The city council's Committee on Finance and Revenue held a hearing last Thursday (Nov. 12) on B18-475, the "Arthur Capper/Carrollsburg Public Revenue Bonds Amendment Act of 2009," which has been introduced to allow the CFO's office to issue $32 million in city-backed bonds to help fund "phase 3" infrastructure improvements at Capper/Carrollsburg. This would be in addition to the $9.5 million in stimulus money that DCHA was awarded by HUD that will allow the phase 2 townhouses at Capitol Quarter to go forward, possibly by the third quarter of 2010 if current financing negotiations with EYA go smoothly.
(Quick background: This infrastructure work would be a combination of underground work on the Second Street blocks around Canal Park, the relocation of the DPW operations at New Jersey and K and demolition of that block, and perhaps the construction of I Street between Second and New Jersey. These projects were originally expected to be funded by the sale of unrated municipal bonds, but the current Economic Difficulties have made those sorts of bonds all but extinct, and additional attempts to secure loans from banks for the money have been fruitless as well. Read this for more details.)
The hearing was pretty straightforward--you can watch it via streaming video, plus I've managed to procure the prepared written testimony of David Cortiella from DCHA if you're more of a reader than a watcher (like me!). The main takeaways:
* The city is intending to sell $32 million in short-term bonds, and will cover the estimated $600,000 a year in costs from funds in an industrial revenue bonds assessment fund held by the Office of the Deputy Mayor for Planning and Economic Development. After three years, when presumably the bond market is a bit healthier and Capper's own PILOT fund has begun to receive payments, long-term bonds will be issued. John Ross of the CFO's office called this "a very clever arrangement."
* Because the council originally approved a $55 million bond offering as part of the original Capper PILOT legislation, the cost of these bonds is already reflected in the city's budget.
* DCHA and the CFO are asking that this bill be approved on an emergency basis at the council's December meeting, so that the bonds could be sold during late December or early January, which is apparently a good bond-selling time of year. (Christmas bonds for everyone!)
* Cortiella mentioned that DCHA is also investigating a change in the tax code that may allow the financing of the 189-unit apartment building planned for the old Capper Seniors site at Seventh and L (Square 882) by the third quarter of 2010.
* Money has already begun to flow into the Capper PILOT thanks to the completed houses in Capitol Quarter, and if the phase 1 and 2 townhouses and Square 882 apartments are finished as currently scheduled, approximately $1.2 million will be flowing to the PILOT fund each year by 2012. (It's the PILOT fund that then pays back the bonds.)
Jack Evans--the only councilmember at the hearing--was receptive to the plans and also to moving the bill as emergency legislation, calling it "a good project" and saying it should "definitely move forward." He also made sure to note that, since the new bonds are being backed with proceeds from the Gallery Place TIF, that the city will be "backing Ward 6 projects with Ward 2 money": "We're always helpful when we can be helpful," he said. He also reminisced that, when he first ran for city council in 1991, Near Southeast was in Ward 2, and that he received all of six votes across the entire precinct in the 13-man primary.
The council's December legislative meeting is scheduled for Dec. 15.
Comments (0)
 
