCTION
TENANT LAYOUT FOR A NEW RESTAURANT IN EXISTING BUILDING. THIS SPACE HAS NOT BEEN PREVIOUSLY OCCUPIED. WORK INCLUDES NEW EXTERIOR FINISHES SIDEWALK CAF? PLUMBING ELECTRICAL AND MECHANICAL AS WELL AS INTERIOR WORK. THIRD PARTY REVIEW.
601 L ST SE   
07/15/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / EDUARDO L. LOPEZ
E1507545 / SUPPLEMENTAL
55 M ST SE   
07/15/15 
HINES GLOBAL REIT 55 M STREET LLC / CARL J. SMITH
E1507529 / SUPPLEMENTAL
   
07/27/15 
HINES GLOBAL REIT 55 M STREET LLC / ANTHONY G SAMBURG
E1507875 / SUPPLEMENTAL
99 M ST SE   
07/15/15 
BALLPARK SQUARE 701 LLC / LP CONSULTING SERVICES
SH1400072 / CONSTRUCTION
SHEETING AND SHORING AS PER PLANS FOR NEW OFFICE BUILDING
   
07/15/15 
BALLPARK SQUARE 701 LLC / LP CONSULTING SERVICES
FD1500019 / CONSTRUCTION
FOUNDATION TO GRADE IN PREPARATION FOR CONSTRUCTION OF A NEW MIXED USE BUILDING
100 M ST SE   
07/10/15 
SQUARE 743 INC / JOHN MCDONALD
P1507412 / SUPPLEMENTAL
   
07/10/15 
CDI MARINE / CHIP GIBBS VSC FIRE & SECURITY
B1509942 / CONSTRUCTION
ADD ONE SPRINKLER HEAD
   
07/21/15 
SQUARE 743 INC / JOSE UMANZOR-ALVAREZ; SQUARE 743 INC; ROBERT LAWALL
E99685352 / SUPPLEMENTAL
   
07/21/15 
UNKNOWN UNKNOWN / PATRICK BARRON; UNKNOWN UNKNOWN; ROBIN MALLEY
E65875186 / SUPPLEMENTAL
400 M ST SE   
07/23/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY (LAND) / VERNON A. MONTAGUE
P1507715 / SUPPLEMENTAL
1201 M ST SE   
07/10/15 
WEST HALF 1 LLC /
P1507408 / SUPPLEMENTAL
   
07/10/15 
WEST HALF 1 LLC /
P1507409 / SUPPLEMENTAL
74 N ST SE   
07/23/15 
CAPITOL RIVERFRONT HOTEL LLC / DAVID FONTANA MCKEEVER SERVICES CORP
B1403426 / CONSTRUCTION
CONCRETE PAVEMENT ENTIRELY ON PRIVATE PROPERTY FOR CONSTRUCTION ACCESS TO NEIGHBORING PROPERTY 1265 1ST ST SE.
909 NEW JERSEY AVE SE   
07/17/15 
SCARLET OAK / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1507594 / CONSTRUCTION
TPR. REVISION TO EXISTING PERMIT # TL1500002. VALUE ENGINEERING RESULTING IN CHANGES TO MPE SYSTEMS AND MECHANICAL STRUCTURAL SUPPORT.
1111 NEW JERSEY AVE SE   
07/10/15 
NJA ASSOCIATES LLC /
P1507417 / SUPPLEMENTAL
   
07/16/15 
GALLERY CAPITAL PROP LLC GALLERY CAPITAL PROP LLC / DONALD LAYTON; GALLERY CAPITAL GALLERY CAPITAL PROP LLC; TOM MCGUIRE
E77440335 / SUPPLEMENTAL
1500 SOUTH CAPITOL ST SE   
07/10/15 
TAYLOR SWIFT CONCERT TOUR / JEWEL HANSON
TN1500150 / CONSTRUCTION
SPECIAL EVENT TAYLOR SWIFR CONCERT TOUR 1 MAIN STAGE 180W X 75OH X 60 D ASSEMBLE FRONT OF HOUSE PLATFORM 20'W X 9 H X 17'D ASSEMBLE 2 DELAY TOWERS 20W X 66'H X 24'D
   
07/11/15 
WASHINGTON NATIONALS / JOHN GALT; WASHINGTON NATIONALS; JAY LIVESAY
E53891753 / SUPPLEMENTAL
   
07/15/15 
NONE / JAMES W CONNER
E1507526 / SUPPLEMENTAL
   
07/23/15 
LERNER DC
B1510545 / CONSTRUCTION
REVISION TO PERMIT NUMBER #B1506810 TO ADD EXHAUST HOOD.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




     © Copyright 2015 JD.