January 23, 2007
May 18, 2014
3rd at I, Looking West-Northwest (see more)

This morning Mayor Fenty held a press conference at Nationals Park with various city officials to highlight tomorrow's Anacostia Waterfront Information Fair, and also talk up the recent progress and near-term next steps for the more than $8 billion worth of economic development, transportation, and infrastructure projects in the pipeline along the Anacostia River (not only in Near Southeast, but from the Southwest Waterfront all the way up past RFK).
Having sworn off taking any more photos of The Mayor at the Microphone (unless he shows up in a Hawaiian shirt and swimtrunks or something), I decided to record the 20-minute event instead, so that the five or six of you interested in hearing the remarks can do so. (It's a 2.6-mb MP3 file; the first few seconds are rough, but then it settles in.)
If you listen, you'll hear how the mayor managed to cajole the notoriously camera-shy Stan Kasten into saying a few words about what's happening along the river and in the neighborhood from the point of view of the area's largest tenant. Deputy Mayor Neil Albert, DDOT Director Frank Seales, Office of Planning head Harriet Tregoning, and the director of the city's Office of the Environment George Hawkins spoke as well. There was some discussion throughout (and especially at the end) about how the slowing economy might be impacting both the city's plans and developers' projects, but the mayor remains optimistic.
The press release from the mayor's office sums up the main points of today's event, but here's the Near Southeast-specific highlights from both the remarks and some other chatter of the day. First up, news of the three big parks:
The city "will break ground at Diamond Teague Park by the end of 2008." (And the guide for tomorrow's fair says that the park will be completed in spring 2009, which is the same date we've been hearing for a while.) The mayor also touted the operating agreement with Forest City Washington to build and maintain the $42 million, 5-acre Park at the Yards (but you knew about this already), as well as the the agreement with the Canal Park Development Corp. to build the $13.1 million, three-block-long park. (No mention of school buses.)
Then there's the bridges: Reconstruction of the 11th Street Bridges is scheduled to begin in mid-2009. (The shortlist of firms vying for the design-build contract was announced a few weeks ago.) Whether we actually see heavy equipment moving in mid-2009, or whether this just marks the first part of the design-build project is not quite clear. I was also told that the contract to demolish the flyover ramps to and from RFK could be completed soon, and that demolition would happen not long after the contract is signed.
Plus, the final Environmental Impact Statement for South Capitol Street and the Douglass Bridge is expected in spring 2009; that's when we'll hear which of the four bridge designs has been chosen.
As for the river itself, the city has started real-time water quality monitoring, updated automatically online 24 hours a day. There's also now the Anacostia 2032 Plan "to make the Anacostia River boatable, swimmable, and fishable in 25 years." And a Green Summer Jobs Corps was created earlier this year to "engage youth in the cleaning and greening of District neighborhoods and parks and to introduce them to green-collar job opportunities."
Finally, a planning process is underway to revamp Boathouse Row, the stretch of boat clubs along the Anacostia between 11th Street and Pennsylvania Avenue. (I took a bunch of photos near the boathouses a few months back, and have been lazy about ever getting them posted, though you can see a few boathouse-free shots of the environs here and here.)
There's more about projects elsewhere along the Anacostia, but other bloggers get to cover those. Will update this post if there's any media coverage from today's event, and will have a fresh post on Saturday after the fair. I imagine I'll Twitter a bit from those festivities (like I did from today's); remember that if you aren't a Twitter-er, you can read my tweets on the JDLand homepage--check 'em out frequently, because I do sometimes post news there first, before I write full blog entries.
SATURDAY FAIR UPDATE: They're now going to be providing free shuttle bus service from the New Jersey & M Metro entrance to/from the ballpark, from 12:30 pm to 5:15 pm. (After they heard somewhere that the Half and M subway entrance is going to be closed on Saturday.)
Comments (0)
 
 More About Nationals Park

JDLand.com Home

Comments

Jay says: (11/14/08 3:14 PM)
I know some people aren't big fans of Nationals Park, but there it is, playing host today and tomorrow and other events. Without it being there, not sure these type announcements would mean as much. I mean, if it wasn't there, where would they have held today's event with the same amount of cachet?

Just saying..




Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Tell readers about your apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
jmauro on Southeast Blvd.: None of the new options will work. They all ignore the fact that the CSX railw...
Packinblackandred on Southeast Blvd.: Awesome news, glad to hear it!
JD on Southeast Blvd.: (Laziness note: I appear to have successfully made it through my latest surgery,...
E. Masquinongy on Southeast Blvd.: I wonder about the wisdom of DDOT administering this development. This is an imm...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
M ST SE AND HALF ST SE   ROBBERY /  08/17/14
800 B/O VIRGINIA AVE SE   THEFT F/AUTO /  08/17/14
M ST SE AND 5TH ST SE   THEFT F/AUTO /  08/15/14
1400 B/O 1ST ST SE   THEFT F/AUTO /  08/14/14
1000 B/O 1ST ST SE   BURGLARY /  08/12/14
800 B/O L ST SE   THEFT F/AUTO /  08/11/14
HALF ST SE AND L ST SE   THEFT F/AUTO /  08/11/14
1000 B/O NEW JERSEY AVE SE   THEFT /  08/07/14
1100 B/O 10TH ST SE   THEFT /  08/07/14
70 B/O I ST SE   THEFT /  08/02/14
100 B/O K ST SE   THEFT F/AUTO /  08/01/14
200 B/O L ST SE   THEFT F/AUTO /  07/30/14
L ST SE AND 2ND ST SE   THEFT F/AUTO /  07/30/14
70 B/O I ST SE   MOTOR VEHICLE THEFT /  07/29/14
70 B/O I ST SE   THEFT /  07/29/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1026 3RD ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
09/04/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
410 M ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 07/11/14
to
09/08/14
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
08/11/14 
TOLL DC LP / ALBERT J. PEARCE
FB1400108 / SUPPLEMENTAL
1259 1ST ST SE   
08/11/14 
CAPITAL RIVERFRONT HOTEL LLC / CAPITAL RIVERFR HOTEL LLC
AH1400636 / CONSTRUCTION
AFTER HOURS FOR PERMIT NUMBER B1401471 FOR 8 / 12 THROUGH 9 / 11 FROM 5AM TO 7PM MONDAY THROUGH SATURDAY.
1201 4TH ST SE   
08/12/14 
JBG/FEDERAL CENTER LIC / JIM CALABRESE
AN1400129 / CONSTRUCTION
PLEASE EXTEND PERMIT AN1300174 THIS IS THE FIRST EXTENSION AND PERMIT WILL BE VALID UNTIL 1 / 31 / 2015.
1212 4TH ST SE   
08/25/14 
FC 1212 LLC / MARK E. RESNICK
E1408462 / SUPPLEMENTAL
1331 4TH ST SE   
08/14/14 
F. C. 1331 LLC / FVI 2020
B1402843 / CONSTRUCTION
CONSTRUCTION OF A BRAND NEW 11 STORY BUILDING. THE BUILDING IN TOTAL IS 350 000 SQ FT. ADDING 327 RESIDENTIAL RENTAL UNITS 20 000 SQ FT. IN COMMERCIAL SPACE AND 3 BELOW GRADE PARKING LEVELS.
   
08/15/14 
CLARK CONCRETE
AH1400650 / CONSTRUCTION
AFTER HOURS TO POUR CONCRETE ON JOBSITE FROM 7AM TO 7PM FROM SUNDAY TO SATURDAY 8 / 15 / 2014 TO 11 / 15 / 2014
1000 5TH ST SE   
08/13/14 
UNITED STATES OF AMERICA /
FD1400132 / CONSTRUCTION
NEW FOUNDATION TO GRADE PERMIT FOR NEW COMMUNITY CENTER INCLUDING UTILITIES. REVISION TO FD1400029 TO REVISE STRUCTURAL DETAILS OF COLUMS.
   
08/20/14 
UNITED STATES OF AMERICA / BRUCE G. PICKETT
E1408304 / SUPPLEMENTAL
1220 12TH ST SE   
08/27/14 
FAIRBANKS MORSE ENGINE / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1411219 / CONSTRUCTION
INTERIOR ONLY NON-STRUCTURAL ALTERATION TO EXISTING OFFICE SPACE. WORK INCLUDS MINOR PARTITION CHANGES AND THE ASSOCIATED HVAC AND ELECTRICAL ALTERATIONS.
1015 HALF ST SE   
08/12/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
TL1400162 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 1ST FLOOR PERFORMANCE STUDIO SPACE AND OFFICE SPACE. PARTITIONS FURNITURE MECHANICAL ELECTRICAL AND LIFE SAFETY. CBS
   