 More About Capper
 All posts: Capper

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Recent Comments:  
Chococar on Tidbits: I see the obstructionists are still trying to block the CSX tunnel. The narrow o...
Edna on Tidbits: Well said, JD, on Jair Lynch. What a bunch of developer nonsense-talk!
JES on Tidbits: Well, last time, we made a bit of a hasty exit..... who knows how the latter rou...
JD on Tidbits: I think that's how it ended up working out last time, that despite all the sturm...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O 10TH ST SE   THEFT F/AUTO /  09/08/14
400 B/O K ST SE   THEFT F/AUTO /  09/08/14
1000 B/O 4TH ST SE   THEFT F/AUTO /  09/05/14
300 B/O M ST SE   ROBBERY /  09/03/14
900 B/O 1ST ST SE   THEFT F/AUTO /  09/03/14
1000 B/O 1ST ST SE   THEFT /  09/03/14
1200 B/O 4TH ST SE   THEFT F/AUTO /  09/02/14
200 B/O M ST SE   THEFT /  09/02/14
300 B/O M ST SE   THEFT /  09/02/14
1100 B/O NEW JERSEY AVE SE   THEFT /  09/01/14
300 B/O K ST SE   THEFT F/AUTO /  08/31/14
1100 B/O 10TH ST SE   THEFT F/AUTO /  08/31/14
300 B/O I ST SE   MOTOR VEHICLE THEFT /  08/30/14
1400 B/O 1ST ST SE   THEFT /  08/29/14
300 B/O WATER ST SE   MOTOR VEHICLE THEFT /  08/27/14
3RD ST SE AND WATER ST SE   THEFT F/AUTO /  08/26/14
100 B/O K ST SE   THEFT F/AUTO /  08/25/14
400 B/O M ST SE   MOTOR VEHICLE THEFT /  08/23/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
09/03/14 
TOLL DC LP / MILLENNIUM POOL
SP1400019 / CONSTRUCTION
INSTALL STAINLESS STEEL POOL ON ROOFTOP OF THE 13-FLOOR APARTMENT BUILDING.
1200 1ST ST SE   
09/05/14 
UNITED STATES OF AMERICA / FVI2020
EX1400033 / CONSTRUCTION
EXCAVATION SITE GRADING ONLY
1020 3RD ST SE   
09/03/14 
MAYIAK LLC / SMK AND ASSOCIATES LLC
B1411577 / CONSTRUCTION
REPAIR OR REPLACE IN KIND KITCHEN CABINETS TILE ON KITCHEN FLOORS. REPLACE FLOORS THROUGHOUT REPLACE BATHROOM VANITY TOILET TUB . PAINT EXTERIOR WINDOW LEDGES AND FRONT PORCH
1212 4TH ST SE   
09/09/14 
FC 1212 LLC /
FB1400131 / SUPPLEMENTAL
   
09/09/14 
FC 1212 LLC / WENDELL D. NIXON
M1403160 / SUPPLEMENTAL
1331 4TH ST SE   
09/09/14 
UNITED STATES OF AMERICA /
P1407907 / SUPPLEMENTAL
1103 9TH ST SE   
09/16/14 
ICP PARTNERS POTOMAC 810 LLC / FRANKLIN T GAINES
P1408621 / SUPPLEMENTAL
1220 12TH ST SE   
09/18/14 
WASHINGTON GAS LIGHT CO / GREGORY E LIGON
E1409179 / SUPPLEMENTAL
   
09/19/14 
WASHINGTON GAS LIGHT CO / JAMES C. GYURAS
E1409204 / SUPPLEMENTAL
   
09/19/14 
WASHINGTON GAS LIGHT CO / JAMES C. GYURAS
E1409203 / SUPPLEMENTAL
1200 13TH ST SE   
09/03/14 
WASHINGTON GAS LIGHT COMPANY / CHRIS WILLETT URS CORPORATION
SB1400412 / CONSTRUCTION
DCCR PROPOSES TO DRILL TWO GEOTECHNICAL BOARINGS MS-MW-02D & MS-MW-02S LOCATED AT 1200 13TH ST SE. BOTH BOARINGS WILL BE 6 INCHES IN DIAMETER 02D WILL BE 36 FEET DEEP WIOTH A 10 FOOT SCREENED INTERVAL STARTING AT 25 FEET DEEP AND 02S WILL BE 23 FEET DEEP WITH A 10 FOOT SCREENED INTERVAL STARTING AT 13 FEET DEEP. BOTH WILL BE DIRLLED WITH HOLLOW STEM AUGER. NO PERMANENT CASING WILL BE INSTALLED. SE...
   
09/03/14 
WASHINGTON GAS LIGHT COMPANY / CHRIS WILLETT URS CORPORATION
SB1400413 / CONSTRUCTION
DCCR PROPOSES TO DRILL ONE GEOTECHNICAL BORING MS-MW 01 LOCATED IN 1200 13TH ST SE. THE BORING WILL BE 6 INCHES IN DIAMETER AND 200 FEET BGS WITH A SCREENED INTERVAL FROM 135 TO 195 FEET BGS DRILLED BY MUD ROTARY. PERMANENT STELL CASING WILL INSTALLED AND BE SOCKETED 10 FEET INTO P / A AND GROUTED BEFORE DRILLING INTO THE PTX. MSDS FOR DRILLING MUD ADDITIVES ATTACHED. SEE IDW MANAGEMENT PLAN AND A...
1015 HALF ST SE   
09/04/14 
HALF ST SE LLC /
P1408319 / SUPPLEMENTAL
601 L ST SE   
09/02/14 
V ? V CONSTRUCTION / STEPHANIE DELCA TRAFFIC ENGINEERING SERVCIES LLC
TC1400023 / CONSTRUCTION
TO ERECT TOWER CRANE AS PER PLANS.
   
