You may have noticed that work seemed to stop a few weeks ago on the new townhouses at Capitol Quarter. Here is the official statement given to me by EYA:
"Several weeks ago we noticed several locations with cracking in the foundations at Capitol Quarter. We immediately put construction on hold, and contacted several geotechnical engineering firms to analyze the situation. While several repair solutions were suggested, we felt the wisest decision to ensure the integrity of the homes was to change foundation designs, and start over with a new enhanced design. Even though this meant removing the framing on several started homes, we feel this solution provides the future residents the confidence of owning structurally sound homes."
Homeowners in these first blocks along L are being told to expect their move-in dates to slide 30 to 60 days as a result of the need to demolish the existing foundations and frames and start construction over again.
Comments (9)
   
 
 More About Capitol Quarter
 All posts: Capper, Capitol Quarter

JDLand.com Home

Comments

Michael says: (10/13/08 7:06 PM)
Why did this happen? Is this normal?


res says: (10/13/08 7:41 PM)
It's obviously not normal. It may have had something to do with the large amount of rain that occurred around the time the foundations were originally put in or something to do with the mix of the mortar. Hopefully it doesn't have anything to do with construction financing.


bruce says: (10/14/08 8:06 AM)
All i know is that it is better to be safe than sorry. I've been waiting so long that i would rather they do it right. Rather than do "repairs", EYA has elected to re-do the foundations.
Not the end of the world I guess.
it's the better solution.


goober says: (10/14/08 8:38 AM)
Gee, another delay with Capitol Quarter. There's a shock! When we gave them money in October, 2006 we were given a move-in date of April 2008. Now we're being told September 2009. This is the third time they've changed the completion date.


CJ says: (10/14/08 3:49 PM)
I applaud EYA for not just patching up the foundation. This seems the responsible way to do it - especially as folks have been waiting.


Jay says: (10/14/08 4:05 PM)
I think the real question should be why did this happen in the first place? Was this a simple miscalculation of how foundation design? Was EYA trying to get away with doing a "cheap" foundation job? Hopefully they end up building the quality product that they advertised.


BBC says: (10/14/08 11:05 PM)
I am glad that EYA is redoing these foundations. It shows that they are truly a quality builder. I think that many other companies would have just patched the foundations and continued. EYA has built many communities. I would imagine that they know how to build foundations. There must be something unexpected going on with the soil in this area. I am truly happy they they stepped up to the plate and are biting the bullet to make things right.

The delay is not really a big deal because this area is not built out yet. Thus, nobody here is really missing out on much.


RES says: (10/17/08 4:49 PM)
I'm impressed that they told the homeowners and took this action - It's the right thing to do, but they were light on the details.

So what's the first delivery supposed to be now? May? Has anyone heard of contract owners getting spooked and canceling or has everyone that had a reservation converted to contract? I'm bullish on the project (obviously, since I purchased), but you never know...


HawkEya says: (10/26/08 2:27 PM)
If I were purchasing one of these homes, I would watch this builder very carefully. I walk by the job site every day; I believe EYA put the cinder block foundations directly on top of gravel, not a poured concrete beam, which is recommended. EYA was obviously trying to cut corners. This was not a minor error, and EYA wasn't "stepping up to the plate" by demolishing the homes and foundations. They were attempting to avoid a full-fledged disaster. Again, if I were purchasing one of these homes, I would do so with great care -- hire an independent inspector to ensure that EYA has built the home you contracted to buy.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News
  

RMP on DDOT Unveils Planned: I support this change. I like the current Ciculator route in theory, but it take...
NavyYardGuy on Peet's Coffee Coming: @ JD..was that a hint..like Compass coffee is coming to Navy Yard too?
Ampersand on DDOT Unveils Planned: aaaaaaand now that I've posted that I see exactly such a route would also be cre...
JD on DDOT Unveils Planned: (That includes Eastern Market.)
JD on DDOT Unveils Planned: "Circulator service between Union Station, Barracks Row, and the Washington Navy...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
900 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/15/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/12/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/11/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/11/17
1100 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/08/17
900 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/08/17
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 12/03/17
300 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/02/17
500 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 12/02/17
1100 5TH ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/01/17
400 B/O M ST SE   THEFT
Shoplifting
 11/29/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/28/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/27/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/24/17
1200 B/O NEW JERSEY AVE SE   THEFT
Theft First Degree (all Other Larceny)
 11/24/17
400 B/O M ST SE   THEFT
Shoplifting
 11/22/17
100 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 11/19/17
70 B/O I ST SE   BURGLARY
Burglary Two
 11/16/17