08/15/14 
HALF ST SE LLC / ROBERT L HUNTER
M1402951 / SUPPLEMENTAL
   
08/16/14 
SAM HOLLEN / DONALD VEALS; SAM HOLLEN; DONALD VEALS
E83010192 / SUPPLEMENTAL
200 I ST SE   
08/08/14 
DANIEL RILEY / OMAR BIAGAS; DANIEL RILEY; JOHN BIAGAS
E47247428 / SUPPLEMENTAL
41 L ST SE   
08/20/14 
WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY (WMATA) / SAMIR ALQUTRI - GEOTECHNICAL SOLUTIONS INC.
SB1400402 / CONSTRUCTION
GSI PLANS TO DRILL 4 SOIL TEST BORINGS TO CONFIRM SOIL STRENGTH WITH A HOLLOW-STEM AUGER EQUIPPED WITH A SPLIT SPOON SAMPLER FOR THE SPT N-VALUE TESTS DOWN TO A MAXIMUM DEPTH OF 80 FEET BELOW EXISTING GRADES. ALL BORINGS WILL BE DRILLED TO THE MAXIMUM DEPTH OR AUGER REFUSAL WHICHEVER OCCURS FIRST. THE BORE HOLES DIMENSION WILL BE 3.25 INCHES AND SHALL BE GROUTED UPON COMPLETION.
20 M ST SE   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
P96600069 / SUPPLEMENTAL
   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
G22130990 / SUPPLEMENTAL
   
08/25/14 
SUBWAY / N/A; DAMON ELLIS
SG1400416 / CONSTRUCTION
INSTALLATION OF NON ELECTRIC SIGN 10FT 8IN LENGTH 2IN WIDE 25IN HEIGHT
   
08/27/14 
JOHN GLUSEPPE-RAMCO / CARL LAVENDT; JOHN GLUSEPPE-RAMCO; CARL LAVENDT
E10905761 / SUPPLEMENTAL
100 M ST SE   
08/16/14 
NORTHWOOD INVESTERS LLC / STANLEY HUBBARD; NORTHWOOD INVESTERS LLC; STANLEY HUBBARD
E14516088 / SUPPLEMENTAL
901 M ST SE   
08/14/14 
CARLTON RAY
AH1400642 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
08/14/14 
CARLTON RAY
AH1400641 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
861 NEW JERSEY AVE SE   
08/21/14 
CONSOLIDATED RAIL CORPORATION / ROBERT COLISH
P1407975 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
08/12/14 
NJA ASSOCIATES LLC / COLIN CLARK
B1308085 / CONSTRUCTION
CONSTRUCT A NEW 13 STORY APARTMENT BUILDING WITH THREE BELOW GRADE PARKING LEVELS FIRST FLOOR RETAIL A PRIVATE SWIMMING POOL PROJECTIONS OF BAY WINDOWS 324 UNITS TO INCLUDE MECHANICAL PLUMBING ELECTRICAL AND ELEVATOR WORK.
1200 SOUTH CAPITOL ST SE   
08/26/14 
MR BALLPARK 4 LLC. / MR BALLPARK 4 LLC.; RPS INC.
SB1400375 / CONSTRUCTION
ENVIRONMENTAL SOIL BORINGS FOR DUE DILIGENCE INVESTIGATION. ADVANCE A SERIES OF 10 ENVIRONMENTAL SOIL BORINGS AT THE SUBJECT SITE TO COLLECT SOIL AND GROUNDWATER SAMPLES FOR FIELD SCREENING AND LABORATORY ANALYSIS. THE SOIL BORINGS ARE BEING CONDUCTED AS PART OF A DUE DILIGENCE INVESTIGATION ASSOCIATED WITH A REAL ESTATE TRANSACTION. INVESTIGATION DERIVED WASTE -IDW- WILL BE LABORATORY TESTED AND ...
1230 SOUTH CAPITOL ST SE   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / RAYMOND SCIANNELLA
E1408379 / SUPPLEMENTAL
   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / CHRIS WING
B1410888 / CONSTRUCTION
INTERIOR ALTERATION TO EXISTING SELF STORAGE BUILDING TO REPLACE FIRE ALARM SYSTEM.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.