09/16/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / EDUARDO L. LOPEZ
E1409105 / SUPPLEMENTAL
   
09/18/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / RICHARD V CAREY
P1408678 / SUPPLEMENTAL
20 M ST SE   
09/08/14 
SOUTHEAST REALTY LLC / WESLEY R. DAVIS
E1408797 / SUPPLEMENTAL
   
09/19/14 
SOUTHEAST REALTY LLC / MATT LOSIGNOR
P1408704 / SUPPLEMENTAL
   
09/19/14 
SOUTHEAST REALTY LLC / MATT LOSIGNOR
P1408703 / SUPPLEMENTAL
55 M ST SE   
09/11/14 
HINES GLOBAL REIT 55 M STREET LLC / DANIEL O WHITE
E1408953 / SUPPLEMENTAL
100 M ST SE   
09/15/14 
SQUARE 743 INC. / SAM HOLLEN RAMCO OF DC INC.
TL1400150 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 6TH FLOOR OFFICE SPACE. PARTITIONS FURNITURE MEP AND LIFE SAFETY. REGUS 2429
   
09/20/14 
SQUARE 743 INC SQUARE 743 INC / KATE MITCHELL; SQUARE 743 INC SQUARE 743 INC; ROBERT HUNTER
AR53284155 / SUPPLEMENTAL
901 M ST SE   
09/12/14 
CARLTON RAY
AH1400687 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
09/12/14 
CARLTON RAY
AH1400686 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
0 N ST SE   
09/10/14 
SNALLYGASTER / ERIK BERGMAN
TN1400195 / CONSTRUCTION
SPECIAL EVENT SNALLYGASTER 1 10X40 TENT 1 20X90 TENT 2 20X160 TENT 1 30X15 STAGE TENT TEMPORARY GENERATOR
   
09/10/14 
DISTRICT OF COLUMBIA / JAMES A. WILLIAMS
E1408914 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
09/17/14 
NEW JERSEY AT H LLC / COLIN CLARK
B1408553 / CONSTRUCTION
CONSTRUCTION OF A 11 STORY 336 UNIT APARTMENT BUILDING WITH FIRST FLOOR RETAIL AND THREE BELOW GRADE LEVELS FOR PARKING GARAGE PER BZA # 18619 GRANTED ON 9 / 24 / 13 WITH CONDITION: SCREENING OF THE PARKING ADJACENT TO H ST.--- SPECIFICALLY SHEETS 6 AND 7 OF EXHIBIT 23 - PLANS TO INCLUDE MECHANICAL PLUMBING AND ELECTRICAL WORK.
25 POTOMAC AVE SE   
09/09/14 
GRIFFIN STEPHEN
PC60869040 / POST CARD
INSTALLATION OF 1 TEMPORARY CONSTRUCTION TRAILER ON PRIVATE PROPERTY.
1500 SOUTH CAPITOL ST SE   
09/09/14 
COMCAST CABLE / MICHAEL SONESEN
AH1400678 / CONSTRUCTION
PLACING INNERDUCT IN EXISITING VERIZON MANHOLES SEPTEMEBR 5TH 2014 - OCTOBER 5TH 2014 EVENINGS ? SATRUDAYS 7PM TO 2AM
300 TINGEY ST SE   
09/11/14 
FC BOILERMAKER LLC / CHRIS WING
B1407179 / CONSTRUCTION
INTERIOR ALTERATION FOR NEW UNLEASHED BY PETCO STORE.
   
09/05/14 
FC BOILERMAKER LLC
B1411671 / CONSTRUCTION
INSTALL FIRE SUPPRESSION SYSTEM TO EXHAUST HOOD.
   
09/13/14 
FC BOILERMAKER LIC FC BOILERMAKER LIC / DENNIS STUBBS; FC BOILERMAKER FC BOILERMAKER LIC; DENNIS STUBBS
P24303627 / SUPPLEMENTAL
   
09/18/14 
FC BOILERMAKER LLC /
P1408685 / SUPPLEMENTAL
   
09/18/14 
CHRIS WING / SHANDI COBB; CHRIS WING; CHARLES CLYNES
AR65033933 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.