Recent Issued Building Permits Archive  
1100 2ND PL SE   
12/13/17 
BAKER DC / CHRISTINE LONG
AH1800290 / CONSTRUCTION
An after hours permit is respectfully requested from 5am thru 9pm daily
1331 2ND ST SE   
11/29/17 
DC WATER / DAVE LEVINE
AH1800282 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water. Corman Construction 301-343-5417
2 I ST SE   
11/29/17 
MCDONALDS CORPORATION / MICHAEL ERIC CAMPBELL
M1800603 / SUPPLEMENTAL
   
11/29/17 
MCDONALDS CORPORATION / DANIEL P. THOMPSON
P1801598 / SUPPLEMENTAL
   
12/01/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800280 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
   
12/14/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800324 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
70 I ST SE   
11/28/17 
DISTRICT OF COLUMBIA / OTIS ELEVATOR COMPANY; OTIS ELEVATOR COMPANY
ER1800447 / SHOP DRAWING
BODY OF WORK: Replace machine and recable elevator # 1.
337 L ST SE   
12/06/17 
JENNIFER LANCASTER / null
E1802092 / SUPPLEMENTAL
347 L ST SE   
12/07/17 
THOMAS PAQUIN / null
E1802129 / SUPPLEMENTAL
   
12/14/17 
THOMAS PAQUIN / BJORN FALK
SOL1800006 / CONSTRUCTION
Installation of a 5.4kW solar PV system. Parapet mounted, 15 panels
555 L ST SE   
11/27/17 
UNITED STATES OF AMERICA / CLIFFORD DIXON
B1714199 / CONSTRUCTION
DGS PROJECT This permit is for interior work only.SWING SPACE FOR WARD 6 CLINIC TO EXISTING VACANT JOY EVANS RECREATION CENTER TEMPORARILY FOR 12 TO 18 MONTHS
515 M ST SE   
12/11/17 
null / BLUE STAR DESIGN BUILD
BP1801085 / POST CARD
300 M ST SE STE# 402 20024   
12/13/17 
FEDERAL CENTER LP / null
P1802065 / SUPPLEMENTAL
100 M ST SE   
12/05/17 
CRANE SERVICE CO / CHRISTINE LONG
AH1800304 / CONSTRUCTION
An after hours permit is respectfully requested from 7AM Saturday thru 7PM Sunday
110 M ST SE   
12/13/17 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / THUY LE
TL1700234 / CONSTRUCTION
Interior alteration for new tenant, restaurant with 37 seats, 49 in occupancy load.
410 M ST SE   
11/20/17 
DC HOUSING / COLLINS ELEVATOR SERVICES INC.; COLLINS ELEVATOR SERVICES INC.
ER1800511 / SHOP DRAWING
BODY OF WORK: 1. Remove old piston. Replace & install jack on car # 1.
861 NEW JERSEY AVE SE   
12/14/17 
CSX TRANSPORTATION INC. / NA CSX TRANSPORTATION, INC.
AH1800330 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1100 NEW JERSEY AVE SE 3RD FL   
11/22/17 
SQUARE 742 LLC / null
P1801490 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
11/20/17 
SQUARE 742 LLC / null
P1801410 / SUPPLEMENTAL
   
12/06/17 
SQUARE 742 LLC / DOMINIC E TOTARO
M1800664 / SUPPLEMENTAL
   
12/08/17 
SQUARE 742 LLC / SAM HOLLEN
B1801219 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MEP, LIFE SAFETY AND STRUCTURAL HANGING MOVABLE PARTITION. 25,226 SQUARE FEET. ALION SCIENCE AND TECHNOLOGY **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2017 JD.